Faulkner Concrete Pipe Co. v. United States F. & G. Co.

Citations

  • 218 So. 2d 1

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that although contractor was liable to supplier for attorney’s fees pursuant to contract between them, supplier could not recover attorney’s fees from surety where neither provided for in bond nor allowable by statute

Source: CourtListener parenthetical corpus (CC0).

Judges: Rodgers

Read full opinion on CourtListener