Skip to main content
· 3/9/1984

Executive Construction, Inc. v. Geduldig

Citations

  • 317 S.E.2d 564
  • 170 Ga. App. 560
  • 1984 Ga. App. LEXIS 1946

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • damages arising naturally out of breach of contract and those contemplated by the parties when the contract made are recoverable as consequential damages
  • claim letters at issue were not required under a contract between the parties

Source: CourtListener parenthetical corpus (CC0).

Judges: Shulman, McMurray, Birdsong