Skip to main content
· 9/19/1994

Erb Lumber Co. v. Homeowner Construction Lien Recovery Fund

Citations

  • 522 N.W.2d 917
  • 206 Mich. App. 716

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • “[S]ince the contract terms established the cost of the materials, and profit and overhead were included, plaintiff is entitled to recover the time-price differential as well.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Murphy, Kelly, Buhl

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.