Skip to main content
· 4/14/1917

Dietrich v. City of Seattle

Citations

  • 95 Wash. 654
  • 164 P. 251
  • 1917 Wash. LEXIS 865

Syllabus

<p>Municipal Cobpobations — Improvements—Contracts—Construction. Where a city had failed to acquire the necessary right to enter upon private property, recovery of damages by reason of the enforced temporary suspension of work under a city contract, which was afterwards completed, is precluded by the terms of a contract which provided the method of adjustment if the improvement could not be completed by reason of an injunction, for a waiver of damages by the contractor in such case, and a resumption of work if the court proceedings allowed it, in which case no extra payment was to be allowed or charged.</p>

Judges: Fullerton

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.