Skip to main content
· 4/24/1962

Devine v. Grace Construction and Supply Co.

Citations

  • 181 N.E.2d 862
  • 243 Ind. 98
  • 1962 Ind. LEXIS 136

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • plaintiff swerved around three or more blockades and drove 50-55 miles per hour in a 15 mile per hour road construction zone
  • plaintiff swerved around three or more blockades and drove 50-55 miles per hour in a 15 mile per hour road construction zone

Source: CourtListener parenthetical corpus (CC0).

Judges: Bobbitt, Achor, Arterburn, Jackson, Landis

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).