D. Federico Co., Inc. v. Commonwealth

Citations

  • 415 N.E.2d 855
  • 11 Mass. App. Ct. 248
  • 1981 Mass. App. LEXIS 897

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • where no timely claim filed, “any right the plaintiff may have had to extra compensation was not perfected, and [thus] barred”
  • no evidence that defendant “concealed the existence of bor-ings reports or soil analyses which would have revealed the subsoil conditions or shown the unreliability of the estimates”
  • where contract explicitly stated that accuracy of engineer’s estimates was not guaranteed, contractor could not recover from owner for increased costs incurred because of the underestimation of the amount of excavation and replacement fill required

Source: CourtListener parenthetical corpus (CC0).

Judges: Armstrong, Rose, Kass

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.