Skip to main content
· 2/3/1970

Cote v. Bloomfield

Citations

  • 262 A.2d 467
  • 128 Vt. 306
  • 1970 Vt. LEXIS 226

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • obligation of owner under mechanic's lien was only as to sum of money due under general contract after offsets for failure of general to complete work
  • obligation of owner under mechanic’s lien was only as to sum of money due under general contract after offsets for failure of general to complete work

Source: CourtListener parenthetical corpus (CC0).

Judges: Barney, Holden, Key, Shangraw, Smith

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.