Skip to main content
· 6/12/1901

Congdon & Henry Hardware Co. v. Grand Island & W. C. R.

Citations

  • 14 S.D. 575
  • 86 N.W. 633
  • 1901 S.D. LEXIS 61

Syllabus

<p>Where plaintiff, who furnishes supplies to a railroad subcontractor to be used in the construction of the road, fails to file his statement for a mechanic’s lien within sixty days, and the contractor fully pays the subcontractor, the statute does not entitle plaintiff to a mechanic’s lien against the railroad, though the company has not paid the contractor.</p>

Judges: Corson, Hanby, Took

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.