Complete Gen. Constr. Co. v. Ohio Dept. of Transp.

Citations

  • 2002 Ohio 59
  • 94 Ohio St. 3d 54

Syllabus

Public construction — Modified Eichleay formula is one way of determining unabsorbed home office overhead damages in public construction delay cases — Courts applying modified Eichleay formula must allow owners opportunity to dispute particular items contractor submits in an overall overhead cost presentation.

Judges: Pfeifer, J.