· 1/15/1812

Coleman v. Southwick

Citations

  • 9 Johns. 45

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • overruling defendants’ demurrer where plaintiff alleged that a delay in payment was contemplated by the contract
  • where parties do not stipulate a fixed time for payment but agree that money is payable only upon a demand in fact therefor, the stat ute of limitation does not begin to ran until an actual demand

Source: CourtListener parenthetical corpus (CC0).

Judges: Kent, Spencer