City of El Paso v. Public Utility Commission of Texas

Citations

  • 839 S.W.2d 895
  • 1992 WL 205181

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that the Commission can allow a utility to recover all deferred charges except deferred carrying costs
  • holding that the Commission can allow a utility to recover all deferred charges except deferred carrying costs
  • holding that the Commission can allow a utility to recover all deferred charges except deferred carrying costs
  • “In conducting a substantial evidence review, we must determine whether the evidence as a whole is such that reasonable minds could have reached the conclusion the agency must have reached in order to take the disputed action”
  • citations 140 expresses the Commission's final calculation of total. omitted

Source: CourtListener parenthetical corpus (CC0).

Judges: Carroll, Aboussie, Jones

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.