· 5/26/1993
City of El Paso v. El Paso Electric Co.
Citations
- 851 S.W.2d 896
- 1993 WL 63956
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- refusing to uphold agency order on factual basis different from that relied on by agency
- refusing to uphold agency order on factual basis different from that relied on by agency
- “‘Capacity costs’ refer to one element of the price charged by a seller of electric power—an element that represents the seller’s fixed costs in generating the power.” Energy-only charges reflect “the seller’s variable costs in generating the power—the cost of fuel, for example.”
- “ ‘Capacity costs’ refer to one element of the price charged by a seller of electric power — an element that represents the seller’s fixed costs in generating the power.” Energy-only charges reflect “the seller’s variable costs in generating the power — the cost of fuel, for example.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Powers, Aboussie, Smith
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).