· 2/20/1970
Chaney and James Construction Company, Inc. v. The United States
Citations
- 421 F.2d 728
- 190 Ct. Cl. 699
- 1970 U.S. Ct. Cl. LEXIS 110
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- upholding decision that 45 days was the reasonable portion of a 90-day delay due to a stop-work order
- “[A]ll delay due to defective or erroneous Government specifications are per se unreasonable and hence compensable.”
- where contract clause is intended as substitute for action at law for breach, “the contractor should be entitled to get the same relief under the clause that he could get in the absence of the clause if he sued for breach of contract”
- \since the Suspension of Work clause is an administrative substitute for an action at law for breach ... the contractor should be entitled to get the same relief under the clause that he could get in the absence of the clause if he sued for breach of contract\
- \since the Suspension of Work clause is an administrative substitute for an action at law for breach . . . . the contractor should be entitled to get the same relief under the clause that he could get in the absence of the clause if he sued for breach of contract\
- addressing substantively identical clause text
Source: CourtListener parenthetical corpus (CC0).
Judges: Cowen, Laramore, Durfee, Davis, Collins, Skelton, Nichols
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.