Chandley v. Cambridge Springs Borough
Citations
- 203 Pa. 139
- 52 A. 87
- 1902 Pa. LEXIS 669
Syllabus
<p>Contract — Delay—Construction of waterworks — Borough.</p> <p>Where a person contracts with a borough to construct waterworks, he is not justified in delaying the work because, prior to the time when any money was due him, the borough had not sold its bonds, the proceeds of which were to be used in payment for the construction of the waterworks; but if the delay in completing the work was due to a default on the part of the borough in making the first and second payments under the contract, the contractor is not liable.</p>
Judges: Collum, Dean, Feel, Mitchell, Pell, Potteb
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.