Boston Gas Company v. Federal Energy Regulatory Commission, Algonquin Gas Transmission Company, Intervenors

Citations

  • 575 F.2d 975
  • 1978 U.S. App. LEXIS 11198

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that \[n]either the Commission nor the courts are given any form of jurisdictional discretion\
  • holding that “[n]either the Commission nor the courts are given any form of jurisdictional discretion”
  • treating as jurisdictional section 717r(a)’s requirement of an “application for rehearing filed within 30 days”
  • noting that FERC has accepted rehearing motions via telegraph
  • “In the present case petitioner presents no meritorious excuse for its failure to file a timely application for rehearing.”
  • “Neither the Commission nor the courts are given any form of jurisdictional discretion.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Coffin, Campbell, Bownes

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.