· 3/6/1986
Bob Neiner Farms, Inc. v. Hendrix
Citations
- 490 N.E.2d 257
- 141 Ill. App. 3d 499
- 1 U.C.C. Rep. Serv. 2d (West) 634
- 95 Ill. Dec. 784
- 1986 Ill. App. LEXIS 1935
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- building construction contract was primarily for goods, so claim properly was dismissed under UCC statute of limitations
- building construction contract was primarily for goods, so claim properly was dismissed under UCC statute of limitations
- the builder provided a standardized structure and placed it on the buyer's site, and the builder was not in the business of providing individualized design and construction services; the court held this to be a contract for goods
- the builder provided a standardized structure and placed it on the buyer’s site, and the builder was not in the business of providing individualized design and construction services; the court held this to be a contract for goods
Source: CourtListener parenthetical corpus (CC0).
Judges: Barry
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.