Black Lake Pipe Line Co. v. Union Construction Co.

Citations

  • 538 S.W.2d 80
  • 19 Tex. Sup. Ct. J. 318
  • 1976 Tex. LEXIS 221

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • recognizing that contractor could recover quantum meruit “for the reasonable value of services rendered and accepted which are not covered by the contract”
  • recognizing that contractor could recover quantum meruit “for the reasonable value of services rendered and accepted which are not covered by the contract” (emphasis added)
  • noting that the architect's approval was not binding on the owner, but was on the contractors
  • noting that the architect’s approval was not binding on the owner, but was on the contractors
  • adopting reasonableness test because construction contract provided that one party to contract could overrule its own inspectors' decision about whether performance was satisfactory
  • adopting reasonableness test because construction contract provided that one party to contract could overrule its own inspectors’ decision about whether performance was satisfactory

Source: CourtListener parenthetical corpus (CC0).

Judges: Sam D. Johnson

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).