Artigas v. Renewal Arts Realty Corp.

Citations

  • 22 A.D.3d 327
  • 803 N.Y.S.2d 12

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • apportioning 75% of damages to the defendant where 25% of the fault for the delay was attributable to the plaintiff
  • apportioning 75% of damages to the defendant where 25% of the fault for the delay was attributable to the plaintiff
  • 11.22% of costs to cover profits and overhead was found to be reasonable
  • recovery upheld when records were maintained “on a daily basis and meticulously recorded the number of men and machines on the job as well as the type of work being done each day”
  • claim for actual costs was properly supported with daily records “meticulously recording] the number of men and machines on the job each day as well as the type of work being done on each day”

Source: CourtListener parenthetical corpus (CC0).

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.