Artigas v. Renewal Arts Realty Corp.
Citations
- 22 A.D.3d 327
- 803 N.Y.S.2d 12
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- apportioning 75% of damages to the defendant where 25% of the fault for the delay was attributable to the plaintiff
- apportioning 75% of damages to the defendant where 25% of the fault for the delay was attributable to the plaintiff
- 11.22% of costs to cover profits and overhead was found to be reasonable
- recovery upheld when records were maintained “on a daily basis and meticulously recorded the number of men and machines on the job as well as the type of work being done each day”
- claim for actual costs was properly supported with daily records “meticulously recording] the number of men and machines on the job each day as well as the type of work being done on each day”