Syllabus
This appeal concerns a subcontractor's claims for non-payment. The trial court dismissed the claim for unjust enrichment against defendant Clark, the home owner, as not ripe because the plaintiff subcontractor had not exhausted its remedies against the party with whom it had contracted. The plaintiff appeals. We affirm.