American Trading and Production Corporation v. Shell International Marine Ltd.

Citations

  • 453 F.2d 939
  • 1972 A.M.C. 318
  • 1972 U.S. App. LEXIS 11995

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • closing of Suez Canal requiring charterer to sail nearly twice as many miles at . . . cost of nearly one-third more than . . . contract price does not excuse performance
  • closing of Suez Canal requiring charterer to sail nearly twice as many miles at a cost of nearly one third more than the contract price does not excuse performance
  • closing of Suez Canal requiring charterer to sail nearly twice as many miles at a cost of nearly one third more than the contract price does not excuse performance
  • “Mere increase in cost alone is not a sufficient excuse for non- performance. It must be an ‘extreme and unreasonable’ expense.”
  • no relief for increase of less than one-third

Source: CourtListener parenthetical corpus (CC0).

Judges: Smith, Kaufman, Mulligan