- Construction contract provided that the methods and equipment used in fulfilling the contract were to have the approval of the engineer. Therefore, trial court erred in entering summary judgment in favor of an engineer.
- Construction contract provided that the methods and equipment used in fulfilling the contract were to have the approval of the engineer. Therefore, trial court erred in entering summary judgment in favor of an engineer.
Source: CourtListener parenthetical corpus (CC0).
Judges: Per Curiam
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.