Alamance County Bd. of Education v. Chevrolet
Citations
- 342 N.C. 893
- 467 S.E.2d 899
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- key date commencing 12-month period was receipt by contractor of final decision
- contractor’s suit barred by statute of limitations, filing nine days late
Source: CourtListener parenthetical corpus (CC0).