Skip to main content
· 5/2/1983

Airport Construction & Materials, Inc. v. Bivens

Citations

  • 649 S.W.2d 830
  • 279 Ark. 161
  • 31 Cont. Cas. Fed. 71,467
  • 1983 Ark. LEXIS 1379

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • rejecting the argument that “while [Leslie Miller] involved a contractor in a direct relationship with the federal government, the contract [at issue in Bivens] [wa]s a private matter”
  • Leslie Miller rule applied to subcontractors on federal project because federal policy of selecting the lowest responsible bidder would have been frustrated by subjecting even the subcontractor to state regulations
  • Leslie Miller rule applied to subcontractors on federal project because federal policy of selecting the lowest responsible bidder would have been frustrated by subjecting even the subcontractor to state regulations

Source: CourtListener parenthetical corpus (CC0).

Judges: Hays

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.