NRC Reviews of Reactor Designs Previously Authorized by U.S. Department of Energy or Department of War
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
The U.S. Nuclear Regulatory Commission (NRC) is amending its regulations to facilitate direct leveraging of prior U.S. Department of Energy or Department of War authorizations of demonstration reactors into the NRC's licensing reviews of commercial reactor facility applications that reference those designs. This rulemaking improves NRC licensing review efficiency, where applicable, by explicitly establishing by regulation an additional means for reactor applicants to demonstrate the safety functions of their reactor designs, thereby contributing to the safe and secure use and deployment of civilian nuclear energy technologies.
Full Text
<html>
<head>
<title>Federal Register, Volume 91 Issue 205 (Monday, October 26, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 205 (Monday, October 26, 2026)]
[Rules and Regulations]
[Pages 67195-67200]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-21801]
========================================================================
Rules and Regulations
Federal Register
________________________________________________________________________
This section of the FEDERAL REGISTER contains regulatory documents
having general applicability and legal effect, most of which are keyed
to and codified in the Code of Federal Regulations, which is published
under 50 titles pursuant to 44 U.S.C. 1510.
The Code of Federal Regulations is sold by the Superintendent of Documents.
========================================================================
Federal Register / Vol. 91, No. 205 / Monday, October 26, 2026 /
Rules and Regulations
[[Page 67195]]
NUCLEAR REGULATORY COMMISSION
10 CFR Parts 50 and 53
[NRC-2025-1503]
RIN 3150-AL60
NRC Reviews of Reactor Designs Previously Authorized by U.S.
Department of Energy or Department of War
AGENCY: Nuclear Regulatory Commission.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is amending its
regulations to facilitate direct leveraging of prior U.S. Department of
Energy or Department of War authorizations of demonstration reactors
into the NRC's licensing reviews of commercial reactor facility
applications that reference those designs. This rulemaking improves NRC
licensing review efficiency, where applicable, by explicitly
establishing by regulation an additional means for reactor applicants
to demonstrate the safety functions of their reactor designs, thereby
contributing to the safe and secure use and deployment of civilian
nuclear energy technologies.
DATES: This final rule is effective on November 25, 2026.
ADDRESSES: Please refer to Docket ID NRC-2025-1503 when contacting the
NRC about the availability of information for this action. You may
obtain publicly available information related to this action by any of
the following methods:
<bullet> Federal Rulemaking website: Electronically at <a href="https://www.regulations.gov">https://www.regulations.gov</a>. Search for Docket ID NRC-2025-1503. Address
questions about NRC dockets to Helen Chang; telephone: 301-415-3228;
email: <a href="/cdn-cgi/l/email-protection#652d0009000b4b260d040b02250b17064b020a13"><span class="__cf_email__" data-cfemail="b2fad7ded7dc9cf1dad3dcd5f2dcc0d19cd5ddc4">[email protected]</span></a>. For technical questions, contact the
individuals listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
<bullet> NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at <a href="https://www.nrc.gov/reading-rm/adams.html">https://www.nrc.gov/reading-rm/adams.html</a>. To begin the search, select ``Begin ADAMS Public Search.''
For problems with ADAMS, please contact the NRC's Public Document Room
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email
to <a href="/cdn-cgi/l/email-protection#1f4f5b4d314d7a6c706a6d7c7a5f716d7c31787069"><span class="__cf_email__" data-cfemail="257561770b7740564a50574640654b57460b424a53">[email protected]</span></a>. For the convenience of the reader,
instructions about obtaining materials referenced in this document are
provided in the ``Availability of Documents'' section.
<bullet> NRC's PDR: The PDR, where you may examine and order copies
of publicly available documents, is open by appointment. To make an
appointment to visit the PDR, please send an email to
<a href="/cdn-cgi/l/email-protection#beeefaec90ecdbcdd1cbccdddbfed0ccdd90d9d1c8"><span class="__cf_email__" data-cfemail="ce9e8a9ce09cabbda1bbbcadab8ea0bcade0a9a1b8">[email protected]</span></a> or call 1-800-397-4209 or 301-415-4737, between 8
a.m. and 4 p.m. eastern time, Monday through Friday, except Federal
holidays.
FOR FURTHER INFORMATION CONTACT: Aaron Kwok, Office of Nuclear Material
Safety and Safeguards, telephone: 301-415-1371, email:
<a href="/cdn-cgi/l/email-protection#c988a8bba6a7e782bea6a289a7bbaae7aea6bf"><span class="__cf_email__" data-cfemail="df9ebeadb0b1f194a8b0b49fb1adbcf1b8b0a9">[email protected]</span></a> and Jackie Harvey, Office of Advanced Reactors,
telephone: 301-415-7534, email: <a href="/cdn-cgi/l/email-protection#fbb19a988a8e9e978295d5b39a898d9e82bb958998d59c948d"><span class="__cf_email__" data-cfemail="0d476c6e7c786861746323456c7f7b68744d637f6e236a627b">[email protected]</span></a>. Both are
staff of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001.
SUPPLEMENTARY INFORMATION:
Table of Contents
I. Executive Order 14300: Ordering the Reform of the Nuclear
Regulatory Commission
II. Discussion
III. Opportunities for Public Participation
IV. Public Comment Analysis
V. Regulatory Flexibility Certification
VI. Regulatory Analysis
VII. Backfitting and Issue Finality
VIII. Cumulative Effects of Regulation
IX. Plain Writing
X. National Environmental Policy Act
XI. Paperwork Reduction Act
XII. Executive Orders
A. Executive Order 12866: Regulatory Planning and Review (as
Amended by Executive Order 14215, Ensuring Accountability for All
Agencies)
B. Executive Order 14154: Unleashing American Energy
C. Executive Order 14192: Unleashing Prosperity Through
Deregulation
D. Executive Order 14270: Zero-Based Regulatory Budgeting To
Unleash American Energy
XIII. Congressional Review Act
XIV. Voluntary Consensus Standards
XV. Availability of Guidance
XVI. Availability of Documents
I. Executive Order 14300: Ordering the Reform of the Nuclear Regulatory
Commission
On May 23, 2025, President Donald J. Trump signed Executive Order
(E.O.) 14300, ``Ordering the Reform of the Nuclear Regulatory
Commission.'' Section 5, ``Reforming and Modernizing the NRC's
Regulations,'' directed the NRC to undertake a review and wholesale
revision of its regulations and guidance documents as guided by the
policies set forth in section 2 of the E.O. This rulemaking addresses
section 5(d), which contemplates an expedited pathway to approve
reactor designs that the U.S. Department of Energy (DOE) or the
Department of War (DOW) have tested and that have demonstrated the
ability to function safely.\1\ E.O. 14300 further states that NRC
review of such designs should focus solely on risks that may arise from
new applications permitted by NRC licensure, rather than revisiting
risks that have already been addressed in the DOE or DOW processes.
---------------------------------------------------------------------------
\1\ Consistent with E.O. 14347, ``Restoring the United States
Department of War,'' this Federal Register notice refers to the
``Department of War'' and ``Department of Defense'' interchangeably.
Per section 2(d) of E.O. 14347, the regulatory text for this limited
scope rulemaking continues to use the title, ``Department of
Defense,'' to avoid creating inconsistencies with or causing
confusion in the NRC's existing regulations in title 10 of the Code
of Federal Regulations.
---------------------------------------------------------------------------
II. Discussion
Consistent with its authority and historical practice under section
161 of the Atomic Energy Act of 1954 (AEA) to make, promulgate, issue,
rescind, and amend rules and regulations as well as that under section
182 of the AEA to determine the information that enables the Commission
to make the findings required to grant an application for a utilization
facility, the NRC is amending title 10 of the Code of Federal
Regulations (10 CFR) section 50.43, ``Additional standards and
provisions affecting class 103 licenses and certifications for
commercial power,'' and section 53.440, ``Design requirements.'' These
changes explicitly establish a pathway for streamlined reviews for
licensing commercial reactor designs that have previously received
[[Page 67196]]
DOE or DOW authorization and that have been tested and have
demonstrated the ability to function safely. The amendment to Sec.
50.43 explicitly establishes such a pathway for the licensing
frameworks under 10 CFR part 50, ``Domestic Licensing of Production and
Utilization Facilities,'' and part 52, ``Licenses, Certifications, and
Approvals for Nuclear Power Plants,'' and the amendment to Sec. 53.440
does so for the 10 CFR part 53, ``Risk-Informed, Technology-Inclusive
Regulatory Framework for Commercial Nuclear Plants,'' licensing
framework. A similar provision is included in a separate proposed rule,
``Licensing Requirements for Microreactors and Other Reactors With
Comparable Risk Profiles,'' which, if finalized, would apply to the
associated proposed 10 CFR part 57, ``Licensing Requirements for
Microreactors and Other Reactors with Comparable Risk Profiles,''
licensing framework (91 FR 23628; May 1, 2026). The primary intent of
this rulemaking is to improve NRC licensing review efficiency, and in
turn increase capacity, for conducting licensing reviews. At the same
time, this rulemaking maintains flexibility for the NRC to leverage a
broad range of technologies, testing methods, and information from
previously authorized and evaluated designs, as appropriate and
supported by an applicant in its commercial license application. In
turn, this contributes to the safe and secure use and deployment of
civilian nuclear energy technologies.
Section 50.43(e) provides two options for license applicants to
demonstrate how newer reactor designs, including those that use
simplified, inherent, passive, or other innovative means, accomplish
their safety functions. The final rule adds the option, to be codified
in Sec. 50.43(f), for an applicant to reference information from a
prior DOE or DOW authorization as a means for an NRC license applicant
to show that the design can accomplish its safety functions, as
required by Sec. 50.43(e).
The amendment to Sec. 50.43 explicitly reflects the option for NRC
Class 103 license applicants to directly reference a prior DOE or DOW
authorization when demonstrating compliance with NRC regulatory
requirements. Applicants using this option are required to identify how
aspects of the prior authorization satisfy NRC regulations, including
Sec. 50.43(e). Applicants are also required to address how any changes
to the design, its functionality, associated hazards, siting
information, or underlying safety assumptions from those considered in
prior authorization reviews meet applicable NRC requirements.
Under the part 53 licensing framework, Sec. 53.440 provides a
series of design requirements. The requirements in Sec. 53.440(a)(1)
reflect an essential element of ensuring a proposed design can comply
with the performance criteria in part 53, namely that the abilities of
design features to fulfill their safety functions are demonstrated by a
combination of analyses, test programs, prototype testing, and
operating experience. This requirement closely aligns with the language
in Sec. 50.43(e) and reflects the same foundational requirement.
The amendment to Sec. 53.440(a)(1) explicitly accommodates the
option for NRC Class 103 license applicants to directly reference a
prior DOE or DOW authorization for the purpose of demonstrating that
the design features required by Sec. 53.400, ``Design features for
licensing-basis events'' meet the defined functional design criteria
required by Sec. Sec. 53.410, ``Functional design criteria for design-
basis accidents,'' and 53.420, ``Functional design criteria for
licensing-basis events other than design-basis accidents.'' Such a
demonstration is required to consider interdependent effects throughout
the commercial nuclear plant and the range of conditions under which
the design features required by Sec. 53.400 must function throughout
the plant's lifetime. Applicants using this option are required to
identify how aspects of the prior authorization satisfy applicable NRC
regulations.
The new Sec. Sec. 50.43(f) and 53.440(a)(1) pathways will be
supported by the draft Interim Staff Guidance (ISG), DANU-ISG-2026-XX,
``NRC Application Pathway for Reactor Designs Previously Authorized by
U.S. Department of Energy or Department of War.'' The guidance is not
part of this rulemaking but was published for public comment on April
17, 2026 (91 FR 20717). The scope of such guidance is intended to
facilitate staff review of future commercial nuclear plant license
applications, including advanced reactor designs that may not employ
light-water technology.
The NRC also recognizes significant public interest in this rule
and has provided a separate public comment response document as
discussed in Section IV of this document, ``Public Comment Analysis.''
While that document provides comprehensive responses to comments,
several points are highlighted below.
Some comments expressed concern that this rulemaking would impact
the NRC's performance of independent evaluations of license
applications mandated under the AEA. Specifically, section 103 of the
AEA and title II of the Energy Reorganization Act of 1974 (88 Stat.
1242) authorize the NRC to, among other things, issue licenses for
commercial nuclear power plants if in the opinion of the Commission,
issuance of the license would not be inimical to the common defense and
security or to the health and safety of the public. First and foremost,
this rulemaking does not affect the NRC's commitment to conducting
independent reviews, nor does this rulemaking alter any underlying
regulatory requirements an applicant must meet. Nothing in this rule
delegates to DOE, DOW, or any other agency the NRC's functions to
evaluate a request for NRC approval, and nothing in this rule allows
the NRC to forego an independent review. Regardless of whether an
applicant references a prior DOE or DOW authorization, it remains the
applicant's responsibility to demonstrate compliance with all
applicable requirements, under the AEA and NRC regulations, and the NRC
will continue to conduct the independent assessments necessary to
confirm whether such requirements have indeed been satisfied. Where an
NRC applicant references information from a prior design authorized and
tested by DOE or DOW, the applicant is responsible for justifying the
applicability and relevance of the information it seeks to rely upon,
and where it does so, the NRC may be able to tailor the focus and depth
of its review.
Under this approach, the NRC notes that the extent to which prior
DOE or DOW information can be leveraged depends on the information an
applicant provides and the associated justification as to how it meets
NRC requirements. For example, the scope of a DOE or DOW authorization
or associated testing may not fully represent a commercial reactor
configuration or the breadth of analyses necessary for an NRC licensing
basis. The final rule is intentionally structured to reflect that not
all prior DOE or DOW authorizations may meet the full scope of
requirements specified in Sec. 50.43 and, in recognition of this, to
nevertheless make clear that the NRC retains the flexibility to
leverage information from such authorizations to the maximum extent
practical.
In addition, some comments highlighted that it would be beneficial
for the NRC to provide additional clarity as to the type of information
an NRC application might include in a discussion of how a prior DOE or
DOW authorization supports the application.
[[Page 67197]]
In light of these comments, the NRC is clarifying that, when
demonstrating compliance with applicable regulations, an NRC applicant
may, for example, consider including a discussion of the following: (A)
the scope of the prior authorization, including the testing, analyses,
and operational experience on which it relied, as applicable; (B) the
safety functions and design features addressed by such authorization;
and (C) any differences from the prior authorization in design,
operational, or siting factors relevant to the application that are
material to the Commission's licensing review.
Finally, several commenters expressed concerns that the proposed
Sec. 50.43(e)(3) would establish a lower safety standard than that
required by Sec. 50.43(e)(1)-(2) and Sec. 53.440(a)(1). As explained
in the public comment response document, the NRC has revised the
language originally proposed to be codified in Sec. 50.43(e)(3) and
has added it as a new subsection Sec. 50.43(f) to clarify and to
reaffirm that this rulemaking does not alter the safety standard
established inSec. 50.43(e) and to enhance consistency with the
approach taken in the rule revision to Sec. 53.440(a)(1). As such, the
final rule language makes clear that Sec. 50.43(f) is one option that
a commercial license applicant may use to satisfy the requirements, or
a subset of the requirements, contained in section(e). As previously
noted, applicants must still meet all applicable NRC and statutory
requirements. Although Sec. 50.43(f) provides a pathway for reactor
technologies to demonstrate the ability to accomplish safety functions
under Sec. 50.43(e), if an authorization does not supply all necessary
information, the final rule language in Sec. 50.43(f) reflects that
applicants must address any remaining gaps to ensure full compliance
with NRC requirements.
III. Opportunities for Public Participation
The proposed rule was published in the Federal Register on April 2,
2026 (91 FR 16584) for a 30-day comment period ending May 4, 2026. The
NRC held a public meeting on April 14, 2026, and developed a public
meeting summary (ML26131A245).
IV. Public Comment Analysis
The NRC prepared a summary and analysis of public comments (``NRC
Response to Public Comments: NRC Reviews of Reactor Designs Previously
Authorized by U.S. Department of Energy or Department of War'')
received on the proposed rule, as referenced in the ``Availability of
Documents'' section. In response to the proposed rule, the NRC received
136 unique comment submissions.
The public comment submissions are available from the Federal
rulemaking website at <a href="https://www.regulations.gov">https://www.regulations.gov</a> under Docket ID NRC-
2025-1503. Responses to the public comments, including a summary of how
this final rule changed as a result of the public comments, can be
found in the public comment response document as indicated in the
``Availability of Documents'' section of this document.
V. Regulatory Flexibility Certification
Under the Regulatory Flexibility Act (5 U.S.C. 605(b)), the NRC
certifies that this rule does not have a significant economic impact on
a substantial number of small entities. This final rule affects only
the licensing and operation of nuclear power plants. The companies that
own these plants do not fall within the scope of the definition of
``small entities'' set forth in the Regulatory Flexibility Act or the
size standards established by the NRC (10 CFR 2.810).
VI. Regulatory Analysis
The NRC has not prepared a separate regulatory analysis. However,
the NRC performed a qualitative economic analysis of the rule's
impacts. As a result of this final rule, the NRC expects that the NRC
will not need to repeat technical reviews previously performed by DOE
or DOW, to the extent that those reviews cover the same scope as the
related content in the NRC license application. The final rule language
at Sec. 50.43(f) offers an option to meet the requirements in Sec.
50.43(e), and the final rule language in Sec. 53.440(a) provides an
option for how to demonstrate that the design features required by
Sec. 53.400 meet the design criteria required by Sec. Sec. 53.410 and
53.420. Therefore, the NRC does not anticipate that an application
under the new Sec. 50.43(f) or the revised Sec. 53.440(a)(1) would
require more review work than under the existing requirements.
Furthermore, the NRC assumes that applications under these sections
will be high-quality applications.
In general, the NRC expects cost savings to both applicants in
preparing an application and the NRC in reviewing that application. The
NRC was not able to quantify these potential savings in a useful way at
this time. These savings depend on the applicability of the DOE/DOW
reviews to NRC requirements and the ability of applicants to
demonstrate that applicability, the number of applications that may
reference a previous DOE/DOW authorization, as well as how any
potential differences (e.g., changes to the design or site-specific
factors) from the previously authorized design also meet NRC
requirements. The NRC anticipates that use of the approaches provided
by Sec. 50.43(f) or 53.440(a)(1) will become more efficient as
experience is gained, i.e., there may be an initial learning curve
which may result in greater cost savings over time, to both the NRC and
applicants, as a result of the additional flexibility this final rule
provides to applicants. Therefore, the NRC expects that this final rule
will be cost beneficial to both the NRC and future applicants.
VII. Backfitting and Issue Finality
The changes to Sec. Sec. 50.43(f) and 53.440(a)(1) do not impose
new or revised requirements on existing licensees or approval holders
because they include an option that would apply only to future
applicants. Therefore, the changes do not constitute backfitting as
defined in Sec. 50.109(a)(1) or 53.1590(a)(1) or affect the issue
finality of an existing approval issued under 10 CFR part 52,
``Licenses, Certifications, and Approvals for Nuclear Power Plants.''
VIII. Cumulative Effects of Regulation
The NRC seeks to minimize any potential negative consequences
resulting from the cumulative effects of regulation (CER). The CER
describes the challenges that licensees, or other impacted entities
such as State partners, may face while implementing new regulatory
positions, programs, or requirements (e.g., rules, generic letters,
backfits, inspections). The CER is an organizational effectiveness
challenge that may result from a licensee or impacted entity
implementing a number of complex regulatory actions, programs, or
requirements within limited available resources.
The goals of the NRC's CER effort were met throughout the
development of this final rule. The NRC engaged with external
stakeholders at a public meeting and solicited public comments on the
proposed rule. The NRC included in the proposed rule a request for
feedback related to CER. Specifically, the NRC requested feedback on
the implementation and potential unintended consequences of the
proposed rule, and invited comments on the regulatory analysis. The NRC
received several comment submissions in response to these CER
questions, which are addressed in the public comment response document
as indicated in the ``Availability of Documents'' section of this
document.
[[Page 67198]]
IX. Plain Writing
The Plain Writing Act of 2010 (Pub. L. 111-274) requires Federal
agencies to write documents in a clear, concise, and well-organized
manner. The NRC has written this document to be consistent with the
Plain Writing Act as well as the Presidential Memorandum, ``Plain
Language in Government Writing,'' published June 10, 1998 (63 FR
31885).
X. National Environmental Policy Act
The NRC has determined that this final rule is the type of action
eligible for categorical exclusion because it meets the criterion
described in Sec. 51.22(a)(1). This provision includes amendments to
parts 50 and 53 related to procedures for filing and reviewing
applications for licenses or construction permits or early site permits
or other forms of permission or for amendments to or renewals of
licenses or construction permits or early site permits or other forms
of permission. The action belongs to a category of actions that the
Commission, by rule or regulation, has declared to be a categorical
exclusion, after first finding that the actions within the category do
not individually or cumulatively have a significant effect on the human
environment. Therefore, neither an environmental impact statement nor
environmental assessment has been prepared for this final rule. For any
particular licensing action that would use the pathways from this rule,
the NRC will comply with its obligations under the National
Environmental Policy Act, including by developing or using an
environmental impact statement, environmental assessment, or
categorical exclusion, as applicable.
XI. Paperwork Reduction Act
This final rule does not contain any new or amended collections of
information subject to the Paperwork Reduction Act of 1995 (44 U.S.C.
3501 et seq.). Existing collections of information were approved by the
Office of Management and Budget (OMB), approval numbers 3150-0011 and
3150-0274.
Public Protection Notification
The NRC may not conduct or sponsor, and a person is not required to
respond to, a collection of information unless the document requesting
or requiring the collection displays a currently valid OMB control
number.
XII. Executive Orders
The following are Executive orders that are related to this final
rule:
A. Executive Order 12866: Regulatory Planning and Review (as Amended by
Executive Order 14215, Ensuring Accountability for All Agencies)
E.O. 12866 provides that the Office of Information and Regulatory
Affairs (OIRA) within the OMB will review all significant rules. OIRA
has determined that this final rule is a significant regulatory action
under section 3(f) of E.O. 12866; though not economically significant
under section 3(f)(1). Accordingly, the NRC submitted this final rule
to OIRA for review. The NRC has prepared an economic analysis in
accordance with section 6(a)(3)(B) of E.O. 12866. More can be found in
Section VI, of this document, ``Regulatory Analysis.''
B. Executive Order 14154: Unleashing American Energy
NRC has examined this final rule and has determined that it is
consistent with the policies and directives outlined in E.O. 14154.
C. Executive Order 14192: Unleashing Prosperity Through Deregulation
This action is a deregulatory action as defined by E.O. 14192.
Details on the estimated costs of this final rule can be found in
Section VI of this document, ``Regulatory Analysis.''
D. Executive Order 14270: Zero-Based Regulatory Budgeting To Unleash
American Energy
E.O. 14270, ``Zero-Based Regulatory Budgeting to Unleash American
Energy,'' requires the NRC to insert a conditional sunset date into all
new or amended NRC regulations provided the regulations are (1)
promulgated under the AEA, the Energy Reorganization Act of 1974, as
amended (ERA), or the Nuclear Waste Policy Act of 1982, as amended
(NWPA); (2) not statutorily required; and (3) not part of the NRC's
permitting regime. The NRC determined that the regulatory changes
proposed in this rule are part of the NRC's regulatory permitting
scheme authorized by the AEA, ERA, or NWPA. Therefore, the NRC views
this rulemaking to be outside the scope of E.O. 14270 and did not
insert conditional sunset dates for the regulatory changes in this
final rule.
XIII. Congressional Review Act
This final rule is a rule as defined in the Congressional Review
Act (5 U.S.C. 801-808). However, OMB has found that it does not meet
the criteria at 5 U.S.C. 804(2).
XIV. Voluntary Consensus Standards
The National Technology Transfer and Advancement Act of 1995,
Public Law 104-113, requires that Federal agencies use technical
standards that are developed or adopted by voluntary consensus
standards bodies unless the use of such a standard is inconsistent with
applicable law or otherwise impractical. In this final rule, the NRC
revised its regulations to facilitate direct leveraging of prior DOE or
DOW authorizations of demonstration reactors into the NRC's licensing
reviews of commercial reactor facility applications that utilize those
designs. This action does not constitute the establishment of a
standard that contains generally applicable requirements.
XV. Availability of Guidance
The NRC will be issuing new guidance for the implementation of the
amendments in this rulemaking. The NRC will publish Federal Register
notices announcing the availability of the new guidance documents. The
documents will be available at <a href="https://www.regulations.gov">https://www.regulations.gov</a> by searching
on Docket ID NRC-2026-0760.
XVI. Availability of Documents
The documents identified in the following table are available to
interested persons through one or more of the following methods, as
indicated.
------------------------------------------------------------------------
ADAMS accession No./Federal
Document Register citation
------------------------------------------------------------------------
Final Rule Documents
------------------------------------------------------------------------
NRC Response to Public Comments: ``NRC ML26282A996.
Reviews of Reactor Designs Previously
Authorized by U.S. Department of Energy or
Department of War,'' October 2026.
Public Meeting Summary for April 14, 2026, ML26131A245.
Meeting on NRC Reviews of Previously
Authorized Reactor Designs, May 12, 2026.
------------------------------------------------------------------------
[[Page 67199]]
Proposed Rule Documents
------------------------------------------------------------------------
Proposed Rule--``NRC Reviews of Reactor 91 FR 16584.
Designs Previously Authorized by U.S.
Department of Energy or Department of
War,'' April 2, 2026.
Unofficial Redline Rule Language for the ML25301A002.
Proposed Rule--``NRC Reviews of Reactor
Designs Previously Authorized by U.S.
Department of Energy or Department of
War,'' March 2026.
------------------------------------------------------------------------
Other References
------------------------------------------------------------------------
Draft Interim Staff Guidance, DANU-ISG-2026- 91 FR 20717.
XX, ``NRC Application Pathway for Reactor
Designs Previously Authorized by U.S.
Department of Energy or Department of
War,'' April 17, 2026.
Executive Order 12866, ``Regulatory 58 FR 51735.
Planning and Review,'' October 4, 1993.
Executive Order 14154, ``Unleashing 90 FR 8353.
American Energy,'' January 29, 2025.
Executive Order 14192, ``Unleashing 90 FR 9065.
Prosperity Through Deregulation,''
February 6, 2025.
Executive Order 14215, ``Ensuring 90 FR 10447.
Accountability for All Agencies,''
February 24, 2025.
Executive Order 14270, ``Zero-Based 90 FR 15643.
Regulatory Budgeting to Unleash American
Energy,'' April 15, 2025.
Executive Order 14300, ``Ordering the 90 FR 22587.
Reform of the Nuclear Regulatory
Commission,'' May 29, 2025.
NRC Size Standard for Making Determinations 50 FR 50241.
Required by the Regulatory Flexibility Act
of 1980, December 9, 1985.
Presidential Memorandum, ``Plain Language 63 FR 31885.
in Government Writing,'' June 10, 1998.
Proposed Rule--``Licensing Requirements for 91 FR 23628.
Microreactors and Other Reactors with
Comparable Risk Profiles'' (3150-AL36; NRC-
2025-0379), May 1, 2026.
Final Rule--Receipts-Based NRC Size 87 FR 8943.
Standards, February 17, 2022.
------------------------------------------------------------------------
The NRC may post materials related to this document, including
public comments, on the Federal rulemaking website at <a href="https://www.regulations.gov">https://www.regulations.gov</a> under Docket ID NRC-2025-1503. In addition, the
Federal rulemaking website allows members of the public to receive
alerts when changes or additions occur in a docket folder. To
subscribe: (1) navigate to the docket folder (NRC-2025-1503); (2) click
the ``Subscribe'' button; and (3) enter an email address and click on
the ``Subscribe'' button.
List of Subjects
10 CFR Part 50
Administrative practice and procedure, Antitrust, Backfitting,
Classified information, Criminal penalties, Education, Emergency
planning, Fire prevention, Fire protection, Intergovernmental
relations, Nuclear power plants and reactors, Penalties, Radiation
protection, Reactor siting criteria, Reporting and recordkeeping
requirements, Whistleblowing.
10 CFR Part 53
Administrative practice and procedure, Antitrust, Backfitting,
Construction permit, Combined license, Classified information, Criminal
penalties, Early site permit, Emergency planning, Fees, Fire
prevention, Fire protection, Inspection, Intergovernmental relations,
Limited work authorization, Manufacturing license, Nuclear power plants
and reactors, Operating license, Penalties, Prototype, Radiation
protection, Reactor siting criteria, Reporting and recordkeeping
requirements, Standard design, Standard design certification, Training
programs.
For the reasons set out in the preamble and under the authority of
the Atomic Energy Act of 1954, as amended; the Energy Reorganization
Act of 1974, as amended; and 5 U.S.C. 552 and 553, the NRC is adopting
the following amendments to 10 CFR parts 50 and 53:
PART 50--DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION
FACILITIES
0
1. The authority citation for part 50 continues to read as follows:
Authority: Atomic Energy Act of 1954, secs. 11, 101, 102, 103,
104, 105, 108, 122, 147, 149, 161, 181, 182, 183, 184, 185, 186,
187, 189, 223, 234 (42 U.S.C. 2014, 2131, 2132, 2133, 2134, 2135,
2138, 2152, 2167, 2169, 2201, 2231, 2232, 2233, 2234, 2235, 2236,
2237, 2239, 2273, 2282); Energy Reorganization Act of 1974, secs.
201, 202, 206, 211 (42 U.S.C. 5841, 5842, 5846, 5851); Nuclear Waste
Policy Act of 1982, sec. 306 (42 U.S.C. 10226); National
Environmental Policy Act of 1969 (42 U.S.C. 4332); 44 U.S.C. 3504
note; ADVANCE Act of 2024, sec. 301 (42 U.S.C. 2133 note).
0
2. In Sec. 50.43, add paragraph (f) to read as follows:
Sec. 50.43 Additional standards and provisions affecting class 103
licenses and certifications for commercial power.
* * * * *
(f) An application under paragraph (e) of this section may include
consideration of relevant information gathered from a utilization
facility that has been previously authorized by the Department of
Energy or the Department of Defense and that has been tested and has
demonstrated the ability to function safely. Any reference to such a
design must identify how attributes of the authorization satisfy NRC
regulations, including paragraph (e) of this section.
PART 53--RISK-INFORMED, TECHNOLOGY-INCLUSIVE REGULATORY FRAMEWORK
FOR COMMERCIAL NUCLEAR PLANTS
0
3. The authority citation for part 53 continues to read:
Authority: Atomic Energy Act of 1954, secs. 11, 101, 103, 108,
122, 147, 161, 181, 182, 183, 184, 185, 186, 187, 189, 223, 234 (42
U.S.C. 2014, 2131, 2132, 2133, 2134, 2135, 2138, 2152, 2167, 2169,
2201, 2231, 2232, 2233, 2234, 2235, 2236, 2237, 2239, 2273, 2282);
Energy Reorganization Act of 1974, secs. 201, 202, 206, 211 (42
U.S.C. 5841, 5842, 5846, 5851); Nuclear Waste Policy Act of 1982,
sec. 306 (42 U.S.C. 10226); National Environmental Policy Act of
1969 (42 U.S.C. 4332); 44 U.S.C. 3504 note; Pub. L. 115-439, 132
Stat. 5571.
0
4. In Sec. 53.440, revise paragraph (a)(1) to read as follows:
Sec. 53.440 Design requirements.
(a)(1) Analysis, appropriate test programs, prototype testing,
operating experience, or a combination thereof must demonstrate that
each design feature required by Sec. 53.400 meets the defined
functional design criteria
[[Page 67200]]
required by Sec. Sec. 53.410 and 53.420. This demonstration must
consider interdependent effects throughout the commercial nuclear plant
and the range of conditions under which the design features required by
Sec. 53.400 must function throughout the plant's lifetime. The bases
for this demonstration may include consideration of relevant
information gathered from a utilization facility that has been
previously authorized by the Department of Energy or the Department of
Defense and which has been tested and has demonstrated the ability to
function safely. Any reference to such a design must identify how
attributes of the authorization satisfy NRC regulations.
* * * * *
Dated: October 22, 2026.
For the Nuclear Regulatory Commission.
Jody Martin,
Secretary of the Commission.
[FR Doc. 2026-21801 Filed 10-22-26; 4:15 pm]
BILLING CODE 7590-01-P