Clear Power LLC (the Applicant or Clear Power) has applied for authorization to transmit electric energy from the United States to Mexico pursuant to the Federal Power Act.
Full Text
<html>
<head>
<title>Federal Register, Volume 91 Issue 201 (Tuesday, October 20, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 201 (Tuesday, October 20, 2026)]
[Notices]
[Pages 66321-66322]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-21424]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[OE Docket No. EA-531]
Application for Authorization To Export Electric Energy; Clear
Power LLC
AGENCY: Office of Electricity, Department of Energy.
ACTION: Notice of application.
-----------------------------------------------------------------------
SUMMARY: Clear Power LLC (the Applicant or Clear Power) has applied for
authorization to transmit electric energy from the United States to
Mexico pursuant to the Federal Power Act.
DATES: Comments must be submitted on or before November 19, 2026.
ADDRESSES: Comments or requests for more information should be
addressed by electronic mail to <a href="/cdn-cgi/l/email-protection#96d3faf3f5e2e4fff5ffe2efb8d3eee6f9e4e2e5d6fee7b8f2f9f3b8f1f9e0"><span class="__cf_email__" data-cfemail="5e1b323b3d2a2c373d372a27701b262e312c2a2d1e362f703a313b70393128">[email protected]</span></a>.
FOR FURTHER INFORMATION CONTACT: Marina Fennel, (240) 702-6156,
<a href="/cdn-cgi/l/email-protection#40052c2523343229232934396e0538302f3234330028316e242f256e272f36"><span class="__cf_email__" data-cfemail="7e3b121b1d0a0c171d170a07503b060e110c0a0d3e160f501a111b50191108">[email protected]</span></a>.
SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE)
regulates electricity exports from the United States to foreign
countries in accordance with section 202(e) of the Federal Power Act
(FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300).
Sections 301(b) and 402(f) of the DOE Organization Act (42 U.S.C.
7151(b) and 7172(f)) transferred this regulatory authority, previously
exercised by the now-defunct Federal Power Commission, to DOE.
Section 202(e) of the FPA provides that an entity which seeks to
export electricity must obtain an order from DOE authorizing that
export (16 U.S.C. 824a(e)). On January 8, 2026, the authority to issue
such orders was delegated to the DOE's Assistant Secretary for the
Office of Electricity by Redelegation Order No. S3-DEL-OE1-2026.
On April 16, 2026, Clear Power filed an application (Application or
App.) with DOE for renewal of export authority to transmit electric
energy from the United States to Mexico for an additional five-year
term. App. at 1. Clear Power was originally granted export
authorization under Order No. EA-487 on December 9, 2020, which expired
on December 9, 2025. Since Clear Power did not apply for renewal until
after the expiration of the current export authorization, DOE is
processing the application as a request for a new export authorization.
According to the Application, Clear Power is a limited liability
corporation with its principal place of business in Folsom, California.
The Applicant is a power marketer with ``authorization from the Federal
Energy Regulatory Commission (FERC) to market electric energy and
capacity at wholesale pursuant to market-based rate authorization.''
Id. at 2. Clear Power states that it is a ``wholly-owned subsidiary of
the Alaywan Trust, which owns or is affiliated with entities that own
or control a combined total of 18.0 MW (nameplate) of operating
renewable generation facilities all located in the California
Independent System Operator (CAISO) market.'' Id. Clear Power ``does
not own or control any electric power generation, transmission
distribution facilities'' and ``does not have a franchised service
area'' Id. at 3. Thus, the Applicant states that it has ``no
`transmission system' of its own on which power exports could have a
reliability or stability impact.'' Id. at 5. Clear Power ``will
schedule its exports from the U.S. in compliance with all applicable
reliability criteria, standards and guides as are set out by the North
American Electricity Reliability Corporation (NERC) (or any successor
organization), the North American Energy Standards Board (or any
successor organization) and regional reliability councils and as
applied by U.S. transmission providers.'' Id. at 5-6.
The existing international transmission facilities to be utilized
by the Applicant have been previously authorized by Presidential
permits issued pursuant to Executive Order 10485, as amended, and are
appropriate for open access transmission by third parties. See App. at
Exhibit C.
Procedural Matters: Any person desiring to be heard in this
proceeding should file a comment to the Application at
<a href="/cdn-cgi/l/email-protection#185d747d7b6c6a717b716c61365d6068776a6c6b587069367c777d367f776e"><span class="__cf_email__" data-cfemail="56133a333522243f353f222f78132e2639242225163e277832393378313920">[email protected]</span></a>.
Comments concerning Clear Power's Application should be clearly
marked with OE Docket No. EA-531. Comments will be posted along with
the relevant application on the program website at <a href="http://www.energy.gov/oe/pending-applications">www.energy.gov/oe/pending-applications</a>.
A final decision will be made on the requested authorization after
the environmental impacts have been evaluated consistent with the
National Environmental Policy Act of 1969 (NEPA), as amended (42 U.S.C.
4321, et seq.), the DOE NEPA regulations at 10 CFR part 1021, and the
DOE's NEPA
[[Page 66322]]
Implementing Procedures (June 2026) and after DOE evaluates whether the
proposed action will have an adverse impact on the sufficiency of
supply or reliability of the United States electric power supply
system.
Copies of this Application are available on the program website at
<a href="http://www.energy.gov/oe/pending-applications">www.energy.gov/oe/pending-applications</a> or by emailing
<a href="/cdn-cgi/l/email-protection#0b4e676e687f796268627f72254e737b64797f784b637a256f646e256c647d"><span class="__cf_email__" data-cfemail="a6e3cac3c5d2d4cfc5cfd2df88e3ded6c9d4d2d5e6ced788c2c9c388c1c9d0">[email protected]</span></a>.
Signing Authority
This document of the Department of Energy was signed on October 14,
2026, by Catherine Jereza, Assistant Secretary, Office of Electricity,
pursuant to delegated authority from the Secretary of Energy. That
document with the original signature and date is maintained by DOE. For
administrative purposes only, and in compliance with requirements of
the Office of the Federal Register, the undersigned DOE Federal
Register Liaison Officer has been authorized to sign and submit the
document in electronic format for publication, as an official document
of the Department of Energy. This administrative process in no way
alters the legal effect of this document upon publication in the
Federal Register.
Signed in Washington, DC, on October 16, 2026.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
[FR Doc. 2026-21424 Filed 10-19-26; 8:45 am]
BILLING CODE 6450-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on October 20, 2026.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.