Modernizing the Commission's National Environmental Policy Act Rules
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
In this document, the Federal Communications Commission (Commission or FCC) seeks additional comment on the Commission's National Historic Preservation Act (NHPA) framework, to further expedite, simplify, and reduce the costs of environmental review. This includes refreshing the record on the meaning of "undertaking" and the Commission's approach to implementing section 106 of the NHPA. The Commission also seeks comment on whether activities related to the deployment and operation of communications infrastructure are within the scope of "undertaking," as well as on other practices or actions the Commission could adopt to provide more efficiency and predictability in the section 106 process. Additionally, the Commission seeks comment on whether communications infrastructure deployments are agency actions subject to the Endangered Species Act (ESA).
Full Text
<html>
<head>
<title>Federal Register, Volume 91 Issue 200 (Monday, October 19, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 200 (Monday, October 19, 2026)]
[Proposed Rules]
[Pages 66062-66069]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-21347]
=======================================================================
-----------------------------------------------------------------------
FEDERAL COMMUNICTIONS COMMISSION
47 CFR Part 1
[WT Docket No. 25-217; FCC 26-64; FR ID: 372724]
Modernizing the Commission's National Environmental Policy Act
Rules
AGENCY: Federal Communications Commission.
ACTION: Proposed rule.
-----------------------------------------------------------------------
SUMMARY: In this document, the Federal Communications Commission
(Commission or FCC) seeks additional comment on the Commission's
National Historic Preservation Act (NHPA) framework, to further
expedite, simplify, and reduce the costs of environmental review. This
includes refreshing the record on the meaning of ``undertaking'' and
the Commission's approach to implementing section 106 of the NHPA. The
Commission also seeks comment on whether activities related to the
deployment and operation of communications infrastructure are within
the scope of ``undertaking,'' as well as on other practices or actions
the
[[Page 66063]]
Commission could adopt to provide more efficiency and predictability in
the section 106 process. Additionally, the Commission seeks comment on
whether communications infrastructure deployments are agency actions
subject to the Endangered Species Act (ESA).
DATES: Comments are due on or before November 18, 2026; reply comments
are due on or before December 3, 2026. Written comments on the Initial
Regulatory Flexibility Analysis (IRFA) in this document must have a
separate and distinct heading designating them as responses to the IRFA
and must be submitted on or before November 18, 2026.
ADDRESSES: You may submit comments, identified by WT Docket No. 25-217,
by any of the following methods:
<bullet> Federal Communications Commission's Website: <a href="https://www.fcc.gov/ecfs/">https://www.fcc.gov/ecfs/</a>. Follow the instructions for submitting comments.
<bullet> People with Disabilities: Contact the FCC to request
reasonable accommodations (accessible format documents, sign language
interpreters, CART, etc.) by email: <a href="/cdn-cgi/l/email-protection#f3b5b0b0c6c3c7b3959090dd949c85"><span class="__cf_email__" data-cfemail="86c0c5c5b3b6b2c6e0e5e5a8e1e9f0">[email protected]</span></a> or phone: 202-418-
0530.
For detailed instructions for submitting comments and additional
information on the rulemaking process, see the SUPPLEMENTARY
INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Robert Krinsky, Wireless
Telecommunications Bureau, Competition & Infrastructure Policy
Division, (202) 418-2909, <a href="/cdn-cgi/l/email-protection#097b666b6c7b7d27627b60677a6270496f6a6a276e667f"><span class="__cf_email__" data-cfemail="9ceef3fef9eee8b2f7eef5f2eff7e5dcfaffffb2fbf3ea">[email protected]</span></a>.
SUPPLEMENTARY INFORMATION: This is a summary of the Commission's
Further Notice of Proposed Rulemaking (FNPRM), FCC 25-64, adopted on
September 30, 2026, and released on October 1, 2026. The full text of
this document is available at <a href="https://docs.fcc.gov/public/attachments/FCC-26-64A1.pdf">https://docs.fcc.gov/public/attachments/FCC-26-64A1.pdf</a>. The Commission also concurrently adopted a Report and
Order (Order), FCC 25-64, adopted on September 30, 2026, streamlining
the Commission's rules implementing the National Environmental Policy
Act (NEPA).
Ex Parte Rules
The proceeding this FNPRM initiates shall be treated as a ``permit-
but-disclose'' proceeding in accordance with the Commission's ex parte
rules. See 47 CFR 1.1200 et seq. Persons making ex parte presentations
must file a copy of any written presentation or a memorandum
summarizing any oral presentation within two business days after the
presentation (unless a different deadline applicable to the Sunshine
period applies). Persons making oral ex parte presentations are
reminded that memoranda summarizing the presentation must (1) list all
persons attending or otherwise participating in the meeting at which
the ex parte presentation was made, and (2) summarize all data
presented and arguments made during the presentation. If the
presentation consisted in whole or in part of the presentation of data
or arguments already reflected in the presenter's written comments,
memoranda or other filings in the proceeding, the presenter may provide
citations to such data or arguments in his or her prior comments,
memoranda, or other filings (specifying the relevant page and/or
paragraph numbers where such data or arguments can be found) in lieu of
summarizing them in the memorandum. Documents shown or given to
Commission staff during ex parte meetings are deemed to be written ex
parte presentations and must be filed consistent with rule 1.1206(b).
In proceedings governed by rule 1.49(f) or for which the Commission has
made available a method of electronic filing, written ex parte
presentations and memoranda summarizing oral ex parte presentations,
and all attachments thereto, must be filed through the electronic
comment filing system available for that proceeding, and must be filed
in their native format (e.g., .doc, .xml, .ppt, searchable .pdf).
Participants in this proceeding should familiarize themselves with the
Commission's ex parte rules.
Regulatory Flexibility Act
The Commission has prepared an Initial Regulatory Flexibility
Analysis (IRFA) concerning the potential impact of rule and policy
change proposals on small entities in the FNPRM. The Commission invites
the general public, in particular small businesses, to comment on the
IRFA. Comments must be filed by the deadlines for comments on the FNPRM
indicated on the first page of this document and must have a separate
and distinct heading designating them as responses to the IRFA.
Paperwork Reduction Act
This document may also contain proposed new or modified information
collection requirements. The Commission, as part of its continuing
effort to reduce paperwork burdens, invites the general public and the
Office of Management and Budget (OMB) to comment on any information
collection requirements contained in this document, as required by the
Paperwork Reduction Act of 1995, Public Law 104-13. In addition,
pursuant to the Small Business Paperwork Relief Act of 2002, Public Law
107-198, see 44 U.S.C. 3506(c)(4), the Commission seeks specific
comment on how the Commission might further reduce the information
collection burden for small business concerns with fewer than 25
employees.
Providing Accountability Through Transparency Act
The Providing Accountability Through Transparency Act, Public Law
118-9, requires each agency, in providing notice of a rulemaking, to
post online a brief plain-language summary of the proposed rule. The
required summary of this FNPRM is available at <a href="https://www.fcc.gov/proposed-rulemakings">https://www.fcc.gov/proposed-rulemakings</a>. To request materials in accessible formats for
people with disabilities (e.g., Braille, large print, electronic files,
audio format), send an email to <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="e1878282d4d1d5a1878282cf868e97">[email protected]</a> or call the Consumer &
Governmental Affairs Bureau at (202) 418-0530.
Synopsis
I. Further Notice of Proposed Rulemaking
1. Through this Further Notice of Proposed Rulemaking (FNPRM), the
Commission seeks additional comment on the Commission's NHPA framework,
including section 106 efficiencies. Additionally, the Commission seeks
comment on whether communications infrastructure deployments are agency
actions subject to the ESA.
A. Definition of ``Undertaking'' Under the National Historic
Preservation Act
2. In light of the decisions in the Order, the Commission seeks to
refresh the record on the meaning of ``undertaking'' and the
Commission's approach to implementing section 106 of the National
Historic Preservation Act (NHPA) as set forth in the Modernizing the
Commission's National Environmental Policy Act Rules Notice of Proposed
Rulemaking (NEPA NPRM), 90 Fed Reg 40295, published on August 19, 2025.
The Commission has built a record on the subject of whether
``undertaking'' and ``major Federal action'' are coterminous.
Therefore, no further comment on this matter is being sought in this
FNPRM. Additionally, and in light of the Commission's findings above
related to the licensing of spectrum, the Commission seeks comment on
whether activities that are part of the deployment and operation of
communications infrastructure are within the scope of ``undertaking.''
The
[[Page 66064]]
Commission also seeks comment on actions and practices that the
Commission could adopt to provide more efficiencies in the section 106
process and add greater predictability for all stakeholders.
1. Licensing of Spectrum and ``Undertaking''
3. Section 106 of the NHPA requires federal agencies to take into
account the effect of an ``undertaking on any historic property.'' The
NHPA further defines ``undertaking'' as ``a project, activity, or
program funded in whole or in part under the direct or indirect
jurisdiction of a Federal agency.'' This includes: ``(1) those carried
out by or on behalf of a Federal agency; (2) those carried out with
Federal financial assistance; (3) those requiring a Federal permit,
license or approval; and (4) those subject to State or local regulation
administered pursuant to a delegation or approval by a Federal
agency.'' The Advisory Council on Historic Preservation (ACHP) rules
afford each individual federal agency the responsibility to ``determine
whether [a] proposed Federal act to be taken by it is an undertaking.''
In its comments on the NEPA NPRM, ACHP stated that the ``FCC could use
the rulemaking process to define a list of activities that do not rise
to the level of an `undertaking' due to a lack of federal involvement
under Section 106.''
4. As discussed in the Order, the Commission licenses the use of
spectrum, not facilities. Importantly, the Commission notes that:
Commission rules do not legally require licensees to build
communications infrastructure upon receiving a spectrum authorization;
while the Commission's spectrum licensing rules manage spectrum to
ensure that it is used efficiently and to prevent harmful interference,
licensees retain control and responsibility over their facility
deployment decisions; there is an insufficient causal connection
between the Commission's licensing activity and subsequent
infrastructure deployments; buildout requirements do not require the
construction of particular facilities in any specific place and may be
satisfied without new construction; and revocation or suspension of a
spectrum license does not require dismantlement of a tower. Because of
this, the Commission seeks comment on whether the construction of
communications facilities connected with the issuance of a Commission
license for the use of spectrum should be regarded as an
``undertaking,'' where the Commission does not issue a ``permit,
license or approval'' for deployment of the facilities themselves, but
rather for the use of spectrum. To the extent the Commission clarifies
the extent to which its actions constitute undertakings, the Commission
seeks comment on whether to apply that clarification prospectively or
to existing facilities, including those built prior to 2005.
5. Finally, the Commission seeks comment on the impact of the
Commission's determination in the Order that Commission spectrum
licenses and facilities deployment in connection with spectrum licenses
are not subject to NEPA review and the Commission's related rescission
of Sec. 1.1312 of the rules on whether spectrum licensing is an
undertaking under the NHPA. The Commission previously determined that
the issuance of a geographic area license constituted an undertaking
because of the Commission's ``limited approval authority,'' in Sec.
1.1312 of the NEPA rules, which required completion of the
environmental review process prior to tower construction. The
Commission seeks comment on whether the actions in the Order, which
remove that limited approval authority, merit reconsideration of the
determination that Commission spectrum licensing activities are subject
to NHPA review.
2. Section 106 Efficiencies
6. The Commission seeks comment on whether there are efficiencies
to be gained through modifications to the Commission's NHPA procedures.
The Commission invites comment on the measures discussed below and on
any additional measures that will enable the Commission to fulfill its
section 106 commitments in a manner that minimizes delays to
infrastructure deployment for communications services.
7. Batching. To reduce repetitive submissions and paperwork for all
parties, the Commission seeks comment on whether allowing multiple
installation submissions into a single filing via the Commission's
Tower Construction Notification System (TCNS) would create
efficiencies. What challenges would this pose? The Commission invites
commenters to provide data or examples illustrating how batching may
affect administrative costs, review timelines, and overall project
delivery. In particular, the Commission is interested in whether
batching reduces repetitive paperwork, streamlines coordination among
stakeholders, or introduces new complexities.
8. Currently, batching is permitted in the context of the Positive
Train Control (PTC) Program Comment. This was a streamlined process for
certain facilities associated with building out the PTC railroad safety
system. The Commission seeks comment on the experience of the PTC
batching process. What has worked well? Has batching posed challenges?
9. If the Commission permits batching, what guidelines should be
established to realize efficiencies while minimizing drawbacks? In this
regard, should there be a limit on the number of facilities to be
batched? How should this be determined? Should geographic proximity be
a factor? In this regard, would the use of common zip codes be a useful
organizing principle for batching? Should the size of the facility be a
factor? Should shared characteristics among the facilities be a factor
(for example, the deployment of the same antenna structure or
collocation antenna in similar terrain)? Should the extent of expected
ground disturbance be a factor? Are there other factors relevant to
batching eligibility? Should batching be accompanied by different time
limits for processing? What changes to the current TCNS process might
facilitate batching? The Commission seeks comment on these and any
other policy or operational matters regarding batching that commenters
may be aware of through their experiences.
10. Non-compliant Towers. Non-compliant towers are structures that
did not previously undergo section 106 review or lack documentation of
such review, but which parties may have an interest in for collocation.
Commenters to the NEPA NPRM advocated for bringing these towers into
compliance. The Commission seeks comment on whether there should be an
initiative to facilitate collocation on such non-compliant towers. The
Commission notes that the Collocation NPA, which established
streamlined section 106 reviews for collocation infrastructure
projects, includes review of collocations on non-compliant towers under
certain circumstances. Pursuant to the Collocation NPA, however, there
would be additional streamlined processing opportunities if the towers
came into section 106 compliance. The Commission has recognized the
benefits to industry and to historic properties from collocations on
existing structures, and encourages collocation of antennas where
technically and economically feasible, in order to reduce the need for
new tower construction. The Commission seeks comment on approaches to
bringing non-compliant towers into compliance to enable future
collocation. The Commission also seeks comment on potential
efficiencies or
[[Page 66065]]
challenges associated with such approaches.
11. Geographic Areas of Interest. In the context of tribal historic
preservation review, Tribal Nations and Native Hawaiian Organizations
(NHOs) identifying areas of cultural, historical, or religious interest
for purposes of the section 106 process and TCNS, the Commission seeks
comment on any trends that have developed in the indication of
Geographic Areas of Interests since the Commission considered this
matter in 2017. If the data support a conclusion that such areas are
expanding significantly along with historic properties, the Commission
seeks comment on what practices might assist in addressing an increased
designation of Geographic Areas of Interest. Are there techniques for
increasing efficiencies that could be adopted, whether it be features
of TCNS, adjustments to Forms 620 and 621, or other techniques to
evaluate wider geographic interests without materially compromising the
section 106 process?
12. Emergency and Disaster Situations. In response to the NEPA
NPRM, a number of commenters have argued for greater efficiencies in
responding to damage to infrastructure due to weather-related incidents
to more quickly restore communications for citizens in the impacted
area. Specifically, commenters seek the ability to rebuild or fortify
structures damaged by a weather incident, natural disaster, or other
incident without reprising the section 106 process. The Commission
seeks comment on the merits of this proposal. The Commission notes that
the Wireless NPA includes existing exclusions from section 106 review
for construction of a replacement tower that does not substantially
increase the size of the tower, and for construction of a temporary
communications tower. The Commission also notes that ACHP rules set
forth alternative procedures for undertakings in response to declared
disasters or emergencies or in response to other immediate threats to
life or property. The Commission seeks comment on the sufficiency of
these existing exclusions and procedures and whether additional
efficiencies are needed. Should any section 106 efficiency addressing
emergency situations be conditioned on a certain level of damage?
Should replacement or improved infrastructure constructed pursuant to
such an efficiency be held to any historic preservation conditions
resulting from the initial section 106 process? What other
considerations are relevant to a section 106 exemption when damage to
facilities rises to a level of a communications emergency? What are the
criteria for a communications emergency? Would accessing the
Commission's established waiver process on a case-by-case basis be a
preferred approach in such emergency situations? The Commission seeks
comment on the trade-offs between applying general rules or a case-by-
case approach to emergency situations, and the Commission encourages
commenters to provide data and statistics to support the cost and
benefit estimates associated with each approach.
13. Tribal Consultation and Monitoring. In response to the NEPA
NPRM, Verizon has expressed an interest in ``more definite timelines''
for section 106 review. Specifically, Verizon maintains that in its
``experience, where Government-to-Government consultation is requested,
the Tribe's response timeline stretches from 30-60 days to an average
of 110 days.'' For this reason Verizon advocates ``narrowing the scope
of the consultation process. . . .'' Tribes also commented on the
challenges that they face with expedited timelines. The Commission
seeks comment on how often Tribal consultations extend Tribal response
timelines beyond 60 days. What specific modifications are recommended
that would resolve any timeliness issues without compromising the
integrity of the consultation process?
14. Timeline for Tribal Review Process. In the Accelerating
Wireless Broadband Deployment by Removing Barriers to Infrastructure
Investment, Second Report and Order (Wireless Broadband Deployment
Second R&O), 83 FR 19440, published May 03, 2018, the Commission
adopted the current procedures for applicants to notify Tribal Nations
and NHOs (Tribal Nations/NHOs) of proposed tower builds and
collocations, and reciprocally, for Tribal Nations/NHOs to respond by
indicating whether such proposals may affect historic properties to
which they attach religious and/or cultural significance. Specifically,
the Commission adopted a 45-day process for the applicants and Tribal
Nations/NHOs to engage after which tower construction or collocation
installations could proceed.
15. As part of this 45-day review process, applicants are required
to send submission packets to the Tribal Nations/NHO. The Tribal
Nations/NHOs have 30 calendar days to respond to the applicant's
submission packet, which begins on the date that Tribal Nations/NHOs
can be shown to have received or may reasonably be expected to have
received the relevant submission packets. If an applicant does not
receive a response within 30 calendar days of the date that Tribal
Nations/NHOs can be shown to have or may reasonably be expected to have
received the submission packet, the applicant can refer the matter to
the Commission for follow-up.
16. Within five business days after receiving the applicant's
referral, the Commission sends a letter and/or email to the Tribal
Nation's or NHO's designated cultural resource representative with a
reminder that the 30-day period for review of the submission packet has
elapsed and requesting that, within 15 calendar days of the date of the
letter and/or email, the Tribal Nation/NHO indicate its interest or
lack thereof in participating in a section 106 review. During the 15-
day period, Commission staff place phone calls to the designated
cultural resource representative. If the Tribal Nation/NHO does not
respond within 15 calendar days, the applicant's pre-construction
obligations are discharged with respect to that Tribal Nation/NHO. The
Commission concluded that pursuant to ACHP rules, these procedures
``satisfy the Commission's obligation to make reasonable and good faith
efforts to identify Tribal Nations and NHOs that may attach religious
and cultural significance to historic properties that may be affected
by an undertaking.''
17. The Commission seeks comment on whether the telephone call
component of the 45-day procedure is necessary given that the
Commission already sends a letter and/or email for the same purpose.
Since the effective date of these procedures on July 2, 2018, through
January 8, 2026, Commission staff has placed approximately 20,539
telephone calls during the 15-day period after the 30-day review period
accorded Tribal Nations/NHOs to review submission packets. These calls
consume a considerable amount of Commission staff time. In 2025 alone,
approximately 1,669 calls were placed. These calls are in addition to
letters and/or emails reminding the Tribal Nations/NHOs that the 30-day
review period has elapsed and informing them of the additional 15 days
to indicate interest or lack thereof in participating in the section
106 review before the applicant's pre-construction obligations are
considered discharged. To the extent commenters argue that these calls
are necessary, the Commission requests that commenters explain why
letters or emails are insufficient. For those advocating in favor of
retaining the phone call step, the Commission seeks comment on how this
might be done more efficiently. For example, if
[[Page 66066]]
feasible, would a recorded message be a suitable substitute for in-
person contact?
B. Definition of ``Agency Action'' Under the Endangered Species Act
18. In light of the Commission's finding in the Order above that
spectrum licensing is not an MFA, the Commission seeks comment on
whether construction of communications facilities in connection with
Commission spectrum authorizations are ``agency actions'' subject to
the ESA. As discussed in the Order and further outlined in this FNPRM,
the Commission licenses the use of spectrum, not facilities.
19. In the NEPA NPRM the Commission sought comment ``on the impact
to the Commission's other legal responsibilities if certain actions
were to fall outside NEPA for failure to qualify as MFAs.''
Additionally, commenters were invited to identify other legal
requirements that may be affected by any potential changes to the
Commission's NEPA rules consistent with the amended statute. In
response, CTIA contends that ``the Commission should make a finding
that wireless deployments that do not require ASR are not agency
`actions' under the ESA for the same basic reasons they are not MFAs
under NEPA.'' Other commenters, however, encourage the Commission to
maintain or expand its obligations under the ESA.
20. Under the ESA, an agency action ``means all activities or
programs of any kind authorized, funded, or carried out, in whole or in
part, by Federal agencies in the United States or upon the high seas.
Examples include, but are not limited to (a) actions intended to
conserve listed species or their habitat; (b) the promulgation of
regulations; (c) the granting of licenses, contracts, leases,
easements, rights-of-way, permits, or grants-in-aid; or (d) actions
directly or indirectly causing modifications to the land, water, or
air.'' Cases interpreting the definition of an ``agency action'' under
ESA compare the standard to the standard for ``major federal action''
under NEPA. However, some courts also hold that the definition of
``agency action'' should be broadly construed.
21. The Commission seeks comment on whether the construction of
communications facilities connected with the issuance of a Commission
license for the use of spectrum is an ``agency action'' where the
Commission does not grant a license or permit for deployment of the
infrastructure facilities themselves, but rather for the use of
spectrum. Commenters should explain the basis for their views or any
suggested alternatives, and comment on benefits and costs associated
with adopting their position.
II. Initial Regulatory Flexibility Analysis
22. As required by the Regulatory Flexibility Act of 1980, as
amended (RFA) the Commission has prepared this Initial Regulatory
Flexibility Analysis (IRFA) of the policies and rules proposed in the
FNPRM assessing the possible significant economic impact on a
substantial number of small entities. The Commission requests written
public comments on this IRFA. Comments must be identified as responses
to the IRFA and must be filed by the deadlines for comments specified
on the first page of the FNPRM. The Commission will send a copy of the
FNPRM, including this IRFA, to the Chief Counsel for the Small Business
Administration (SBA) Office of Advocacy. In addition, the FNPRM and
IRFA (or summaries thereof) will be published in the Federal Register.
A Need for, and Objectives of, the Proposed Rules
1. Definition of Undertaking Under the National Historic Preservation
Act
23. In the FNPRM, the Commission seeks comment on its approach to
implementing section 106 of the National Historic Preservation Act
(NHPA), including section 106 efficiencies. Specifically, the
Commission seeks to refresh the record on the meaning of
``undertaking'' and the Commission's approach to implementing section
106 of the NHPA. Additionally, and in light of the Commission's
findings related to the licensing of spectrum, the Commission seeks
comment on whether activities that are part of the deployment and
operation of communications infrastructure are within the scope of
``undertaking.'' The Commission also seeks comment on actions and
practices that the Commission could adopt to provide more efficiencies
in the section 106 process and add greater predictability for all
stakeholders.
24. The NHPA requires federal agencies to take into account the
effect of an ``undertaking on any historic property'' and the Advisory
Council on Historic Preservation's rules afford each individual federal
agency the responsibility to ``determine whether [a] proposed Federal
act to be taken by it is an undertaking.'' The Commission licenses the
use of spectrum and not facilities. Because of this, the Commission
seeks comment on whether the construction of communications facilities
connected with the issuance of a Commission license for the use of
spectrum should be regarded as an ``undertaking,'' where the Commission
does not issue a ``permit, license or approval'' for deployment of the
facilities themselves, but rather for the use of spectrum. The
Commission seeks comment on the impact of its determination that
spectrum licenses and facilities deployment in connection with spectrum
licenses are not subject to NEPA review and its related rescission of
Sec. 1.1312 of the rules on whether spectrum licensing is an
undertaking under the NHPA. The Commission also seeks comment on
whether its actions merit reconsideration of the determination that
Commission spectrum licensing activities are subject to NHPA review.
25. The Commission seeks comment on whether there are efficiencies
to be gained through modifications to the Commission's NHPA procedures.
Specifically, the Commission seeks comment on whether it should permit
batching of section 106 submissions in order to reduce repetitive
submissions and paperwork. The Commission seeks comment on possible
approaches to bringing non-compliant towers into compliance with
section 106 in order to increase the inventory of structures available
for communications facility deployment through collocation, rather than
the typically more onerous process of erecting new tower structures.
The Commission seeks comment on any trends that have developed in the
indication of Geographic Areas of Interest and what practices might
assist in addressing an increased designation of Geographic Areas of
Interest. In terms of emergency and disaster situations, the Commission
seeks comment on whether additional efficiencies are needed in
responding to damage infrastructure due to weather-related incidents to
more quickly restore communications for citizens in impacted areas. The
Commission seeks comment on Tribal consultations timelines and what
specific modifications are needed to resolve any timeliness issues
without compromising the integrity of the consultation process.
Finally, the Commission seeks comment on procedures for applicants to
notify Tribal Nations and NHOs (Tribal Nations/NHOs) of proposed tower
builds and collocations, and reciprocally, for Tribal Nations/NHOs to
respond by indicating whether such proposals may affect historic
properties to which they attach religious and/or cultural significance.
[[Page 66067]]
2. Definition of ``Agency Action'' Under the Endangered Species Act
26. In the FNPRM, the Commission also seeks comment on whether the
construction of communications facilities connected with the issuance
of a Commission license for the use of spectrum is an ``agency action''
under the Endangered Species Act (ESA) where the Commission does not
grant a license or permit for deployment of the facilities themselves,
but rather for the use of spectrum. Under the ESA, an agency action
``means all activities or programs of any kind authorized, funded, or
carried out, in whole or in part, by Federal agencies in the United
States or upon the high seas. Examples include, but are not limited to
(a) actions intended to conserve listed species or their habitat; (b)
the promulgation of regulations; (c) the granting of licenses,
contracts, leases, easements, rights-of-way, permits, or grants-in-aid;
or (d) actions directly or indirectly causing modifications to the
land, water, or air.''
B. Legal Basis
27. The proposed action is authorized pursuant to sections 1, 2,
4(i)-(j), 201, 214, 301, 302a, 303, 307, 309, 319, and 332 of the
Communications Act of 1934, as amended 47 U.S.C. 151, 152, 154(i)-(j),
201, 214, 301, 302a, 303, 307, 309, 319, and 332, section 704(b) of the
Telecommunications Act of 1996, Public Law 104-104, section 102 of the
National Environmental Policy Act of 1969, as amended, 42 U.S.C. 4332,
section 106 of the National Historic Preservation Act of 1966, as
amended, 54 U.S.C. 306108, and the Endangered Species Act of 1973, as
amended, 16 U.S.C. 1536.
C. Description and Estimate of the Number of Small Entities to Which
the Proposed Rules Will Apply
28. The RFA directs agencies to provide a description of and, where
feasible, an estimate of the number of small entities that may be
affected by the proposed rules, if adopted. The RFA generally defines
the term ``small entity'' as having the same meaning as the terms
``small business,'' ``small organization,'' and ``small governmental
jurisdiction.'' In addition, the term ``small business'' has the same
meaning as the term ``small business concern'' under the Small Business
Act (SBA). A ``small business concern'' is one which: (1) is
independently owned and operated; (2) is not dominant in its field of
operation; and (3) satisfies any additional criteria established by the
SBA. The SBA establishes small business size standards that agencies
are required to use when promulgating regulations relating to small
businesses; agencies may establish alternative size standards for use
in such programs, but must consult and obtain approval from SBA before
doing so.
29. The Commission's actions, over time, may affect small entities
that are not easily categorized at present. The Commission therefore
describes three broad groups of small entities that could be directly
affected by the Commission's actions. In general, a small business is
an independent business having fewer than 500 employees. These types of
small businesses represent 99.9% of all businesses in the United
States, which translates to 34.75 million businesses. Next, ``small
organizations'' are not-for-profit enterprises that are independently
owned and operated and not dominant their field. While the Commission
does not have data regarding the number of non-profits that meet that
criteria, over 99 percent of nonprofits have fewer than 500 employees.
Finally, ``small governmental jurisdictions'' are defined as cities,
counties, towns, townships, villages, school districts, or special
districts with populations of less than fifty thousand. Based on the
2022 U.S. Census of Governments data, the Commission estimates that at
least 48,724 out of 90,835 local government jurisdictions have a
population of less than 50,000.
30. The rules proposed in the FNPRM will apply to small entities in
the industries identified in the chart below by their six-digit North
American Industry Classification System (NAICS) codes and corresponding
SBA size standard. Based on currently available U.S. Census data
regarding the estimated number of small firms in each identified
industry, the Commission concludes that the proposed rules will impact
a substantial number of small entities. Where available, the Commission
also provides additional information regarding the number of
potentially affected entities in the industries identified below.
Table 1--2022 U.S. Census Bureau Data by NAICS Code
----------------------------------------------------------------------------------------------------------------
Regulated industry (footnotes
specify potentially affected Total small % Small
entities within a regulated NAICS code SBA size standard Total firms firms firms
industry where applicable)
----------------------------------------------------------------------------------------------------------------
Wireless Telecommunications 517112 1,500 employees......... 1,184 1,081 91.30
Carriers (except Satellite).
Satellite Telecommunications.. 517410 $44 million............. 332 195 58.73
All Other Telecommunications.. 517810 $40 million............. 1,673 1,007 60.19
----------------------------------------------------------------------------------------------------------------
Table 2--Telecommunications Service Provider Data
----------------------------------------------------------------------------------------------------------------
2024 Universal service monitoring report SBA size standard (1,500 employees)
telecommunications service provider data (data as of -------------------------------------------------------
December 2023)
--------------------------------------------------------- Total number FCC Small firms % Small entities
Affected entity Form 499A filers
----------------------------------------------------------------------------------------------------------------
Wireless Telecommunications Carriers (except Satellite). 585 498 85.13
----------------------------------------------------------------------------------------------------------------
[[Page 66068]]
D. Description of Economic Impact and Projected Reporting,
Recordkeeping, and Other Compliance Requirements for Small Entities
31. The RFA directs agencies to describe the economic impact of
proposed rules on small entities, as well as projected reporting,
recordkeeping and other compliance requirements, including an estimate
of the classes of small entities which will be subject to the
requirement and the type of professional skills necessary for
preparation of the report or record.
32. The FNPRM seeks comment on potential rule changes that may
affect reporting, recordkeeping and other compliance requirements.
Specifically, the FNPRM seeks comment on the following: (1) the
identification of ``undertaking'' in the context of the deployment of
communications facilities; (2) the batching process for submitting
multiple proposed applications for section 106 review; (3) bringing
into section 106 compliance existing towers that are non-compliant; (4)
trends that have developed in the indication of Geographic Areas of
Interest; (5) streamlining the re-establishment of communications
infrastructure capacity after damage from natural disasters and other
emergencies; and (6) modification of procedures for applicants to
notify Tribal Nations of proposed tower builds and collocations, and
reciprocally, for Tribal Nations to respond by indicating whether such
proposal may affect historic properties to which they attach religious
and/or cultural significance. The FNPRM also seeks comment on whether
the construction of communications facilities connected with the
issuance of a Commission license for the use of spectrum is an ``agency
action'' under the ESA where the Commission does not grant a license or
permit for deployment of the facilities themselves, but rather for the
use of spectrum.
33. The Commission anticipates that if the record supports a more
accurate and precise identification of the ``undertaking'' under the
NHPA for aspects of communications facilities deployment, this will not
increase the burden on small entities engaged in the section 106
process and that the expenditure of time and resources on the section
106 process will be reduced for small entities. Batching is a
streamlined process whereby section 106 analysis associated with
proposed communications infrastructure deployments may be submitted to
State Historic Preservation Officers (SHPOs) and through the Tower
Construction Notification System (TCNS) in batches instead of
individually. The FNPRM seeks comment on whether SHPOs and Tribal
Historic Preservation Officers (THPOs) should batch submissions and
under what circumstances. Presently, batching is only in use for the
deployment of communications facilities associated with the building
out the Positive Train Control (PTC) railroad safety system through the
PTC Program Comment. If batching is expanded to additional deployment
situations, this may require modifications to reporting or other
compliance requirements for small entities and/or jurisdictions to
enable such submissions. The Commission anticipates that batching
rather than individual submissions will add no additional burden to
small entities and may reduce the cost and delay associated with the
deployment of wireless infrastructure. The Commission also anticipates
that if the record supports a more accurate and precise identification
of ``agency actions'' under the ESA for aspects of communications
facilities deployment, this will not increase the burden on small
entities engaged in complying with the ESA and that the expenditure of
time and resources in complying with the ESA will be reduced for small
entities.
34. Additionally, the FNPRM seeks comment on whether and through
what procedures the Commission should act to bring into section 106
compliance existing towers that are now non-complaint. The Commission
anticipates that if the record supports adoption of a process that can
facilitate section 106 compliance that this will reduce the burden on
small entities by diminishing expenses and delays associated with the
deployment of wireless infrastructure because the number of
opportunities to collocate will increase for small entities. This
change will allow small entities to have more opportunities to avail
themselves of the multiple section 106 exclusion scenarios permitted by
the Collocation NPA.
35. The Commission also seeks comment on trends in the
identification of Geographic Areas of Interest by Tribal Nations and
NHOs. These are areas within which Tribal Nations or NHOs have
identified historic properties with religious and cultural significance
to them. The Commission seeks comment both on whether the record
includes data indicating a significant expansion of the geographic area
being selected, and, if so, on methods that might assist with
processing the enlarged geographic scope. If such methods are
meritorious, the Commission anticipates that the time and resource
burden expended on the section 106 process would be reduced for small
entities.
36. The Commission also seeks comment on whether the repair or
replacement of a damaged tower structure that results in a
communication capacity emergency should be able to proceed without
section 106 review in circumstances in which section 106 review had
been completed for the structure at that site prior to it being
damaged. The Commission anticipates that if the record supports
adoption of this approach, this will reduce the burden on small
entities of re-establishing communications capacity in emergency
situations. The Commission also seeks comment regarding whether Tribal
Nation requests for Government-to-Government consultation concerning
the proposed deployment of communications infrastructure have a
material effect on the timing of these deployments, and, if so, what
modifications could be adopted to ameliorate timing delays without
compromising the integrity of these consultations. The Commission
anticipates that if the record supports both a determination that these
consultations generally have a material impact on the timing of
facilities deployment, and the adoption of adjustments that can shorten
the timetable while preserving the integrity of the consultation
process, that small entities will benefit in terms of saved time and
resources expended to accomplish facilities deployments.
37. Finally, the FNPRM seeks comment on more definite timelines for
section 106 review. The Commission current rules provide procedures for
applicants to notify Tribal Nations and NHOs (Tribal Nations/NHOs) of
proposed tower builds and collocations, and reciprocally, for Tribal
Nations/NHOs to respond by indicating whether such proposals may affect
historic properties to which they attach religious and/or cultural
significance. Changes to these rules should benefit small entities by
making for a more standardized and efficient process and implementation
of these changes should save small entities resources. Such
modifications should resolve timeliness issues without compromising the
integrity of the consultation process.
38. At this time, the Commission cannot quantify the potential cost
savings of any rules changes discussed in the FNPRM, should they be
adopted. The Commission does not believe that small entities would need
to hire professionals in order for them to comply with the proposed
rules. As part of the Commission's invitation for
[[Page 66069]]
comment by interested parties, however, the Commission requests that
any small entities participating in the comment process discuss any
benefits or drawbacks associated with the proposed approaches, provide
information on their current costs of compliance with the Commission's
existing rules, as well as provide data and information on any
differential impacts faced by small entities. The Commission expects
the information the Commission receives in comments to help the
Commission identify and evaluate relevant matters for small entities,
including compliance costs, and identify other burdens that may result
from the matters raised in the FNPRM.
E. Discussion of Significant Alternatives Considered That Minimize the
Significant Economic Impact on Small Entities
39. The RFA directs agencies to provide a description of any
significant alternatives to the proposed rules that would accomplish
the stated objectives of applicable statutes, and minimize any
significant economic impact on small entities. The discussion is
required to include alternatives such as: ``(1) the establishment of
differing compliance or reporting requirements or timetables that take
into account the resources available to small entities; (2) the
clarification, consolidation, or simplification of compliance and
reporting requirements under the rules for such small entities; (3) the
use of performance rather than design standards; and (4) an exemption
from coverage of the rule, or any part thereof, for such small
entities.
40. In developing its proposals in the FNPRM for minimizing
significant economic impact on small entities, the Commission
considered significant alternatives. The Commission will continue to
consider a number of approaches to refining its section 106 processing
rules, including by seeking comment on whether to expand the batching
approach to section 106 submissions. The Commission will also consider
the record in refining its compliance with the ESA. Part of the
determination process will include consideration of savings in time and
financial resources for small entities.
41. In addition, the FNPRM invites comment from small entities on
alternative approaches in which the Commission could refine its
historic preservation section 106 processing rules and its compliance
with ESA in ways that will reduce economic impact and regulatory
burdens on project sponsors. The Commission then will decide what
actions it should take based on the subsequently developed record. Part
of the decisional process will include evaluating the impact of these
decisions on small entities and what alternatives the Commission might
adopt to lessen significant economic impacts and regulatory burdens on
small entities. The Commission will consider alternative proposals and
approaches from commenters that would minimize the economic impact on
small entities. The Commission's evaluation of the comments filed in
this proceeding will shape the final conclusions it reaches, the final
alternatives it considers, and the actions it ultimately takes to
minimize any significant economic impact that may occur on small
entities from the final rules.
F. Federal Rules That May Duplicate, Overlap, or Conflict With the
Proposed Rules
42. None.
III. Ordering Clauses
43. It is ordered, pursuant to sections 4(i), 301, 302, 303(r),
308, 309, and 333 of the Communications Act of 1934, 47 U.S.C. 154(i),
301, 302a, 303(r), 308, 309, 333, that this Further Notice of Proposed
Rulemaking, is adopted as set forth above.
44. It is further ordered that the Office of the Secretary shall
send a copy of this Further Notice of Proposed Rulemaking, including
the Initial Regulatory Flexibility Analyses, to the Chief Counsel for
Advocacy of the Small Business Administration.
Federal Communications Commission
Marlene Dortch,
Secretary, Office of the Secretary.
[FR Doc. 2026-21347 Filed 10-16-26; 8:45 am]
BILLING CODE 6712-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.