Blue Energy Global, Inc.; Blue Energy Center-Port of Victoria Nuclear Unit 1; Phased Construction Permit Application-Limited Work Authorization
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
The U.S. Nuclear Regulatory Commission (NRC) has received the first part of a phased construction permit application, including a limited work authorization (LWA) request, from Blue Energy Global, Inc., for a single-unit BWRX-300 plant to be located at the Blue Energy Center in Victoria, Texas. The unit is named Blue Energy Center--Port of Victoria Nuclear Unit 1.
Full Text
<html>
<head>
<title>Federal Register, Volume 91 Issue 194 (Thursday, October 8, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 194 (Thursday, October 8, 2026)]
[Notices]
[Pages 64409-64410]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-20678]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 99902137; NRC-2026-4654]
Blue Energy Global, Inc.; Blue Energy Center--Port of Victoria
Nuclear Unit 1; Phased Construction Permit Application--Limited Work
Authorization
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice; receipt.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has received the
first part of a phased construction permit application, including a
limited work authorization (LWA) request, from Blue Energy Global,
Inc., for a single-unit BWRX-300 plant to be located at the Blue Energy
Center in Victoria, Texas. The unit is named Blue Energy Center--Port
of Victoria Nuclear Unit 1.
DATES: October 8, 2026.
ADDRESSES: Please refer to Docket ID NRC-2026-4654 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
<bullet> Federal Rulemaking website: Go to <a href="https://www.regulations.gov">https://www.regulations.gov</a> and search for Docket ID NRC-2026-4654. Address
questions about Docket IDs in <a href="http://Regulations.gov">Regulations.gov</a> to Bridget Curran;
telephone: 301-415-1003; email: <a href="/cdn-cgi/l/email-protection#1e5c6c777a797b6a305d6b6c6c7f705e706c7d30797168"><span class="__cf_email__" data-cfemail="a0e2d2c9c4c7c5d48ee3d5d2d2c1cee0ced2c38ec7cfd6">[email protected]</span></a>. For technical
questions, contact the individual(s) listed in the For Further
Information Contact'' section of this document.
<bullet> NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at <a href="https://www.nrc.gov/reading-rm/adams.html">https://www.nrc.gov/reading-rm/adams.html</a>. To begin the search, select ``Begin ADAMS Public Search.''
For problems with ADAMS, please contact the NRC's Public Document Room
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email
to <a href="/cdn-cgi/l/email-protection#b0e0f4e29ee2d5c3dfc5c2d3d5f0dec2d39ed7dfc6"><span class="__cf_email__" data-cfemail="f6a6b2a4d8a493859983849593b6988495d8919980">[email protected]</span></a>. The Blue Energy Limited Work Authorization
application is available in ADAMS under Package Accession No.
ML26265A371.
[[Page 64410]]
<bullet> NRC's PDR: The PDR, where you may examine and order copies
of publicly available documents, is open by appointment. To make an
appointment to visit the PDR, please send an email to
<a href="/cdn-cgi/l/email-protection#bfeffbed91eddaccd0cacddcdaffd1cddc91d8d0c9"><span class="__cf_email__" data-cfemail="bfeffbed91eddaccd0cacddcdaffd1cddc91d8d0c9">[email protected]</span></a> or call 1-800-397-4209 or 301-415-4737, between 8
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except
Federal holidays.
FOR FURTHER INFORMATION CONTACT: Prosanta Chowdhury, telephone: 301-
415-1647; email: <a href="/cdn-cgi/l/email-protection#b9e9cbd6cad8d7cdd897fad1d6ceddd1cccbc0f9d7cbda97ded6cf"><span class="__cf_email__" data-cfemail="57072538243639233679143f3820333f22252e1739253479303821">[email protected]</span></a> and Jackson Barth,
telephone: 240-290-2848; email: <a href="/cdn-cgi/l/email-protection#440e25272f372b2a6a062536302c042a36276a232b32"><span class="__cf_email__" data-cfemail="4f052e2c243c2021610d2e3d3b270f213d2c61282039">[email protected]</span></a>. Both are staff
of the Office of Advanced Reactors at the U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Discussion
On September 15, 2026, Blue Energy, Inc., filed with NRC, the first
part of a phased construction permit application for a utilization
facility pursuant to Section 103 of the Atomic Energy Act and part 50
of title 10 of the Code of Federal Regulations (10 CFR), ``Domestic
Licensing of Production and Utilization Facilities.'' Part 1 of the
application includes an LWA request pursuant to 10 CFR 50.10(d),
``Request for limited work authorization.'' Blue Energy's LWA
application requests NRC approval to conduct certain early construction
activities for a BWRX-300 plant at the Blue Energy Center--Port of
Victoria Nuclear Unit 1 site located in Victoria, Texas. The submittal
includes two related exemption requests as well as an environmental
report and applicable portions of the preliminary safety analysis
report to support the LWA and exemption reviews. The information
submitted by the applicant also includes certain administrative
information such as financial qualifications submitted pursuant to 10
CFR 50.33 as well as technical information submitted pursuant to 10 CFR
50.34. Blue Energy, Inc., submitted Part 1 of its application as part
of a phased application approach for a construction permit for a
utilization facility, as described in 10 CFR 2.101(a)(9) and 10 CFR
2.600(d). Blue Energy, Inc., intends to submit a full construction
permit application no later than 18 months after this Part 1 submittal.
II. Further Information
If the NRC staff finds the Part 1 of the phased construction permit
application acceptable for docketing, the staff will begin a detailed
technical review. Subsequent Federal Register notices will address the
acceptability of the tendered application for docketing and
opportunities for participation of the public during the course of the
staff's review.
A copy of the application is available for public inspection at
<a href="https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with/pre-application-activities/blue-energy">https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with/pre-application-activities/blue-energy</a>.
Authority: 42 U.S.C. 2011 et seq.
Dated: October 6, 2026.
For the Nuclear Regulatory Commission.
Jorge Hernandez Munoz,
Acting Chief, Advanced Reactor Licensing Branch 4, Division of Advanced
Reactor Licensing, Office of Advanced Reactors.
[FR Doc. 2026-20678 Filed 10-7-26; 8:45 am]
BILLING CODE 7590-01-P