Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
October 8, 2026
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 91 Issue 194 (Thursday, October 8, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 194 (Thursday, October 8, 2026)]
[Notices]
[Page 64366]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-20658]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3031-001]
Shoshone Irrigation District; Notice of Existing Licensee's
Failure To File a Timely Notice of Intent To File a New License
Application, and Soliciting Notices of Intent To File a License
Application and Pre-Application Documents
The current license for Garland Canal Project No. 3031 was issued
to the original licensee, Shoshone Irrigation District, on October 9,
1981.\1\ The original license was issued for a term of 50 years, ending
August 31, 2031. The 2.61-megawatt (MW) project is located on Garland
Irrigation Canal in Park County, Wyoming.
---------------------------------------------------------------------------
\1\ See Shoshone Irrigation District, 17 FERC ] 62,013 (1981).
---------------------------------------------------------------------------
The project consists of: (1) drop structure and intake; (2) a 10-
foot by 10-foot concrete penstock approximately 2,400-feet-long; (3) a
concrete powerhouse consisting of one generating unit rated at 2.6 MW;
(4) a substation located adjacent to the powerhouse; (5) 4.16 kilovolt
(kV) generator leads connecting to a step-up transformer bank; (5) 12.5
kV transmission line; (7) tailrace; and (8) appurtenant facilities.
At least five years before the expiration of a license, the
Commission's regulations require the licensee to file with the
Commission a notice of intent (NOI) that contains an unequivocal
statement of the licensee's intention to file or not to file an
application for a new license, details on the principal project works
and installed plant capacity, and other information.\2\ Pursuant to 18
CFR 16.23, an existing licensee that fails to file an NOI at least 5
years before the existing license expires shall be deemed to have filed
a notice indicating that it does not intend to file an application to
relicense its project. Additionally, pursuant to 18 CFR 16.24, an
existing licensee that informs the Commission that it does not intend
to file an application, may not file an application to relicense its
project, either individually or in conjunction with an entity or
entities that are not currently licensees of the project.
---------------------------------------------------------------------------
\2\ 18 CFR 16.6 (2025).
---------------------------------------------------------------------------
Because the current license expires on September 30, 2031, the NOI
was due to be filed no later than the close of business on September
30, 2026. Shoshone Irrigation District failed to file an NOI by this
date.
Any party interested in filing a license application for the
Garland Canal Project No. 3031 must first file a NOI \3\ and pre-
application document (PAD) \4\ pursuant to Part 5 of the Commission's
regulations. Although the integrated licensing process is the default
pre-filing process, section 5.3(b) of the Commission's regulations
allows a potential license applicant to request to use alternative
licensing procedures when it files its NOI.\5\
---------------------------------------------------------------------------
\3\ 18 CFR 5.5 (2025).
\4\ Id. at Sec. 5.6.
\5\ Id. at Sec. 5.3(b).
---------------------------------------------------------------------------
This notice sets a deadline of 120 days from the date of this
notice for interested applicants, other than the existing licensee, to
file NOIs, PADs, and requests to use an alternative licensing process.
Applications for a new license from potential (non-licensee)
applicants must be filed with the Commission at least 24 months prior
to the expiration of the current license.\6\ Because the current
license expires on September 30, 2031, applications for license for
this project must be filed by September 30, 2029.\7\
---------------------------------------------------------------------------
\6\ Id. at Sec. 16.20.
\7\ To the extent an interested applicant files an NOI and PAD
and elects or is required to use the Commission's ILP, a process
plan will be issued within 180 days of this notice, which
accelerates the steps of the ILP to allow for filing a subsequent
license application by the September 30, 2029 deadline.
---------------------------------------------------------------------------
For public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, contact the Office
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#8bc4dbdbcbedeef9e8a5ece4fd"><span class="__cf_email__" data-cfemail="a4ebf4f4e4c2c1d6c78ac3cbd2">[email protected]</span></a>.
Questions concerning this notice should be directed to Lauren
Townson at (202) 502-8572 or <a href="/cdn-cgi/l/email-protection#024e637770676c2c566d756c716d6c42646770612c656d74"><span class="__cf_email__" data-cfemail="b1fdd0c4c3d4df9fe5dec6dfc2dedff1d7d4c3d29fd6dec7">[email protected]</span></a>.
(Authority: 18 CFR 2.1)
Dated: October 5, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-20658 Filed 10-7-26; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>