Skip to main content
Notice2026-19983

Sabine Pass Liquefaction, LLC, Sabine Pass Liquefaction Stage V, LLC, Sabine Crossing Pipeline, LLC, Cheniere Creole Trail Pipeline, L.P.; Notice of Availability of the Final Environmental Impact Statement for the Proposed Sabine Pass Stage 5 Expansion Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 30, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 188 (Wednesday, September 30, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 188 (Wednesday, September 30, 2026)]
[Notices]
[Pages 61844-61845]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-19983]



[[Page 61844]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP24-75-001; Docket No. CP25-505-000; Docket No. CP25-506-
000]


Sabine Pass Liquefaction, LLC, Sabine Pass Liquefaction Stage V, 
LLC, Sabine Crossing Pipeline, LLC, Cheniere Creole Trail Pipeline, 
L.P.; Notice of Availability of the Final Environmental Impact 
Statement for the Proposed Sabine Pass Stage 5 Expansion Project

    The staff of the Federal Energy Regulatory Commission (Commission) 
have prepared a final environmental impact statement (EIS) for the 
Sabine Pass Stage 5 Expansion Project (Project), proposed by Sabine 
Pass Liquefaction, LLC; Sabine Pass Liquefaction Stage V, LLC; Sabine 
Crossing Pipeline, LLC; and Cheniere Creole Trail Pipeline, L.P. 
(collectively, the Applicants).\1\ The Applicants propose to expand the 
existing Sabine Pass Liquefied Natural Gas (SPLNG) Terminal facility in 
Cameron Parish, Louisiana by adding three new liquefaction trains and 
appurtenant facilities; construct and operate the Sabine Crossing 
Pipeline (SCPL), a new, 48-inch-diameter, 55.6-mile-long natural gas 
pipeline as well as one new compressor station, six new meter stations, 
and other new appurtenant facilities in Liberty, Chambers, and 
Jefferson Counties, Texas and Cameron Parish, Louisiana; and construct 
and operate the new greenfield Tarpon Compressor Station in Cameron 
Parish, Louisiana, expand the existing Gillis Compressor Station in 
Beauregard Parish, Louisiana, and modify an existing delivery meter 
station in Cameron Parish, Louisiana, all along the existing Creole 
Trail Pipeline System (CTPL).
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is FERC/EISX-019-20-000-1751972136.
---------------------------------------------------------------------------

    FERC is the lead federal agency for authorizing interstate natural 
gas transmission facilities under the Natural Gas Act of 1938 (NGA) and 
the lead federal agency for preparation of the final EIS. The final EIS 
assesses the potential environmental effects of the construction and 
operation of the SPLNG Terminal Expansion, SCPL and SCPL Aboveground 
Facilities, and CTPL Aboveground Facilities (collectively referred to 
as ``the Project'') in accordance with the requirements of the National 
Environmental Policy Act (NEPA) \2\ and the Commission's implementing 
regulations.\3\ The principal purposes of the final EIS are to: 
identify and assess the potential effects on the natural and human 
environment; describe and evaluate reasonable alternatives; identify 
and recommend mitigation measures; and facilitate public involvement in 
the environmental review process. The EIS concludes that for most 
resources, the construction and operation of the Project would result 
in limited environmental effects. Most environmental effects would be 
temporary or short-term during construction, but some long-term and 
permanent environmental effects would occur in wetlands, forested 
lands, visual resources, and on air quality. This determination is 
based on our review of the information provided by the Applicants and 
further developed from environmental information requests; scoping; 
literature research; consideration of potential alternatives; contacts 
with federal, state, and local agencies; and other stakeholders. We 
conclude that effects would be less than significant with 
implementation of the Applicants' proposed avoidance, minimization, and 
mitigation measures as well as the environmental and engineering 
conditions we recommend the Commission include in any Project 
authorization it may issue. In addition, based on a preliminary 
engineering and technical review of the SPLNG Terminal Expansion 
design, we conclude there are acceptable layers of protection or 
safeguards that would reduce the risk of a potentially hazardous 
scenario from developing into an event that could impact the offsite 
public.
---------------------------------------------------------------------------

    \2\ National Environmental Policy Act of 1969, as amended 
(Public Law [Pub. L.] 91-190. 42 U.S.C. 4321-4347, as amended by 
Pub. L. 94-52, July 3, 1975; Pub. L. 94-83, August 9, 1975; Pub. L. 
97-258, 4(b), September 13, 1982; Pub. L. 118-5, June 3, 2023; Pub. 
L. 119-21, July 4, 2025).
    \3\ 18 Code of Federal Regulations (CFR) 380.
---------------------------------------------------------------------------

    Two districts of the U.S. Army Corps of Engineers, the U.S. 
Department of Transportation, the U.S. Coast Guard, the National 
Oceanic and Atmospheric Administration--National Marine Fisheries 
Service, and the U.S. Department of Energy participated as cooperating 
agencies in the preparation of the final EIS. Cooperating agencies have 
jurisdiction by law or special expertise with respect to resources 
potentially affected by the proposal and participate in the NEPA 
analysis. Although the cooperating agencies provided input towards the 
conclusions and recommendations presented in the final EIS, the 
agencies will present their own conclusions and recommendations in 
their respective records of decision (where applicable) for the 
Projects.
    The final EIS addresses the potential environmental effects of 
construction and operation in Texas and Louisiana of the following 
facilities:
    <bullet> SPLNG Terminal Expansion:
    [cir] Three new Liquefaction Trains (Trains 7, 8 and 9) and 
appurtenant facilities.
    <bullet> SCPL:
    [cir] Approximately 55.6 miles of 48-inch-diameter pipeline.
    [cir] SCPL Aboveground Facilities:
    [ssquf] Four 52,500-horsepower (hp) modular compressor packages and 
appurtenant facilities at the new Hamshire Compressor Station along the 
pipeline route;
    [ssquf] Six new meter stations (i.e., Moss Bluff, two at Winnie, 
Kinder Morgan Tejas, Hamshire, SCPL Delivery) along the pipeline route; 
and
    [ssquf] Four new pig traps \4\ and three new mainline valves (MLV) 
along the pipeline route.
---------------------------------------------------------------------------

    \4\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes. A pig trap is an 
ancillary item of pipeline equipment, with associated pipework and 
valves, for introducing a pig into a pipeline or removing a pig from 
a pipeline.
---------------------------------------------------------------------------

    <bullet> CTPL Aboveground Facilities:
    [cir] Two 23,470-hp compressor packages and appurtenant facilities 
at the existing Gillis Compressor Station along the existing pipeline 
system;
    [cir] One 52,500-hp modular compressor package and appurtenant 
facilities at the new Tarpon Compressor Station along the existing 
pipeline system; and
    [cir] One new 16-inch-diameter meter and flow control run and one 
new filter at an existing meter station within the SPLNG Terminal.
    The Commission mailed a copy of the Notice of Availability of the 
final EIS to federal, state, and local government representatives and 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; potentially affected landowners and other 
interested individuals and groups; and newspapers and libraries in the 
project area. The final EIS is only available in electronic format. It 
may be viewed and downloaded from the FERC's website (<a href="http://www.ferc.gov">www.ferc.gov</a>), on 
the natural gas environmental documents page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). In 
addition, the final EIS may be accessed by using the eLibrary link on 
the FERC's website. Click on the eLibrary link (<a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>) select ``General Search'' and enter 
the docket

[[Page 61845]]

number in the ``Docket Number'' field, excluding the last three digits 
(i.e., CP24-75, CP25-505 or CP25-506). Be sure you have selected an 
appropriate date range. For assistance, please contact FERC Online 
Support at <a href="/cdn-cgi/l/email-protection#387e5d4a5b77565451565d6b4d4848574a4c785e5d4a5b165f574e"><span class="__cf_email__" data-cfemail="f3b5968190bc9d9f9a9d96a08683839c8187b395968190dd949c85">[email&#160;protected]</span></a> or toll free at (866) 208-3676, 
or for TTY, contact (202) 502-8659.
    The final EIS is not a decision document. It presents Commission 
staff's independent analysis of the environmental issues for the 
Commission to consider when addressing the merits of all issues in this 
proceeding. Under Section 3 of the NGA, the FERC considers as part of 
its decision to authorize natural gas facilities, all factors bearing 
on the public interest. Specifically, regarding whether to authorize 
natural gas facilities used for importation or exportation, the FERC 
shall authorize the proposal unless it finds that the proposed 
facilities will not be consistent with the public interest. Under 
section 7(c) of the NGA, the Commission determines whether interstate 
natural gas transportation facilities are in the public convenience and 
necessity and, if so, grants a Certificate of Public Convenience and 
Necessity to construct and operate them. The Commission bases its 
decisions on both economic issues, including need, and environmental 
effects.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#9bd4cbcbdbfdfee9f8b5fcf4ed"><span class="__cf_email__" data-cfemail="39766969795f5c4b5a175e564f">[email&#160;protected]</span></a>. Additional 
information about the project is available from the FERC website 
(<a href="http://www.ferc.gov">www.ferc.gov</a>) using the eLibrary link. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription that allows you to keep track of all formal issuances and 
submittals in specific dockets. This can reduce the amount of time you 
spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to 
register for eSubscription.

(Authority: 18 CFR 2.1)

    Dated: September 25, 2026.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2026-19983 Filed 9-29-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on September 30, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.