Breaker Water & Energy Park, LLC; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 30, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 188 (Wednesday, September 30, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 188 (Wednesday, September 30, 2026)]
[Notices]
[Pages 61839-61840]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-19981]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD26-5-000]


Breaker Water & Energy Park, LLC; Notice of Preliminary 
Determination of a Qualifying Conduit Hydropower Facility and 
Soliciting Comments and Motions To Intervene

    On September 21, 2026, and supplemented on September 25, 2026, 
Breaker Water & Energy Park, LLC, filed a notice of intent to construct 
a qualifying conduit hydropower facility, pursuant to section 30 of the 
Federal Power Act (FPA). The proposed Buckeye Hydrokinetic Project 
would have an installed capacity of 8 kilowatts (kW) and would be 
located along the Buckeye Water Conservation and Drainage District's 
Buckeye Main Canal, near Buckeye, Maricopa County, Arizona.
    Applicant Contact: Ryan Cook, 1115 Howell Mill Rd. NW, Atlanta, 
Georgia 30318, 614-619-0038, <a href="/cdn-cgi/l/email-protection#62101b030c4c010d0d0922070f10051b4c010d0f"><span class="__cf_email__" data-cfemail="cbb9b2aaa5e5a8a4a4a08baea6b9acb2e5a8a4a6">[email&#160;protected]</span></a>.
    FERC Contact: Christopher Chaney, 202-502-6778, 
<a href="/cdn-cgi/l/email-protection#ddbeb5afb4aea9b2adb5b8aff3beb5bcb3b8a49dbbb8afbef3bab2ab"><span class="__cf_email__" data-cfemail="c1a2a9b3a8b2b5aeb1a9a4b3efa2a9a0afa4b881a7a4b3a2efa6aeb7">[email&#160;protected]</span></a>.
    Qualifying Conduit Hydropower Facility Description: The project 
would consist of: (1) one 8-kW modular hydrokinetic turbine, and (2) 
and appurtenant facilities.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
      Statutory provision              Description       Satisfies (Y/N)
------------------------------------------------------------------------
FPA 30(a)(3)(A)................  The conduit the                      Y
                                  facility uses is a
                                  tunnel, canal,
                                  pipeline, aqueduct,
                                  flume, ditch, or
                                  similar manmade water
                                  conveyance that is
                                  operated for the
                                  distribution of water
                                  for agricultural,
                                  municipal, or
                                  industrial
                                  consumption and not
                                  primarily for the
                                  generation of
                                  electricity.
FPA 30(a)(3)(C)(i).............  The facility is                      Y
                                  constructed,
                                  operated, or
                                  maintained for the
                                  generation of
                                  electric power and
                                  uses for such
                                  generation only the
                                  hydroelectric
                                  potential of a non-
                                  federally owned
                                  conduit.
FPA 30(a)(3)(C)(ii)............  The facility has an                  Y
                                  installed capacity
                                  that does not exceed
                                  40 megawatts.
FPA 30(a)(3)(C)(iii)...........  On or before August 9,               Y
                                  2013, the facility is
                                  not licensed, or
                                  exempted from the
                                  licensing
                                  requirements of Part
                                  I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: The proposed Buckeye Hydrokinetic 
Project will not alter the primary purpose of the conduit, which is for 
agricultural consumption. Therefore, based upon the above criteria, 
Commission staff

[[Page 61840]]

preliminarily determines that the operation of the project described 
above satisfies the requirements for a qualifying conduit hydropower 
facility, which is not required to be licensed or exempted from 
licensing.
    Comments and Motions to Intervene: Deadline for filing comments, 
comments contesting whether the facility meets the qualifying criteria, 
and motions to intervene: October 26, 2026, 5:00 p.m. Eastern Time.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS,'' ``COMMENTS CONTESTING 
QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY,'' or ``MOTION TO 
INTERVENE,'' as applicable; (2) state in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) state the name, address, and telephone number of the 
person filing; and (4) otherwise comply with the requirements of 
sections 385.2001 through 385.2005 of the Commission's regulations.\1\ 
All comments contesting Commission staff's preliminary determination 
that the facility meets the qualifying criteria must set forth their 
evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2025).
---------------------------------------------------------------------------

    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#afe0ffffefc9caddcc81c8c0d9"><span class="__cf_email__" data-cfemail="cb849b9b8badaeb9a8e5aca4bd">[email&#160;protected]</span></a>.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at <a href="http://www.ferc.gov/docs-filing/efiling.asp">http://www.ferc.gov/docs-filing/efiling.asp</a>. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#8fc9caddccc0e1e3e6e1eadcfaffffe0fdfbcfe9eafdeca1e8e0f9"><span class="__cf_email__" data-cfemail="aaeceff8e9e5c4c6c3c4cff9dfdadac5d8deeacccfd8c984cdc5dc">[email&#160;protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may send a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent 
via any other carrier must be addressed to: Debbie-Anne A. Reese, 
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, 
Rockville, MD 20852. A copy of all other filings in reference to this 
application must be accompanied by proof of service on all persons 
listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 385.2010.
    Locations of Notice of Intent: The Commission provides all 
interested persons an opportunity to view and/or print the contents of 
this document via the internet through the Commission's website at 
<a href="http://www.ferc.gov/docs-filing/elibrary.asp">http://www.ferc.gov/docs-filing/elibrary.asp</a>. Enter the docket number 
(i.e., CD26-5) in the docket number field to access the document. You 
may also register online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be notified via email of new filings and issuances 
related to this or other pending projects. Copies of the notice of 
intent can be obtained directly from the applicant. For assistance, 
call toll-free 1-866-208-3676 or email <a href="/cdn-cgi/l/email-protection#165053445559787a7f787345636666796462567073647538717960"><span class="__cf_email__" data-cfemail="f3b5b6a1b0bc9d9f9a9d96a08683839c8187b395968190dd949c85">[email&#160;protected]</span></a>. For 
TTY, call (202) 502-8659.

(Authority: 18 CFR 2.1)

    Dated: September 25, 2026.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2026-19981 Filed 9-29-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>