Marine Protection: Modification To Expand Ocean Dredged Material Disposal Sites Offshore of Corpus Christi, Texas

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 28, 2026
Effective
October 28, 2026

Issuing agencies

Environmental Protection Agency

Abstract

The Environmental Protection Agency (EPA) is issuing a rule that modifies the existing EPA-designated ocean dredged material disposal sites (ODMDSs) offshore of Corpus Christi, Texas; specifically, the Corpus Christi Ship Channel (CCSC) ODMDS and the Corpus Christi New Work (CCNW) ODMDS to serve the long-term need for locations to dispose of suitable material dredged from the Corpus Christi Bay area. The modified sites will be subject to monitoring and management to ensure continued protection of the marine environment.

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 186 (Monday, September 28, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 186 (Monday, September 28, 2026)]
[Rules and Regulations]
[Pages 61138-61144]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-19745]


=======================================================================
-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 228

[EPA-R06-OW-2025-3359; FRL 13119-02-R6]


Marine Protection: Modification To Expand Ocean Dredged Material 
Disposal Sites Offshore of Corpus Christi, Texas

AGENCY: Environmental Protection Agency (EPA).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Environmental Protection Agency (EPA) is issuing a rule 
that modifies the existing EPA-designated ocean dredged material 
disposal sites (ODMDSs) offshore of Corpus Christi, Texas; 
specifically, the Corpus Christi Ship Channel (CCSC) ODMDS and the 
Corpus Christi New Work (CCNW) ODMDS to serve the long-term need for 
locations to dispose of suitable material dredged from the Corpus 
Christi Bay area. The modified sites will be subject to monitoring and 
management to ensure continued protection of the marine environment.

DATES: The final rule is effective on October 28, 2026.

ADDRESSES: The EPA has established a docket for this action under 
Docket No. EPA-R06-OW-2025-3359. All documents in the docket are listed 
on the Federal e-Rulemaking Portal: <a href="http://www.regulations.gov">http://www.regulations.gov</a>.

FOR FURTHER INFORMATION CONTACT: Wendy Jacques, Environmental 
Protection Agency, Region 6, Water Division, Marine Coastal and 
Nonpoint Source Section (6WD-AM) (R06-WD-APB-MCNSS), 1201 Elm Street, 
Suite 500, Dallas, TX 75270; telephone number: 214-665-7395; email 
address: <a href="/cdn-cgi/l/email-protection#0b616a687a7e6e78257c6e656f724b6e7b6a256c647d"><span class="__cf_email__" data-cfemail="167c77756763736538617378726f5673667738717960">[email&#160;protected]</span></a>. Further information is available via 
the EPA website at <a href="https://www.epa.gov/marine-protection-permitting/marine-protection-permitting-epa-region-6">https://www.epa.gov/marine-protection-permitting/marine-protection-permitting-epa-region-6</a>.

SUPPLEMENTARY INFORMATION:

Table of Contents

I. Potentially Affected Persons
II. Background
III. Environmental Statutory Review
IV. Response to Comments
V. Statutory and Executive Order Reviews

I. Potentially Affected Persons

    Persons potentially affected by this action include those who seek 
or might seek permits or approval to dispose of dredged material into 
ocean waters pursuant to the Marine Protection, Research and 
Sanctuaries Act (MPRSA) (See 33 U.S.C. 1401 et seq). The EPA's action 
is therefore relevant to persons, including dredging entities and 
government bodies, seeking to dump dredged material in ocean waters 
offshore of Corpus Christi, Texas (currently, the U.S. Army Corps of 
Engineers (USACE) and other persons with permits to use designated 
sites offshore of Corpus Christi, Texas), as well as persons interested 
in protection of the marine environment. Potentially affected 
categories and persons include:

------------------------------------------------------------------------
                                             Examples of potentially
                Category                        regulated persons
------------------------------------------------------------------------
Federal Government.....................  USACE Civil Works projects and
                                          other Federal agencies.
Industry and general public............  Port authorities, marinas and
                                          harbors, shipyards and marine
                                          repair facilities, berth
                                          owners.
State, local and Tribal governments....  Governments owning and/or
                                          responsible for ports,
                                          harbors, and/or berths,
                                          government agencies requiring
                                          disposal of dredged material
                                          associated with public works
                                          projects.
------------------------------------------------------------------------

    The table above is not intended to be exhaustive but rather 
provides a guide for readers regarding persons likely to be affected by 
this action. For any questions regarding the applicability of this 
action to a particular entity, please refer to the contact person 
listed in the preceding FOR FURTHER INFORMATION CONTACT section.

[[Page 61139]]

II. Background

A. History of Disposal Sites Offshore of Corpus Christi, Texas

    Dredged material was first disposed at the Corpus Christi Ship 
Channel Ocean Dredged Material Disposal Site (CSC ODMDS) location in 
1969, prior to the enactment of the Marine Protection, Research and 
Sanctuaries Act (MPRSA) in 1972. In 1977, the EPA designated a disposal 
site that partially overlaps the existing site under MPRSA on an 
interim basis. In 1989, after a more recent siting analysis during the 
designation of the CCSC ODMDS, the EPA took action to exclude a portion 
of the interim site from consideration for additional disposal of 
dredged material due to the portion's proximity to a biologically 
sensitive area. Suitable dredged material from the regular maintenance 
dredging of the Corpus Christi Ship Channel may be disposed at the CCSC 
ODMDS.
    The existing Corpus Christi New Work (CCNW) ODMDS, previously 
referred to as the New Work ODMDS, was designated in 1988 to provide a 
disposal area for both maintenance and new work material from the U.S. 
Navy's Homeport Project at Corpus Christi/Ingleside, Texas. The Navy 
did not proceed with the project, and the EPA subsequently re-
designated the site for one-time disposal of native channel improvement 
construction (new work) material.
    The EPA is modifying the existing CCSC and CCNW ODMDSs boundaries 
by expanding the area covered by the ODMDSs rather than designating a 
new ocean disposal site or multiple sites off the coast of Corpus 
Christi. Monitoring studies at CCSC and CCNW ODMDSs have confirmed that 
there have been no significant adverse environmental consequences of 
disposal in this area and that there are no unique or limited habitats, 
features, or uses of the ocean that would be adversely affected by the 
disposal of additional dredged material at the expanded sites. Note 
that the EPA's modification of the existing site boundaries does not 
approve of the disposal of dredged material from any specific project 
at the sites. Before any person can ocean dump dredged material at the 
CCSC ODMDS or CCNW ODMDS, the EPA and USACE must evaluate the dredged 
material from the project according to the marine protection criteria 
at 40 CFR part 227, and USACE must authorize the disposal under section 
103 of the MPRSA (See 33 U.S.C. 1413(b)). The USACE relies on the EPA's 
marine protection criteria when evaluating permit requests for (and 
implementing Federal projects involving) the transportation of dredged 
material for the purpose of dumping it into ocean waters. MPRSA permits 
and Federal approvals for projects involving ocean dumping of dredged 
material are subject to the EPA's review and concurrence in accordance 
with 33 U.S.C. 1413(c). The EPA may concur with or without conditions 
or decline to concur (i.e., non-concur) on ocean dumping permits for 
dredged material or authorizations associated with Federal projects to 
transport and dump dredged material in the ocean. If the EPA concurs 
with conditions, the final permit or authorization must include those 
conditions. If the EPA declines to concur, the USACE cannot issue the 
permit for ocean dumping of dredged material or authorize the 
transportation and dumping of dredged material in the ocean associated 
with a Federal project.

B. Location and Configuration of the Modified CCSC and CCNW ODMDSs

    Depths of the modified ODMDSs range from 35 to 55 feet of water, 
and the modified ODMDSs are located between 1.7 nautical miles (nmi) 
and 2.7 nmi offshore. With this action, the EPA expands the existing 
CCSC ODMDS 0.5 nmi to the southwest from an area of 0.61 nmi\2\ to 1.05 
nmi\2\. Additionally, the EPA expands the existing CCNW ODMDS 0.5 nmi 
to the northwest; 0.6 nmi to the northeast; 0.4 nmi to the southeast; 
and 0.8 nmi to the southwest from an area of 1.39 nmi\2\ to 5.57 
nmi\2\.
Modified CCSC ODMDS Coordinates (North American Datum of 1983 (NAD83))
Northwest 27[deg]49'11.28'' N, 97[deg]01'9.84'' W;
Northeast 27[deg]48'43.20'' N, 97[deg]00'22.32'' W;
Southeast 27[deg]47'40.56'' N, 97[deg]01'9.12'' W; and
Southwest 27[deg]48'7.20'' N, 97[deg]01'56.64'' W
Modified CCNW ODMDS Coordinates (NAD83):
Northwest 27[deg]48'31.68'' N, 97[deg]00'24.12'' W;
Northeast 27[deg]47'32.64'' N, 96[deg]58'40.44'' W;
Southeast 27[deg]45'1.08'' N, 97[deg]00'32.04'' W; and
Southwest 27[deg]46'0.48'' N, 97[deg]02'19.32'' W

    The modification of the existing ODMDSs provides ongoing disposal 
capacity for suitable dredged material without causing significant 
adverse impacts, while also affording the most operational flexibility 
for managing the dredged material in a manner that minimizes physical 
impacts over time.

C. Management and Monitoring of the Sites

    The modified ODMDSs are expected to receive suitable dredged 
material from the Port of Corpus Christi's Channel Deepening Project 
(CDP) and suitable dredged material from other applicants who obtain a 
permit that could authorize disposal of dredged material at the 
modified ODMDSs. Under MPRSA section 102(c)(3) and its implementing 
regulations, the EPA is responsible for the management of all ocean 
disposal sites designated under the MPRSA (See 40 CFR 228.3(b)). 
Management of the ocean disposal sites consists of regulating the 
times, quantity and characteristics of the material dumped at the site; 
establishing disposal controls, conditions and requirements to avoid 
and minimize potential impacts to the marine environment; and 
monitoring the site and surrounding environment to verify that 
unanticipated or significant adverse effects are not occurring from 
past or continued use of the ocean disposal site and that terms of the 
MPRSA permit are met.
    As with the existing ODMDSs, the modified ODMDSs will be maintained 
according to a Site Management and Monitoring Plan (SMMP) specifying 
adaptive management provisions to ensure that significant environmental 
impacts do not occur within the sites and adjacent areas. The EPA 
provides the updated SMMP for the modified ODMDSs with the 
environmental assessment (EA) in the rulemaking docket. These documents 
are also accessible at: <a href="https://www.epa.gov/marine-protection-permitting/marine-protection-permitting-epa-region-6">https://www.epa.gov/marine-protection-permitting/marine-protection-permitting-epa-region-6</a>. All parties using 
the CCSC or CCNW ODMDSs will be required to follow any project-specific 
conditions, as well as provisions of the updated SMMPs for the modified 
sites as identified or incorporated into a permit or Federal project 
approval.

D. MPRSA Criteria

    In evaluating the modified ODMDSs, the EPA assessed the sites 
according to the marine protection criteria of the MPRSA, with emphasis 
on the general and specific regulatory criteria at 40 CFR part 228, to 
determine whether the site designations satisfy those criteria. The 
EPA's EA provides an extensive evaluation of the criteria and other 
related factors for the modification of the existing ODMDSs.
General Criteria (40 CFR 228.5)
    (a) Sites must be selected to minimize interference with other 
activities in the

[[Page 61140]]

marine environment, particularly avoiding areas of existing fisheries 
or shellfisheries, and regions of heavy commercial or recreational 
navigation (40 CFR 228.5(a)).
    The EPA developed the original site designations for the existing 
1989 CCSC and the existing 1988 CCNW ODMDSs using a Zone of Siting 
Feasibility (ZSF) approach, including dredged material fate modeling 
with considerations of potential interference with other activities in 
the marine environment such as avoiding areas of existing critical 
fisheries or shellfisheries and regions of heavy commercial or 
recreational navigation. The existing sites do not interfere with other 
legitimate uses of the ocean, because the original designations were 
designed to avoid interferences and to minimize adverse impacts. The 
expanded sites are not expected to have any additional impact beyond 
baseline effects assumed in these earlier evaluations.
    (b) Sites must be situated such that temporary perturbations to 
water quality or other environmental conditions during initial mixing 
caused by disposal operations would be reduced to normal ambient levels 
or undetectable contaminant concentrations or effects before reaching 
any beach, shoreline, marine sanctuary, or known geographically limited 
fishery or shellfishery (40 CFR 228.5(b)).
    The modified ODMDSs will be used for disposal of suitable dredged 
material as determined by the USACE and the EPA under section 103 of 
the MPRSA. Based on the USACE and EPA dredged material testing and 
evaluation procedures, disposal of dredged maintenance material and new 
work material is not expected to have any long-term adverse impact on 
water quality. The existing ODMDSs and modified ODMDSs are located 
sufficiently far from shore and fisheries resources to allow temporary 
water quality disturbances caused by disposal of dredged material to be 
reduced to ambient conditions before reaching any environmentally 
sensitive areas.
    (c) The sizes of disposal sites will be limited to localize for 
identification and control any immediate adverse impacts, and to permit 
the implementation of effective monitoring and surveillance to prevent 
adverse long-range impacts. Size, configuration, and location are to be 
determined as part of the disposal site evaluation (40 CFR 228.5(d)).
    When determining the size of the modified sites, the EPA considered 
the ability to implement effective monitoring and surveillance programs 
to ensure that the environment of the sites could be protected, and 
that navigational safety would not be compromised by the mounding of 
dredged material. The EPA determined the original site footprints based 
on a ZSF analysis as well as a dredged material fate model in support 
of the original site designations. Site use history of both the CCSC 
and CCNW ODMDSs confirms the previous modeling accuracy. Based on a 
dredged material fate model developed to support the CDP, the EPA 
determined that material at each site would remain within the ODMDS 
boundaries and not reach a height which would impair navigation. The 
SMMP describes the future monitoring and management activities the EPA 
and USACE would implement to confirm that disposal at each of the sites 
is not significantly affecting adjacent areas.
    (d) The EPA will, wherever feasible, designate ocean dumping sites 
beyond the edge of the continental shelf and other such sites where 
historical disposal has occurred (40 CFR 228.5(e)).
    The existing and modified CCSC ODMDS is approximately 1.7 nmi 
offshore and lies partially within the boundary of the site designated 
on an interim basis in 1977. The modified CCNW ODMDS is approximately 
2.7 nmi offshore and would fully encompass the existing site. The break 
of the continental shelf is approximately 60 nmi offshore. A dredged 
material disposal site at that location has been deemed unsuitable, 
because safety risks increase and the economic practicality and 
feasibility of monitoring and surveillance decrease with increasing 
distance from shore. Additionally, benthos living beyond the 
continental shelf are not expected to be as resilient to sediment 
resuspension as in the nearshore, higher energy environment. The ZSF 
analysis prepared by the USACE in support of the original 1988 and 1989 
designations for the CCNW ODMDS and the CCSC ODMDS, respectively, 
analyzed geographic constraints due to biological and physical 
resources, cultural and historical resources, environmental quality and 
recreational uses and concluded that designating a disposal site in an 
area beyond the continental shelf was unsuitable.
Specific Criteria (40 CFR 228.6)
    (1) Geographical position, depth of water, bottom topography and 
distance from coast (40 CFR 228.6(a)(1)).
    The modified CCSC ODMDS boundary is located approximately 1.7 nmi 
offshore in water depths of approximately 35 to 50 feet. The modified 
CCNW ODMDS boundary is located further offshore, approximately 2.7 nmi, 
in water depths of approximately 45 to 55 feet. The seafloor in this 
area slopes gently with significant variation in sediment composition 
throughout.
    (2) Location in relation to breeding, spawning, nursery, feeding, 
or passage areas of living resources in adult or juvenile phases (40 
CFR 228.6(a)(2)).
    The modified CCSC and CCNW ODMDSs provide feeding and breeding 
areas for common resident benthic organisms, fish, marine mammal, sea 
turtle, and seabird species. However, habitat in the region of the 
sites and expansion areas is not unique in this portion of the Gulf of 
America and is not critical habitat to the survival of any species of 
fish, invertebrates, sea turtles, whales, or threatened and endangered 
species. Floating larvae and eggs of various species of marine 
organisms are expected to be found at and near the water surface in the 
areas of the ODMDSs and expansion areas. The stress and possible 
mortality of individual organisms encountering adverse conditions 
during dredged disposal operations in the ODMDSs would be negligible 
compared to organisms in the greater region of the Gulf of America. 
Fish and invertebrates in this region of the Gulf of America use the 
nearshore areas for breeding, spawning, and feeding, and the nearshore 
jetties provide for migratory passage. The modified ODMDSs are located 
outside of these sensitive nearshore areas and outside of the buffer 
zone so as not to impact the biologically sensitive areas.
    (3) Location in relation to beaches and other amenity areas (40 CFR 
228.6(a)(3)).
    The modified CCSC ODMDS is located approximately 1.7 nmi from the 
nearest beach or amenity area. The modified CCNW ODMDS is located 
approximately 2.7 nmi from the nearest beach or amenity area. Transport 
of dredged material disposed at the sites occurs parallel to the beach. 
No significant impacts to beaches or amenity areas have been associated 
or detected with the existing sites and none are expected from the 
modified ODMDS boundaries.
    (4) Types and quantities of disposal, and proposed methods of 
release (40 CFR 228.6(a)(4)).
    The Corpus Christi Ship Channel Improvement Project (CCSCIP) 
generated approximately 41 million cubic yards (MCY) of new work 
dredged material and is expected to generate approximately 208 MCY of 
maintenance dredged material over the life of the project. The proposed 
CDP is expected to generate an additional amount,

[[Page 61141]]

approximately 46 MCY of new work dredged material and approximately 7.8 
MCY of maintenance dredged material. Alternatives for placement of 
dredged material have been developed as follows: ocean disposal; upland 
confined placement; and beneficial use. The USACE anticipates employing 
a combination of these options. Only dredged material that is 
determined to be suitable for ocean disposal under national and 
regional testing guidance would be disposed in the modified CCSC and 
CCNW ODMDSs. In addition, all disposal of dredged material in the ocean 
requires an ocean dumping permit issued by the USACE, or in the case of 
a Federal project involving ocean dumping must be authorized by the 
USACE pursuant to MPRSA section 103, with review and concurrence from 
EPA Region 6. Recent and historical chemical, physical, and 
bioaccumulation assessments performed by the USACE have indicated that 
there are no concerns with contaminated sediments in the Corpus Christi 
Ship Channel sediments.
    The maintenance material ranges from silt or sandy silt in the 
Inner Harbor, Upper Bay, and La Quinta Channel to fine or silty sand 
and silt in the entrance channel to silt or sandy silt, fine or silty 
sand and sand in the Lower Bay. The new work material ranges from 
mostly hard clay in the Inner Harbor and La Quinta Extension to mostly 
soft clay in the Upper Bay, mostly medium-to-dense sand in the Lower 
Bay, to very dense sand in the Jetty Channel to soft and firm clay 
toward the Extension Channel. The amount of material to be disposed of 
at the ODMDSs is expected to increase due to authorized private 
development projects and limited upland capacity. Material would be 
discharged from the hopper dredge within the ODMDSs. There would not be 
any waste contained or disposed of with the maintenance dredged 
material or new work material.
    (5) Feasibility of surveillance and monitoring (40 CFR 
228.6(a)(5)).
    Both the modified CCSC and CCNW ODMDSs will continue to be amenable 
to surveillance and monitoring due to their proximity to Corpus Christi 
and their relatively shallow depths. These factors facilitate site 
accessibility and reduce sampling costs and safety risks. The EPA and 
USACE will continue periodic environmental monitoring of the sites, 
approximately every 10 years, which consists of water, sediment and 
elutriate chemistry, bioassays, bioaccumulation studies and benthic 
infauna analyses, as described in the updated SMMP.
    (6) Dispersal, horizontal transport and vertical mixing 
characteristics of the area, including prevailing current direction and 
velocity (40 CFR 228.6(a)(6)).
    Though ocean current monitoring in the vicinity of ODMDSs has 
confirmed both horizontal and vertical current directions (depending on 
the season), the modified sites are predominantly characterized by 
longshore currents. The steady longshore transport and occasional 
storms, including hurricanes, disperse the disposed material from the 
site. These conditions have not adversely affected the ability to 
successfully and precisely dispose of suitable dredged material at both 
ODMDSs in the past and are not expected to affect disposal at the 
modified sites in the future.
    (7) Existence and effects of current and previous discharges and 
dumping in the area (including cumulative effects) (40 CFR 
228.6(a)(7)).
    The EPA is responsible for ODMDS monitoring in accordance with 
requirements specified at 40 CFR 228.13. ODMDS monitoring requirements 
are based on site designation parameters established in the MPRSA and 
its implementing regulations and are described in the SMMP for each 
ODMDS. Site monitoring activities include but are not limited to water 
column data collection, hydrodynamic analysis, sediment sampling and 
analyses for chemical content and concentrations, infauna sampling for 
benthic community analyses, geophysical surveys to determine 
distribution of native seabed features and deposits of disposed 
material, and other surveys to assess the characteristics at 
oceanographic sites. A 2020 survey of the existing CCSC and CCNW ODMDSs 
and proposed expansion areas indicated no significant changes to the 
benthic communities and grain size at the sites and that conditions 
within the ODMDSs were similar to those throughout the greater study 
area. Water and sediment chemistry sampling over the past four decades 
demonstrate that there are no water or sediment quality problems in the 
study area, and that dredged material disposal at the site has not 
caused or contributed to water or sediment quality contamination at the 
sites. Water quality perturbations from active disposal are temporary, 
minor, and insignificant. Short-term, long-term, and cumulative effects 
of dredged material disposal in the modified sites would be minor, and 
similar to those for the existing sites.
    In conjunction with maintenance dredging and chemical, physical, 
and bioaccumulation assessments, the USACE has collected water and 
sediment chemistry data from the Corpus Christi Ship Channel since 
1975. The data indicate that sediments in the Corpus Christi Ship 
Channel are not contaminated and are likely to remain acceptable for 
ocean dumping.
    (8) Interference with shipping, fishing, recreation. . .and other 
legitimate uses of the ocean (40 CFR 228.6(a)(8)).
    Listed uses pertinent to the CCSC and CCNW ODMDSs include shipping, 
mineral extraction, commercial and recreational fishing, and 
recreational and historical sites. The existing sites do not interfere 
with other legitimate uses of the ocean, because the site selection 
process was expressly designed and conducted to avoid interferences and 
minimize adverse impacts. Past dumping of maintenance dredged material 
or new work material has not been known to interfere with other uses, 
and no changes are expected at the modified sites that would alter the 
status quo.
    (9) Existing water quality and ecology of the sites as determined 
by available data or trend assessment of baseline surveys (40 CFR 
228.6(a)(9)).
    According to the 2024 Texas Integrated Report, the existing and 
modified ODMDSs are located within an impaired water body, Texas 
assessment unit ID TX-2501_06. The subsegment is listed as a fish 
consumption advisory for mercury. Water and sediment chemistry data 
from the 2020 monitoring survey indicate no significant water quality 
issues and no significant trends in water quality resulting from 
dredged material dumping. Both the CCSC and CCNW ODMDSs support benthic 
and epibenthic fauna characteristic of the region and there are no 
unique or limited habitats in the vicinity. No adverse impacts to 
benthos, both inside and outside the existing or modified sites, have 
been identified based on previous monitoring and none are expected.
    (10) Potential for the development or recruitment of nuisance 
species (40 CFR 228.6(a)(10)).
    Vessels traveling between multiple distant ports can facilitate 
nuisance species transfer through the uptake and discharge of ballast 
water, as well as through biofouling (and associated cleaning) of 
vessel hulls and appendages. Both the EPA and the U.S. Coast Guard 
administer requirements for ballast water discharges and biofouling 
management that apply to vessels operating in U.S. waters. These 
requirements are unaffected by the action. The U.S. Coast Guard and the 
Smithsonian Environmental Research

[[Page 61142]]

Center also jointly operate the National Ballast Information 
Clearinghouse, which collects and analyzes ballast water management 
data from vessels. Moreover, nuisance species control would continue to 
be managed by State, Federal and private organizations.
    (11) Existence of Significant Natural or Cultural Feature of 
Historical Importance (40 CFR 228.6(a)(11)).
    The Environmental Impact Statements (EISs) developed to support the 
original designations described the location and types of areas and 
features of natural or historical importance that were considered 
during the site selection process. Exclusion areas, including buffer 
zones, were documented during the original siting process. No known 
significant natural or cultural features of historical importance were 
identified in the vicinity of the ODMDSs. The 2020 EPA survey of the 
CCSC and CCNW ODMDSs and proposed expansion areas likewise indicated no 
known significant natural or historical resources in the vicinity. The 
modified ODMDSs would not affect any natural or cultural features of 
historical importance.

III. Environmental Statutory Review

A. National Environmental Policy Act

    Section 102 of the National Environmental Policy Act of 1969, as 
amended (NEPA), 42 U.S.C. 4321 through 4370f, requires Federal agencies 
to prepare an EIS for major Federal actions significantly affecting the 
quality of the human environment. The EPA is not required to apply NEPA 
to designations of MPRSA ocean disposal sites; courts have recognized 
that the EPA's actions applying the MPRSA criteria and procedural 
requirements are functionally equivalent to the procedures applicable 
under NEPA. As a matter of policy, however, the EPA documents its 
consideration of alternatives (as if NEPA applied) to inform certain 
EPA regulatory actions, including certain actions under the MPRSA.
    The EPA developed an EA for the site modifications which addressed 
project alternatives and environmental impacts of the expansion, in 
functional and effective compliance with NEPA. The EPA has relied on 
information from the original Final EIS documents prepared to support 
the 1988 and 1989 designations of the CCNW ODMDS and the CCSC ODMDS, 
respectively, in the development of this EA.

B. Endangered Species Act and Marine Mammal Protection Act

    In accordance with section 7 of the Endangered Species Act, as 
amended, and in consultation with the National Marine Fisheries Service 
(NMFS) Southeast Regional Office, the EPA conducted an evaluation of 
the threatened and endangered species that may occur in the CCSC and 
CCNW ODMDS project areas. In a letter dated January 21, 2025, the EPA 
determined that the modification for expansion of the CCSC and CCNW 
ODMDS boundaries is not likely to adversely affect any listed species 
and will have no effect on critical habitat under NMFS's jurisdiction. 
The NMFS concurred with the EPA's findings on January 28, 2025.
    Additionally, the EPA compiled a current list of the threatened and 
endangered species that are under the jurisdiction of the U.S. Fish and 
Wildlife Service's (USFWS) Texas Coastal Ecological Services Field 
Office and that may be affected by the action. In an evaluation dated 
March 21, 2025, the EPA determined that the modification for expansion 
of the CCSC and CCNW ODMDS boundaries will have no effect on the listed 
species with one exception. The EPA determined that the modification is 
not likely to adversely affect the federally-listed West Indian 
manatee. In a letter dated June 6, 2025, the USFWS concurred with the 
EPA's findings.

C. Magnuson-Stevens Fisheries Conservation and Management Act

    The 1996 amendments to the Magnuson-Stevens Fishery Conservation 
and Management Act (Magnuson-Stevens Act) require that each Federal 
agency consult with NMFS for any action authorized, funded, or 
undertaken, or proposed to be authorized, funded, or undertaken, by the 
agency that may adversely affect any essential fish habitat (EFH) 
identified under the Magnuson-Stevens Act. The EPA prepared an EFH 
assessment dated March 13, 2025, and determined that the modification 
for expansion of the CCSC and CCNW ODMDS boundaries would not have a 
substantial impact on EFH or federally managed fisheries in the Gulf of 
America. The NMFS concurred with the EPA's findings on March 25, 2025, 
and provided no conservation recommendations.

D. Coastal Zone Management Act

    The Coastal Zone Management Act (CZMA) of 1972, as amended, 
requires Federal agencies proposing activities within or outside the 
coastal zone to ensure that those activities are conducted in a manner 
which is consistent to the maximum extent practicable with the 
enforceable policies of approved State coastal management programs. The 
Texas Coastal Management Program (TCMP) was developed and approved by 
NOAA pursuant to the requirements of the CZMA. The Texas General Land 
Office administers the State program, including review of Federal 
agency actions in the Texas coastal zone that affect coastal natural 
resource areas to ensure consistency with the enforceable policies of 
the TCMP. The enforceable policy components of the TCMP are published 
in Title 31 of the Texas Administrative Code (TAC), Chapter 501, as 
amended. The EPA submitted to TCMP a Consistency Determination, 
documenting EPA's determination that the site modifications are 
consistent to the maximum extent practicable with the enforceable 
policies of the approved TCMP program (esp. the Coast Act, Chapter 501 
policies). In a letter dated April 21, 2026, the Texas GLO concurred 
with the EPA's findings.

E. National Historic Preservation Act

    Section 106 of the National Historic Preservation Act, 54 U.S.C. 
306108, as amended, requires Federal agencies to ``take into account'' 
the effect of agency actions on districts, sites, buildings, 
structures, or objects significant in American history, architecture, 
archaeology, engineering, and culture, included in, or eligible for 
inclusion in the National Register of Historic Places. The EPA 
determined during the original site designations (prior to the 
expansion) that no historic properties were affected or would be 
affected by the designation of the CCSC and CCNW ODMDSs. In a letter to 
the Texas Historical Commission dated March 20, 2025, the EPA 
determined that the modification for expansion of the existing CCSC and 
CCNW ODMDS boundaries will likewise have no effect on historic 
properties. In a letter dated August 8, 2025, the Texas Historical 
Commission concurred with the EPA's findings.

IV. Response to Comments on the Proposed Rule, Draft EA and Draft SMMP

    The EPA published the proposed rule, the draft EA, and the draft 
SMMP for a 30-day public comment period on March 12, 2026, and accepted 
comments until April 13, 2026 (91 FR 12126, March 12, 2026). The 
documents were available at <a href="http://www.regulations.gov">www.regulations.gov</a> (Docket ID No. EPA-R06-
OW-2025-3359) and at <a href="https://www.epa.gov/marine-protection-permitting/marine-protection-permitting-epa-region-6">https://www.epa.gov/marine-protection-permitting/marine-protection-permitting-epa-region-6</a>.
    The EPA received discrete comments from eight commenters. The full 
comments and the EPA's responses are

[[Page 61143]]

included in Appendix E to the Final EA and are summarized below. No 
substantive changes were made to the final documents based on the 
comments received.
    One commenter expressed concern over solid contaminants, 
specifically plastic pellets, in dredged material placed in the ODMDSs. 
The proposal, however, only addressed expansion of an available ocean 
disposal location (that will be monitored to assess future effects), 
and would not have authorized any actual dredged material disposal. Any 
such authorization to place any material into the site does not occur 
until a separate, later proceeding conducted by the USACE. Therefore, 
the comment is beyond the scope of the action. Plastics in dredged 
materials are a contaminant of emerging concern, though environmental 
criteria specific to gross plastics are not presently available. The 
MPRSA assessment framework does, however, incorporate biological 
assessments (bioassays) of dredged material to determine its 
suitability for ocean disposal. Bioassays measure acute toxicity and 
larval development using test organisms of representative species to 
assess the combined toxic effects of contaminant mixtures in whole 
dredged material samples.
    One commenter supported the expansion of the sites but raised 
concerns about the resuspension of old sediments contaminated with 
heavy metals. The EPA responded that a 2020 baseline characterization 
survey of the ODMDSs and expansion areas, which included an assessment 
of certain heavy metals, found no significant contaminant loading and 
no adverse impacts related to the sediment chemistry from previous 
dredged material disposal
    One commenter expressed concern that the proposed rule de-
emphasized the environmental impacts of dredged material disposal as 
``temporary, minor, and insignificant'' and that the characterization 
is contradicted by statements in the draft EA about the consideration 
of alternatives that would have ``less adverse environmental impact'' 
on the aquatic environment. The EPA explained that both statements are 
accurate based on: (1) the benign nature of material assessed to be 
suitable for ocean disposal; and (2) the MPRSA requirement to consider 
land-based disposal alternatives.
    One commenter questioned whether the dredged material will be 
tested. The EPA explained that all dredged material considered for 
ocean disposal is evaluated, and if necessary, tested for compliance 
with the ocean dumping criteria defined at 40 CFR part 227. Some 
material is excluded from analytical testing requirements, for example, 
material composed predominantly of sand, gravel, or rock that is found 
in areas of high current or wave energy.
    One commenter expressed opposition to the site expansions citing 
concerns that the expansions would increase the difficulty and expenses 
required to monitor the ocean disposal sites. The EPA responded by 
clarifying the need for the site expansions, explained why the EPA does 
not expect the increases in site area to significantly increase the 
difficulty nor expense required to monitor the sites, and confirmed 
that site monitoring over the past 50 years indicates no significant 
adverse impacts from dredged material disposal.
    One commenter expressed opposition to ocean disposal of dredged 
material generally and urged landfill disposal. The comment is beyond 
the scope of the proposal (which did not purport to authorize disposal 
itself) but the EPA explained that the MPRSA requires that any 
authorization of dredged material disposal in the ocean requires prior 
consideration of the need for ocean disposal and consideration of land-
based alternatives.
    One commenter expressed general opposition to expansion of the port 
and its costs, rather than the disposal sites. The comment is beyond 
the scope of the proposal, which only indirectly relates to any port 
expansion in that the site expansion will accommodate the capacity 
needs for material from future maintenance dredging at a location that 
will be monitored over time.

V. Statutory and Executive Order Reviews

    Additional information about these statutes and Executive Orders 
can be found at <a href="https://www.epa.gov/laws-regulations/laws-and-executive-orders">https://www.epa.gov/laws-regulations/laws-and-executive-orders</a>.
    a. Executive Order 12866, Regulatory Planning and Review and 
Executive Order 13563, Improving Regulation and Regulatory Review (58 
FR 51735, October 4, 1993);
    This action is not a significant regulatory action and was 
therefore not submitted to the Office of Management and Budget (OMB) 
for review.
    b. Executive Order 14192, Unleashing Prosperity Through 
Deregulation (90 FR 9065, February 6, 2025);
    This action is not an Executive Order 14192 regulatory action.
    c. Paperwork Reduction Act (PRA) (44 U.S.C. 3501et seq.);
    This action does not impose an information collection burden under 
the PRA.
    d. Regulatory Flexibility Act (UMRA) (5 U.S.C. 601et seq.);
    After considering the economic impacts of this rule, the EPA 
determined that this action will not have a significant economic impact 
on a substantial number of small entities.
    e. Unfunded Mandates Reform Act (UMRA) (Pub. L. 104-4);
    This action does not contain an unfunded mandate as described in 
UMRA, 2 U.S.C. 1531-1538 and does not significantly or uniquely affect 
small governments.
    f. Executive Order 13132 Federalism (64 FR 43255, August 10, 1999);
    This action does not have federalism implications. It will not have 
substantial effects on the States, on the relationship between the 
national government and the States, or on the distribution of power and 
responsibilities among the various levels of government.
    g. Executive Order 13175, Consultation and Coordination with Indian 
Tribal Governments (65 FR 67249, November 9, 2000);
    This action does not have Tribal implications as specified in 
Executive Order 13175. Thus, Executive Order 13175 does not apply to 
this action. Consistent with the EPA Policy on Consultation and 
Coordination with Indian Tribes, the EPA consulted with Tribal 
officials during the development of this action. A summary of that 
consultation is provided in the EA.
    h. Executive Order 13045, Protection of Children from Environmental 
Health and Safety Risks (62 FR 19885, April 23, 1997);
    This action is not subject to Executive Order 13045, because it 
does not establish an environmental standard intended to mitigate 
health or safety risks.
    i. Executive Order 13211, Actions that Significantly Affect Energy 
Supply, Distribution, or Use (66 FR 28355, May 22, 2001);
    This action is not subject to Executive Order 13211, because it is 
not a significant regulatory action under Executive Order 12866.
    j. National Technology Transfer and Advancement Act (NTTAA) (15 
U.S.C. 272 note);
    This action includes environmental monitoring and measurement as 
described in the updated SMMP. The EPA will not require the use of 
specific, prescribed analytic methods for monitoring and managing the 
modified CCSC and CCNW ODMDSs. The EPA plans to allow the use of any 
method, whether it constitutes a voluntary consensus standard or not, 
that meets the monitoring and measurement criteria discussed in the 
SMMP.

[[Page 61144]]

    k. Executive Order 13089, Coral Reef Protection (63 FR 32701, June 
16, 1998); and
    This order is not applicable to this action. No coral reefs, banks 
or other major physiographic features characterize the shelf in the 
Corpus Christi area.
    l. Executive Order 13112, Invasive Species (64 FR 6183, February 8, 
1999)
    This action will not positively or negatively affect the status of 
invasive species.

List of Subjects in 40 CFR Part 228

    Environmental Protection, Water Pollution Control.

    Dated: September 14, 2026.
Walter Mason,
Regional Administrator, Region 6, U.S. Environmental Protection Agency.
    For the reasons set out in the preamble, the EPA amends part 228 of 
chapter I, title 40 of the Code of Federal Register as follows:

PART 228--CRITERIA FOR THE MANAGEMENT OF DISPOSAL SITES FOR OCEAN 
DUMPING

0
1. The authority citation for part 228 continues to read as follows:

    Authority: 33 U.S.C. 1412 and 1418.


0
2. Amend Sec.  228.15 by:
0
a. Revising paragraphs (j)(16)(i) and (ii); and
0
b. Revising paragraphs (j)(17)(i) and (ii).
    The revisions read as follows:


Sec.  228.15  Dumping sites designated on a final basis.

* * * * *
    (j) * * *
    (16) * * *
    (i) Location: 27[deg]48'31.68'' N, 97[deg]00'24.12'' W; 
27[deg]47'32.64'' N, 96[deg]58'40.44'' W; 27[deg]45'1.08'' N, 
97[deg]00'32.04'' W; 27[deg]46'0.48'' N, 97[deg]02'19.32'' W (NAD83).
    (ii) Size: 5.57 square nautical miles.
* * * * *
    (17) * * *
    (i) Location: 27[deg]49'11.28'' N, 97[deg]01'9.84'' W; 
27[deg]48'43.20'' N, 97[deg]00'22.32'' W; 27[deg]47'40.56'' N, 
97[deg]01'9.12'' W; 27[deg]48'7.20'' N, 97[deg]01'56.64'' W (NAD83).
    (ii) Size: 1.05 square nautical miles.
* * * * *
[FR Doc. 2026-19745 Filed 9-25-26; 8:45 am]
BILLING CODE 6560-50-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on September 28, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.