Agency Information Collection Activities; Submission to the Office of Management and Budget for Review and Approval; Decommissioning Activities

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 22, 2026

Issuing agencies

Interior DepartmentSafety and Environmental Enforcement Bureau

Abstract

In accordance with the Paperwork Reduction Act (PRA) of 1995, the Bureau of Safety and Environmental Enforcement (BSEE) proposes to renew an information collection.

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 182 (Tuesday, September 22, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 182 (Tuesday, September 22, 2026)]
[Notices]
[Pages 60146-60148]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-19293]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Safety and Environmental Enforcement

[Docket ID BSEE-2025-0233; EEEE500000--256E1700D2--ET1SF0000.EAQ000; 
OMB Control Number 1014-0010]


Agency Information Collection Activities; Submission to the 
Office of Management and Budget for Review and Approval; 
Decommissioning Activities

AGENCY: Bureau of Safety and Environmental Enforcement, Interior.

ACTION: Notice of information collection; request for comment.

-----------------------------------------------------------------------

SUMMARY: In accordance with the Paperwork Reduction Act (PRA) of 1995, 
the Bureau of Safety and Environmental Enforcement (BSEE) proposes to 
renew an information collection.

DATES: Interested persons are invited to submit comments on or before 
October 22, 2026.

ADDRESSES: Written comments and recommendations for the proposed 
information collection should be sent within 30 days of publication of 
this notice to <a href="http://www.reginfo.gov/public/do/PRAMain">www.reginfo.gov/public/do/PRAMain</a>. Find this particular 
information collection by selecting ``Currently under 30-day Review--
Open for Public Comments'' or by using the search function. Please 
provide a copy of your comments to Kelly Odom, Acting BSEE ICCO, 45600 
Woodland Road, Sterling, VA 20166; or by email to <a href="/cdn-cgi/l/email-protection#8fc4eae3e3f6a1c0ebe0e2cfedfceaeaa1e8e0f9"><span class="__cf_email__" data-cfemail="a6edc3cacadf88e9c2c9cbe6c4d5c3c388c1c9d0">[email&#160;protected]</span></a>. 
Please reference OMB Control Number 1014-0010 in the subject line of 
your comments.

FOR FURTHER INFORMATION CONTACT: To request additional information 
about this ICR, contact Kelly Odom by email at <a href="/cdn-cgi/l/email-protection#5e153b32322770113a31331e3c2d3b3b70393128"><span class="__cf_email__" data-cfemail="29624c45455007664d4644694b5a4c4c074e465f">[email&#160;protected]</span></a>, or 
by telephone at (703) 787-1775. Individuals in the United States who 
are deaf, deafblind, hard of hearing, or have a speech disability may 
dial 711 (TTY, TDD, or TeleBraille) to access telecommunications relay 
services. Individuals outside the United States should use the relay 
services offered within their country to make international calls to 
the point-of-contact in the United States. You may also view the ICR at 
<a href="http://www.reginfo.gov/public/do/PRAMain">http://www.reginfo.gov/public/do/PRAMain</a>.

SUPPLEMENTARY INFORMATION: In accordance with the PRA and 5 CFR 
1320.8(d)(1), we provide the general public and other Federal agencies 
with an opportunity to comment on new, proposed, revised, and 
continuing collections of information. This helps us assess the impact 
of our information collection requirements and minimize the public's 
reporting burden. It also helps the public understand our information 
collection requirements and provide the requested data in the desired 
format.
    A Federal Register notice with a 60-day public comment period 
soliciting comments on this collection of information was published on 
September 25, 2025 (90 FR 46251). No comments were received.
    As part of our continuing effort to reduce paperwork and respondent 
burdens, we are again soliciting comments from the public and other 
Federal agencies on the proposed ICR that is described below. We are 
especially interested in public comment addressing the following:
    (1) Whether or not the collection of information is necessary for 
the proper performance of the functions of the agency, including 
whether or not the information will have practical utility;
    (2) The accuracy of our estimate of the burden for this collection 
of

[[Page 60147]]

information, including the validity of the methodology and assumptions 
used;
    (3) Ways to enhance the quality, utility, and clarity of the 
information to be collected; and
    (4) How might the agency minimize the burden of the collection of 
information on those who are to respond, including through the use of 
appropriate automated, electronic, mechanical, or other technological 
collection techniques or other forms of information technology, e.g., 
permitting electronic submission of response.
    Comments that you submit in response to this notice are a matter of 
public record. Before including your address, phone number, email 
address, or other personal identifying information in your comment, you 
should be aware that your entire comment--including your personal 
identifying information--may be made publicly available at any time. 
While you can ask us in your comment to withhold your personal 
identifying information from public review, we cannot guarantee that we 
will be able to do so.
    Abstract: BSEE uses the information collected under Subpart Q 
primarily for the following reasons:
    <bullet> To determine the necessity for allowing a well to be 
temporarily abandoned, the lessee/operator must demonstrate that there 
is a reason for not permanently plugging the well, and the temporary 
abandonment will not interfere with fishing, navigation, or other uses 
of the OCS. We use the information and documentation to verify that the 
lessee/operator is diligently pursuing the final disposition of the 
well and has performed the temporary plugging of the wellbore.
    <bullet> To ensure the information submitted in initial 
decommissioning plans in the Alaska and Pacific OCS Regions will permit 
BSEE to become involved on the ground floor planning of platform 
removals anticipated to occur in these OCS regions.
    <bullet> To ensure that all objects (wellheads, platforms, etc.) 
installed on the OCS are properly removed using procedures that will 
protect marine life and the environment during removal operations, and 
the site cleared so as not to conflict with or harm other uses of the 
OCS in coordination with other Federal, State, and local government 
agencies.
    <bullet> To ensure that information regarding decommissioning a 
pipeline in place will not constitute a hazard to navigation and 
commercial fishing operations, unduly interfere with other uses of the 
OCS, such as sand resource areas for coastal restoration projects, or 
have adverse environmental effects.
    <bullet> To verify that decommissioning activities comply with 
approved applications and procedures and are satisfactorily completed.
    <bullet> To evaluate and approve the adequacy of the equipment, 
materials, and/or procedures that the lessee or operator plans to use 
during well modifications and changes in equipment, etc.
    <bullet> To help BSEE better estimate future decommissioning costs 
for OCS leases, rights-of-way, and rights of use and easements. BSEE's 
future decommissioning cost estimates may then be used by BOEM to set 
necessary financial assurance levels to minimize or eliminate the 
possibility that the government will incur abandonment liability. The 
information will assist BSEE and BOEM in meeting their stewardship 
responsibilities and in their roles as regulators.
    Title of Collection: 30 CFR 250, Subpart Q, Decommissioning 
Activities.
    OMB Control Number: 1014-0010.
    Form Number: None.
    Type of Review: Extension of a currently approved collection.
    Respondents/Affected Public: Potential respondents include Federal 
OCS oil, gas, and sulfur lessees and/or operators and holders of 
pipeline rights-of-way.
    Total Estimated Number of Annual Respondents: Currently there are 
approximately 555 Federal OCS oil, gas, and sulfur lessees and holders 
of pipeline rights-of-way. Not all the potential respondents will 
submit information in any given year, and some may submit multiple 
times.
    Total Estimated Number of Annual Responses: 984.
    Estimated Completion Time per Response: Varies from 1 hour to 47 
hours, depending on activity.
    Total Estimated Number of Annual Burden Hours: 19,965.
    Respondent's Obligation: Mandatory.
    Frequency of Collection: Submissions are generally on occasion, 
varies by section, and annual.
    Total Estimated Annual Nonhour Burden Cost: $745,142.

----------------------------------------------------------------------------------------------------------------
                                                                                                        Annual
                                                                 Hour      Average number of annual     burden
  Citation 30 CFR 250 subpart Q     Reporting requirement *     burden            responses              hours
                                                                                                       (rounded)
----------------------------------------------------------------------------------------------------------------
                                                         Non-hour cost burdens
----------------------------------------------------------------------------------------------------------------
                                                     General
----------------------------------------------------------------------------------------------------------------
1704(g); 1706(a), (f); 1712;       These sections contain     APM burden covered under 1014-0026.              0
 1715; 1716; 1721(a), (d), (f)-     references to
 (g); 1722(a), (b), (d); 1723(b);   information, approvals,
 1743(a); Sub G.                    requests, payments,
                                    etc., which are
                                    submitted with an APM,
                                    the burdens for which
                                    are covered under its
                                    own information
                                    collection.
                                                             ----------------------------------------
1700 thru 1754...................  General departure and      Burden covered under Subpart A 1014-             0
                                    alternative compliance    0022.
                                    requests not
                                    specifically covered
                                    elsewhere in Subpart Q
                                    regulations.
                                                             ----------------------------------------
1704(b); 1708....................  Submit work plan and              16  34.........................         544
                                    schedule under Sec.
                                    250.1704(b) that
                                    addresses all wells,
                                    platforms and other
                                    facilities, pipelines,
                                    and site clearance
                                    within 150 days upon
                                    receiving an order to
                                    perform decommissioning;
                                    additional information
                                    as requested by BSEE.
1704(j), (k).....................  Submit to BSEE, within          26.7  275........................       7,343
                                    120 days after
                                    completion of each
                                    decommissioning activity
                                    (including pipelines), a
                                    summary of expenditures
                                    incurred; any additional
                                    information that will
                                    support and/or verify
                                    the summary.
1704(j); NTL.....................  Request and obtain               3.3  38 requests................         125
                                    approval for extension
                                    of 120-day reporting
                                    period; including
                                    justification.
1713.............................  Notify BSEE 48 hours               0  0 notices..................           0
                                    before beginning
                                    operations to
                                    permanently plug a well.
                                                             ----------------------------------------
1721(f)..........................  Install a protector        Burden covered under Subpart I 1014-             0
                                    structure designed        0011.
                                    according to 30 CFR 250,
                                    Subpart I, and equipped
                                    with aids to navigation.
                                    (These requests are
                                    processed via the
                                    appropriate Platform
                                    Application, 30 CFR 250
                                    Subpart I by the OSTS.).
                                                             ----------------------------------------

[[Page 60148]]

 
1721(e); 1722(e), (h)(1); 1741(c)  Identify and report        U.S. Coast Guard requirements.                   0
                                    subsea wellheads, casing
                                    stubs, or other
                                    obstructions; mark wells
                                    protected by a dome;
                                    mark location to be
                                    cleared as navigation
                                    hazard.
                                                             ----------------------------------------
1722(c), (g)(2)..................  Notify BSEE within 5 days        1.3  3 notices..................           4
                                    if trawl does not pass
                                    over protective device
                                    or causes damages to it;
                                    or if inspection reveals
                                    casing stub or mud line
                                    suspension is no longer
                                    protected.
1722(f), (g)(3)..................  Submit annual report on            0  0 reports..................           0
                                    plans for re-entry to
                                    complete or permanently
                                    abandon the well and
                                    inspection report.
1722(h)..........................  Request waiver of                2.8  1 requests.................           3
                                    trawling test.
                                                             ----------------------------------------
1725(a)..........................  Requests to maintain the   Burden covered under Subpart I 1014-             0
                                    structure to conduct      0011.
                                    other activities are
                                    processed, evaluated and
                                    permitted by the OSTS
                                    via the appropriate
                                    Platform Application
                                    process, 30 CFR 250
                                    Subpart I. (Other
                                    activities include but
                                    are not limited to
                                    activities conducted
                                    under the grants of
                                    right-of-ways (ROWs),
                                    rights-of-use and
                                    easement (RUEs), and
                                    alternate rights-of-use
                                    and easement authority
                                    issued under 30 CFR 250
                                    Subpart J, 30 CFR
                                    550.160, and/or 30 CFR
                                    585, etc.).
                                                             ----------------------------------------
1725(e)..........................  Notify BSEE 48 hours               1  74 Notices.................          74
                                    before beginning removal
                                    of platform and other
                                    facilities.
1726; 1704(a)....................  Submit initial                     0  0..........................           0
                                    decommissioning
                                    application in the
                                    Pacific and Alaska OCS
                                    Regions.
1727; 1728; 1730; 1703; 1704(c);   Submit final application        46.7  114 applications...........       5,324
 1725.                              and appropriate data to
                                    remove platform or other
                                    subsea facility
                                    structures (This
                                    included alternate depth
                                    departures and/or
                                    approvals of partial
                                    removal or toppling for
                                    conversion to an
                                    artificial reef.).
                                                             ---------------------------------------------------
                                                              $4,684 fee x 114 = $533,976.
                                                             ---------------------------------------------------
1729; 1704(d)....................  Submit post platform or         34.3  57 reports.................       1,955
                                    other facility removal
                                    report; supporting
                                    documentation; signed
                                    statements, etc.
1740(a) and (c); 1741(g).........  Request approval to use            0  0 requests/contacts........           0
                                    alternative methods of
                                    well site, platform, or
                                    other facility
                                    clearance; contact
                                    pipeline owner/operator
                                    before trawling to
                                    determine its condition.
1743; 1704(g), (i)...............  Verify permanently              13.3  81 certifications..........       1,077
                                    plugged well, platform,
                                    or other facility
                                    removal site cleared of
                                    obstructions; supporting
                                    documentation; and
                                    submit certification
                                    letter.
1750; 1751; 1752; 1754; 1704(e)..  Submit application to           18.7  88 L/T applications........       1,646
                                    decommission pipeline in
                                    place or remove pipeline
                                    (L/T or ROW).
                                                             ---------------------------------------------------
                                                              $1,142 L/T decommission fee x 88 = $100,496.
                                                             ---------------------------------------------------
                                                                      8  51 ROW applications........         408
                                                             ---------------------------------------------------
                                                              $2,170 ROW decommissioning fees x 51 = $110,670.
                                                             ---------------------------------------------------
1753; 1704(f)....................  Submit post pipeline             8.7  168 reports................       1,462
                                    decommissioning report.
                                  ------------------------------------------------------------------------------
    Total Burden.......................................................  984 responses..............      19,965
                                  ------------------------------------------------------------------------------
                                   $745,142 Non-Hour Cost Burdens.
----------------------------------------------------------------------------------------------------------------

    The current OMB approved annual hour burden is 15,997 burden hours 
for this collection of information. This submission requests 19,965 
burden hours. The adjustment increase of 3,968 hours is, in part, due 
to differing interpretations of the time required for regulatory 
submission versus the total time needed to collect and complete the 
associated paperwork. The figures reflect the information provided by 
the oil and gas industry.
    An agency may not conduct, or sponsor and a person is not required 
to respond to a collection of information unless it displays a 
currently valid OMB control number.
    The authority for this action is the Paperwork Reduction Act of 
1995 (44 U.S.C. 3501 et seq.).

Kirk Malstrom,
Chief, Regulations and Standards Branch.
[FR Doc. 2026-19293 Filed 9-21-26; 8:45 am]
BILLING CODE 4310-VH-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>