September 18, 2026

Issuing agencies

Transportation DepartmentFederal Highway Administration

Abstract

This notice announces actions taken by FHWA that are final. The actions relate to a proposed roadway project, the Lee Road Extension--Phase 1, from State Route (SR) 92 to County Road (CR) 141/ Bomar Road in Douglas County, Georgia, and includes widening, intersection reconstruction, and new location project on Bomar Road at Pope Road to the State Route (SR) 92 at Lee Road intersection in Douglas County, Georgia, for approximately 1.7 miles. Those actions grant licenses, permits, and approvals for the project. The FHWA's Finding of No Significant Impact (FONSI) provides details on the Selected Alternative for the proposed improvements.

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 180 (Friday, September 18, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 180 (Friday, September 18, 2026)]
[Notices]
[Pages 59297-59298]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-19098]


-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Highway Administration


Notice of Final Federal Agency Actions on Proposed Highway in 
Georgia

AGENCY: Federal Highway Administration (FHWA), DOT.

ACTION: Notice of limitation on claims for judicial review of actions 
by FHWA.

-----------------------------------------------------------------------

SUMMARY: This notice announces actions taken by FHWA that are final. 
The actions relate to a proposed roadway project, the Lee Road 
Extension--Phase 1, from State Route (SR) 92 to County Road (CR) 141/
Bomar Road in Douglas County, Georgia, and includes widening, 
intersection reconstruction, and new location project on Bomar Road at 
Pope Road to the State Route (SR) 92 at Lee Road intersection in 
Douglas County, Georgia, for approximately 1.7 miles. Those actions 
grant licenses, permits, and approvals for the project. The FHWA's 
Finding of No Significant Impact (FONSI) provides details on the 
Selected Alternative for the proposed improvements.

DATES: By this notice, FHWA is advising the public of final agency 
actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review 
of the Federal agency actions on the listed roadway project will be 
barred unless the claim is filed on or before February 16, 2027. If the 
Federal law that authorizes judicial review of a claim provides a time 
period of less than 150 days for filing such claim, then that shorter 
time period still applies.

FOR FURTHER INFORMATION CONTACT: For FHWA: Ms. Sabrina S. David, 
Division Administrator; FHWA, Georgia Division; 75 Ted Turner Drive, 
Suite 1000, Atlanta, Georgia 30303; 404-562-3630; email: 
<a href="/cdn-cgi/l/email-protection#73201211011a1d125d3712051a1733171c075d141c05"><span class="__cf_email__" data-cfemail="0f5c6e6d7d66616e214b6e79666b4f6b607b21686079">[email&#160;protected]</span></a>. The FHWA Georgia Division's normal business 
hours are 7:30 a.m. to 4:00 p.m. (Eastern time) Monday through Friday. 
For the Georgia Department of Transportation (GDOT): Mr. Russell 
McMurry, Commissioner, GDOT; 600 West Peachtree Street, 22nd Floor, 
Atlanta, Georgia 30308; (404) 631-1990; <a href="/cdn-cgi/l/email-protection#eab8a789a79f98988b93aa8e859ec48d8bc48d859c"><span class="__cf_email__" data-cfemail="ce9c83ad83bbbcbcafb78eaaa1bae0a9afe0a9a1b8">[email&#160;protected]</span></a>. The GDOT 
normal business hours are 8:00 a.m. to 5:00 p.m. (Eastern time) Monday 
through Friday.

SUPPLEMENTARY INFORMATION: Notice is hereby given that FHWA has taken 
final agency actions by issuing a FONSI for the following roadway 
project in the State of Georgia: The Lee Road Extension from SR 92 to 
CR 141/Bomar Road--Phase I in Douglas County, Georgia--Project 
Identification (PI) Number 0019889. The project will reconstruct the 
Bomar Road at Pope Road intersection into a multi-lane roundabout. 
Additionally, Bomar Road will be widened to the north of the Pope Road 
intersection approximately 1,550 feet. From this point along Bomar 
Road, the project will continue on new location for 1.13 miles to the 
spur south of the SR 92 at Lee Road intersection. The purpose of the 
proposed project is to improve connectivity and access within the 
central portion of Douglas County, providing an important county-wide 
east-west connector with greater access to I-20.
    The FHWA's actions and the laws under which such actions were 
taken, are described in the Environmental Assessment (EA) for the 
project, approved on April 30, 2026, the FONSI approved on August 17, 
2026, and other documents in the project file. The EA and FONSI are 
available by contacting FHWA or GDOT at the addresses provided above. 
In addition, these documents can also be viewed and downloaded from the 
project website at <a href="https://douglascountyga.gov/894/0019889-Lee-Road-Extension-from-SR-92-to">https://douglascountyga.gov/894/0019889-Lee-Road-Extension-from-SR-92-to</a>.
    This notice applies to all Federal agency decisions as of the 
issuance date of this notice and all laws under which such actions were 
taken, including but not limited to:
    1. General: National Environmental Policy Act (NEPA) [42 U.S.C. 
4321 et seq.]; Federal-Aid Highway Act [23 U.S.C. 109, 128, and 139].
    2. Air: Clean Air Act [42 U.S.C. 7401-7671(q)].
    3. Noise: Federal-Aid Highway Act of 1970 [Public Law 91-605 [84 
Stat. 1713]; 23 U.S.C. 109(h) and (i)].
    4. Land: Section 4(f) of the Department of Transportation Act of 
1966 [ 23 U.S.C. 138 and 49 U.S.C. 303].
    5. Wildlife: Endangered Species Act (ESA) [16 U.S.C. 1531-1544 and 
Section 1536]; Fish and Wildlife Coordination Act [16 U.S.C. 661-
667(d)]; Migratory Bird Treaty Act [16 U.S.C. 703-712].
    6. Historic and Cultural Resources: Section 106 of the National 
Historic Preservation Act of 1966, as amended [54 U.S.C. 306108 et 
seq.]; Archeological Resources Protection Act of 1977 [16 U.S.C. 
470(aa)-470(mm)]; Archeological and Historic Preservation Act [54 
U.S.C. 312501-3125-8]; Native American Grave Protection and 
Repatriation Act (NAGPRA) [25 U.S.C. 3001-3013].
    7. Social and Economic: American Indian Religious Freedom Act [42 
U.S.C. 1996]; Farmland Protection Policy Act (FPPA) [7 U.S.C. 4201-
4209].
    8. Wetlands and Water Resources: Clean Water Act (Section 319, 
Section 401, Section 404) [33 U.S.C. 1251-

[[Page 59298]]

1387]; Safe Drinking Water Act [42 U.S.C. 300f-300j-26]; TEA-21 
Wetlands Mitigation [23 U.S.C. 103(b)(6)(m), 133(b)(11)]; Flood 
Disaster Protection Act [42 U.S.C. 4001-4128]; Wild and Scenic Rivers 
Act [16 U.S.C. 1271-1287]; Emergency Wetlands Resources Act [16 U.S.C. 
3921, 3931]; Rivers and Harbors Act of 1899 [33 U.S.C 401-406].
    9. Hazardous Materials: Comprehensive Environmental Response, 
Compensation, and Liability Act (CERCLA), as amended by the Superfund 
Amendments and Reauthorization Act of 1986 (SARA) [42 U.S.C. 9601 et 
seq.]; Resource Conservation and Recovery Act (RCRA) [42 U.S.C. 6901-
6992(k)].
    10. Executive Orders: E.O. 11990 Protection of Wetlands; E.O. 11988 
Floodplain Management; E.O. 11593 Protection and Enhancement of 
Cultural Resources; E.O. 13007 Indian Sacred Sites; E.O. 13287 Preserve 
America; E.O. 13175 Consultation and Coordination with Indian Tribal 
Governments; E.O. 11514 Protection and Enhancement of Environmental 
Quality; E.O. 13112 Invasive Species.

(Catalog of Federal Domestic Assistance Program Number 20.205, 
Highway Planning and Construction. The regulations implementing 
Executive Order 12372 regarding intergovernmental consultation on 
Federal programs and activities apply to this program.)


    Authority:  23 U.S.C. 139(l)(1).

Sabrina S. David,
Division Administrator, Georgia Division, Federal Highway 
Administration.
[FR Doc. 2026-19098 Filed 9-17-26; 8:45 am]
BILLING CODE 4910-RY-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on September 18, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.