Notice2026-18991

Vinton Dome Storage Hub, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Vinton Dome Storage Hub Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 16, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 178 (Wednesday, September 16, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 178 (Wednesday, September 16, 2026)]
[Notices]
[Pages 58669-58670]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-18991]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP26-544-000]


Vinton Dome Storage Hub, LLC; Notice of Schedule for the 
Preparation of an Environmental Assessment for the Vinton Dome Storage 
Hub Project

    On June 22, 2026, Vinton Dome Storage Hub, LLC (Vinton Dome) filed 
an application in Docket No. CP26-544-000 requesting a Certificate of 
Public Convenience and Necessity pursuant to Section 7(c) of the 
Natural Gas Act to construct a new natural gas storage facility in 
Calcasieu Parish, Louisiana as part of the Vinton Dome Storage Hub 
Project (Project). Via the proposed Project, Vinton Dome would 
construct a natural gas storage facility designed for the injection and 
storage of natural gas in underground solution-mined salt caverns and 
the withdrawal of stored natural gas for delivery to interstate natural 
gas transmission pipelines. The storage facility would be supplied by 
four 24-inch-diameter, new bidirectional natural gas pipelines that 
would interconnect with existing and planned interstate gas 
transmission pipelines owned and operated by others. Vinton Dome states 
the facility would provide a total underground storage capacity of 
approximately 63.5 billion cubic feet (Bcf) of natural gas, with a 
working gas capacity of 44.5 Bcf.
    On June 30, 2026, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\ The EA will be 
issued for a 30-day comment period.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1788277558.

---------------------------------------------------------------------------

[[Page 58670]]

Schedule for Environmental Review

Issuance of EA--January 29, 2027
90-day Federal Authorization Decision Deadline \2\--April 29, 2027
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per Title 18 Code of Federal 
Regulations 157.22(a), the Commission's deadline for other agency's 
decisions applies unless a schedule is otherwise established by 
federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Vinton Dome Storage Hub Project would consist of the following 
facilities:
    <bullet> five salt dome storage caverns, each 8.9 Bcf in working 
gas capacity and 3.8 Bcf in bas capacity for a total per cavern 
capacity of 12.7 Bcf;
    <bullet> six raw groundwater withdrawal and six class II brine 
disposal wells, including associated pumping and pipeline systems;
    <bullet> one cavern leaching plant;
    <bullet> one 55,000-horsepower (hp) compressor station with 10 
Caterpillar 3616 natural gas driven reciprocating compressor engines at 
5,500 hp per unit, with appurtenant and auxiliary equipment;
    <bullet> a northern header system, consisting of approximately 
16.02-mile-long dual 24-inch-diameter, bidirectional natural gas 
pipelines and six interconnects with other interstate gas transmission 
pipelines with metering and regulation stations;
    <bullet> and an eastern header system, consisting of approximately 
16.27-mile-long dual 24-inch-diameter, bidirectional natural gas 
pipelines, three interconnects with metering and regulation stations, 
and three dual 24-inch-diameter, bidirectional natural gas lateral 
pipelines totaling approximately 0.88 mile to interconnect with four 
existing interstate gas transmission pipelines and metering and 
regulation stations.

Background

    On July 29, 2026, the Commission issued a Notice of Scoping Period 
Requesting Comments on Environmental Issues for the Proposed Vinton 
Dome Storage Hub Project (Notice of Scoping). The Notice of Scoping was 
sent to affected landowners; federal, state, and local government 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; other interested parties; and local libraries 
and newspapers. The Commission received comments regarding concerns 
over cumulative effects of natural gas facilities in the vicinity; 
effects on groundwater, local water supplies, wetlands, and waterways; 
as well as comments regarding effects on impacted communities. 
Commentors also requested more transparency of privileged and 
confidential information and questioned whether Vinton Dome has the 
qualifications to construct a natural gas storage facility. All 
substantive comments received will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#f3bca3a3b395968190dd949c85"><span class="__cf_email__" data-cfemail="baf5eaeafadcdfc8d994ddd5cc">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the FERC 
website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select ``General 
Search'' from the eLibrary menu, enter the selected date range and 
``Docket Number'' excluding the last three digits (i.e., CP26-544), and 
follow the instructions. For assistance with access to eLibrary, the 
helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
<a href="/cdn-cgi/l/email-protection#ce888b9c8d81a0a2a7a0ab9dbbbebea1bcba8ea8abbcade0a9a1b8"><span class="__cf_email__" data-cfemail="9cdad9cedfd3f2f0f5f2f9cfe9ececf3eee8dcfaf9eeffb2fbf3ea">[email&#160;protected]</span></a>. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

(Authority: 18 CFR 2.1)

    Dated: September 11, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-18991 Filed 9-15-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>