Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 178 (Wednesday, September 16, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 178 (Wednesday, September 16, 2026)]
[Notices]
[Pages 58667-58669]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-18988]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14787-004]


Black Canyon Hydro, LLC; Notice of Intent To Prepare a 
Supplemental Environmental Impact Statement for the Seminoe Pumped 
Storage Project, Schedule for Environmental Review, and Request For 
Comments

    The staff of the Bureau of Land Management (BLM) requires 
additional environmental analysis to support its decision on a right-
of-way (ROW) application for the Seminoe Pumped Storage Project No. 
14787 (Seminoe Project). BLM staff, in cooperation with Federal Energy 
Regulatory Commission (FERC or Commission) staff, will prepare a 
supplement (supplemental EIS) to the June 12, 2026 final environmental 
impact statement for the Seminoe Project. The supplemental EIS will 
supplement discussions of the environmental impacts of the proposed BLM 
ROW application associated with the Seminoe Project. Additionally, the 
BLM will discuss and analyze amending components of the Rawlins 
Resource Management Plan (RMP), listed in the Alternatives Considered 
section of this notice. The Seminoe Project would be located at the 
Bureau of Reclamation's (Reclamation) Seminoe Reservoir on the North 
Platte River in Carbon County, Wyoming, approximately 35 miles 
northeast of Rawlins, Wyoming.\1\ The BLM will use this supplemental 
EIS in its decision-making process in compliance with National 
Environmental Policy Act (NEPA) of 1969, as amended, and the Federal 
Land Policy and Management Act (FLPMA) of 1976. The schedule for 
preparing the supplemental EIS is discussed in the Schedule for 
Environmental Review section of this notice.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EISX-019-20-000-1742297464.
---------------------------------------------------------------------------

    As part of the NEPA review process, the BLM and Commission take 
into account concerns the public may have about proposals and the 
environmental impacts that could result whenever it considers the 
issuance of a project. This gathering of public input is referred to

[[Page 58668]]

as ``scoping.'' The Commission previously solicited public input on 
scoping documents for the Seminoe Project. See the final EIS issued 
June 12, 2026, for details on the Commission's previous scoping 
efforts.
    With this notice, the BLM is announcing the beginning of the 
scoping period to solicit public comments and identify issues and is 
providing the planning criteria for public review. The BLM Wyoming 
State Director intends to prepare an RMP Amendment (RMPA) with an 
associated supplemental EIS for the Rawlins Resource Management Plan. 
The RMPA is being considered to allow the BLM to evaluate the ROW 
associated with the Seminoe Pumped Storage Project, which would require 
amending the existing Rawlins RMP.\2\ To ensure that your comments are 
timely and properly recorded, please submit your comments so that the 
Commission receives them in Washington, DC, on or before 5:00 p.m. 
Eastern Time on October 13, 2026.
---------------------------------------------------------------------------

    \2\ The scope of this land use planning process does not include 
addressing the evaluation or designation of Areas of Critical 
Environmental Concern (ACEC) and the BLM is not considering ACEC 
nominations as part of this process.
---------------------------------------------------------------------------

Public Participation

    There are three methods you can use to submit your comments to the 
Commission. The Commission encourages electronic filing of comments and 
has staff available to assist you at (866) 208-3676 or 
<a href="/cdn-cgi/l/email-protection#8ccae9feefc3e2e0e5e2e9dff9fcfce3fef8cceae9feefa2ebe3fa"><span class="__cf_email__" data-cfemail="96d0f3e4f5d9f8fafff8f3c5e3e6e6f9e4e2d6f0f3e4f5b8f1f9e0">[email&#160;protected]</span></a>. Please carefully follow these instructions 
so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) 
under the link to FERC Online. Using eComment is an easy method for 
submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) 
under the link to FERC Online. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the project docket number (P-
14787-004) on your letter. Submissions sent via the U.S. Postal Service 
must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, Maryland 20852.
    Additionally, the Commission offers a free service called 
eSubscription. This service provides automatic notification of filings 
made to subscribed dockets, document summaries, and direct links to the 
documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register 
for eSubscription.
    For public inquiries and assistance with making filings, contact 
the Office of Public Participation at (202)502-6595 or <a href="/cdn-cgi/l/email-protection#c28d929282a4a7b0a1eca5adb4"><span class="__cf_email__" data-cfemail="024d525242646770612c656d74">[email&#160;protected]</span></a>.

Summary of the Proposed Project

    On January 18, 2023, rPlus Hydro, LLLP, on behalf of Black Canyon 
Hydro, LLC (BCH), filed an application pursuant to Part I of the 
Federal Power Act,\3\ for an original major license to construct, 
operate, and maintain the 972-megawatt (MW) Seminoe Project. The 
project as proposed by BCH would occupy 1,043.9 acres of land managed 
by the BLM and 88.2 acres managed by Reclamation. The proposed project 
would involve constructing a new upper reservoir, water conveyance and 
maintenance tunnel system, underground powerhouse, access bridge, and 
two overhead transmission lines. It would use Reclamation's existing 
Seminoe Reservoir on the North Platte River as its lower reservoir. 
Project construction would take about 5 years to complete and require 
permanently disturbing approximately 283.3 acres of land and 
temporarily disturbing another 296.2 acres. The project would require 
13,400 acre-feet of water from the Seminoe Reservoir to initially fill 
the new upper reservoir and would require approximately 672 acre-feet 
of make-up water annually to replace water lost due to evaporation and 
seepage. Once operating, the project would cycle back and forth about 
10,800 acre-feet of water between the upper and lower reservoirs. The 
project would pump water from the lower reservoir during off-peak hours 
and generate electricity by discharging water from the upper reservoir 
through three pump-turbines each rated at 324 MW (for a combined total 
generating capacity of 972 MW) located in the underground powerhouse 
when demand is high. The project would be capable of generating 2,916 
gigawatt-hours per year.
---------------------------------------------------------------------------

    \3\ 16 U.S.C. 791(a)-825(r).
---------------------------------------------------------------------------

    The purpose of the proposed project is to provide a new source of 
hydroelectric power and energy storage to the existing electricity grid 
and provide ancillary services to the electrical grid for grid 
reliability and grid stabilization. BCH has applied for a ROW with the 
BLM for components of the proposed project located on BLM-administered 
public lands. The BLM needs to respond to the ROW application and 
determine whether to approve the ROW, and if so, under what terms and 
conditions. Additionally, the BLM needs to analyze the effects to 
socioeconomic, aquatic, and recreation resources and consider an RMPA 
to adequately address management of Visual Resource Management and Big 
Game Crucial Ranges under the proposed project.

The NEPA Process and the Supplemental EIS

    The planning criteria guide the planning effort and lay the 
groundwork for effects analysis by identifying the preliminary issues 
and their analytical frameworks. Preliminary issues for the planning 
area have been identified by BLM personnel and from early engagement 
conducted for this planning effort with Federal, State, and local 
agencies; Tribes; and other stakeholders. The BLM has identified the 
following preliminary issues for this planning and NEPA effort's 
analysis:
    <bullet> Visual Resource Management: is the proposed ROW compatible 
with the current visual resource management classifications in the 
approved RMP for BLM-administered public lands?
    <bullet> Crucial Big Game Habitats: is the proposed ROW compatible 
with allocations in the approved RMP for the management of crucial big 
game ranges on BLM-administered public lands?
    <bullet> Socioeconomic Resources: under the proposed ROW, what are 
the reasonably foreseeable future effects to the local economy 
(including the hunting, fishing, and tourism industries) in central 
Wyoming?
    <bullet> Aquatic Resources: under the proposed ROW, what are the 
reasonably foreseeable future effects to the aquatic habitats and water 
quality of the North Platte River Blue Ribbon trout fishery (i.e., 
within the Miracle Mile reach of the North Platte River)?
    <bullet> Recreation: under the proposed ROW, what are the 
reasonably foreseeable future effects to the recreational accessibility 
of BLM-administered public lands in the vicinity of the project?

[[Page 58669]]

    The supplemental EIS will present BLM's independent analysis of the 
issues. The Commission and the following other entities will cooperate 
with BLM in preparing the supplemental EIS: Reclamation, the U.S. Fish 
and Wildlife Service (FWS), the U.S. Army Corps of Engineers (Corps), 
the Western Area Power Administration, the Saratoga-Encampment-Rawlins 
Conservation District, the Medicine Bow Conservation District, and the 
Board of Carbon County Commissioners.
    Per 43 CFR 1610.2(e), a draft supplemental EIS would be issued for 
a 90-day comment period. Any draft and final supplemental EIS will be 
available in electronic format in the public record through 
eLibrary.\4\ If eSubscribed, you will receive instant email 
notification when the environmental document is issued.
---------------------------------------------------------------------------

    \4\ For instructions on connecting to eLibrary, refer to the 
Additional Information section of this notice this notice.
---------------------------------------------------------------------------

    The BLM will provide additional opportunities for public 
participation consistent with the NEPA and land use planning processes, 
including a 90-day comment period (per 43 CFR 1610.2(e)) on the Draft 
RMPA and supplemental EIS and will provide a concurrent 30-day public 
protest period and 60-day Governor's consistency review on the Proposed 
RMPA. BLM anticipates the Proposed RMPA and final supplemental EIS will 
be available for public protest of the Proposed RMPA Summer 2027 with 
an Approved RMPA and Record of Decision.

Alternatives Under Consideration

    As part of the review in the supplement EIS, BLM staff will 
consider a range of reasonable alternatives that are technically and 
economically feasible and meet the purpose and need for the proposed 
action. Alternatives that do not meet these requirements will be 
summarized and dismissed from further consideration in the supplemental 
EIS document.
    The BLM will incorporate by reference the action alternatives from 
the Seminoe Project final EIS that cover the BLM ROW application. In 
its description of the proposed action, the BLM may describe additional 
design features from the ROW application. The alternatives may consider 
additional mitigation measures to protect BLM-administered public lands 
and land users.
    The BLM will consider amending land use plan decisions, 
allocations, and management direction to adequately address management 
of Visual Resource Management and Big Game Crucial Ranges.
    The alternatives BLM is considering may be expanded based on the 
comments received, provided they meet the required criteria. With this 
notice, BLM asks commenters to identify other potential reasonable 
alternatives for consideration.

Schedule for Environmental Review

    This Notice of Intent identifies the planned schedule for 
completion of the draft and final supplemental EISs for the project, 
which is based on an issuance of the draft supplemental EIS on January 
14, 2026, opening a 90-day public comment period.\5\
---------------------------------------------------------------------------

    \5\ The project schedule includes a 90-day comment period for 
the draft supplemental EIS to accommodate BLM's requirements under 
its regulations at 43 CFR 1610.2(e).

Issuance of Notice of Availability of the draft supplemental EIS 
January 14, 2027
Issuance of Notice of Availability for the final supplemental EIS July 
16, 2027

    The project is covered under Title 41 of the Fixing America's 
Surface Transportation Act (FAST-41). Under FAST-41, agencies are to 
publish completion dates for all federal environmental reviews and 
authorizations. This notice identifies the Commission's anticipated 
schedule for issuance of the final order for the project, which is 
based on the revised issuance date for the final supplemental EIS. We 
currently anticipate issuing the final order for the project no later 
than:

Issuance of the License Order--October 21, 2027

Additional Information

    Additional information about the project is available on the FERC 
website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the eLibrary link. Click on the eLibrary 
link, click on ``General Search'' and enter the Docket No. P-14787 in 
the ``Docket Number'' field. Be sure you have selected an appropriate 
date range. For assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#75331007163a1b191c1b10260005051a070135131007165b121a03"><span class="__cf_email__" data-cfemail="f5b3908796ba9b999c9b90a68085859a8781b593908796db929a83">[email&#160;protected]</span></a> or (866) 208-3676, or for TTY, contact (202) 
502-8659.
    Any questions regarding this notice may be directed to Michael Tust 
at (202) 502-6522 or <a href="/cdn-cgi/l/email-protection#c8a5a1aba0a9ada4e6bcbdbbbc88aeadbaabe6afa7be"><span class="__cf_email__" data-cfemail="0d60646e656c68612379787e794d6b687f6e236a627b">[email&#160;protected]</span></a>. Questions pertaining to 
BLM's processes, including for the RMPA, should be directed to Kris 
Kirby, acting BLM Wyoming State Director, at <a href="/cdn-cgi/l/email-protection#e78c8c8e95859ea7858b8ac9808891"><span class="__cf_email__" data-cfemail="5338383a21312a13313f3e7d343c25">[email&#160;protected]</span></a>.

(Authority: 18 CFR 2.1)

    Dated: September 11, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-18988 Filed 9-15-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on September 16, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.