Columbia Gas Transmission, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Majorsville-Heard Storage Complex Abandonment Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 14, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 176 (Monday, September 14, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 176 (Monday, September 14, 2026)]
[Notices]
[Page 58111]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-18772]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP26-527-000]


Columbia Gas Transmission, LLC; Notice of Schedule for the 
Preparation of an Environmental Assessment for the Majorsville-Heard 
Storage Complex Abandonment Project

    On May 21, 2026, Columbia Gas Transmission, LLC filed an 
application in Docket No. CP26-527-000 requesting Authorization 
pursuant to Section 7(b) of the Natural Gas Act to abandon certain 
natural gas pipeline facilities. The proposed project is known as the 
Majorsville-Heard Storage Complex Abandonment Project (Project) and 
would eliminate Columbia's need for continued operating and maintenance 
of facilities that are no longer required to meet Columbia's current 
firm service obligations.
    On June 5, 2026, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1785328565.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA--November 30, 2026
90-day Federal Authorization Decision Deadline \2\--February 28, 2027
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.
---------------------------------------------------------------------------

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Columbia proposes to abandon the Heard Storage Field, the 
Majorsville Shallow Storage Field, and the Majorsville Deep Storage 
Field, including all associated facilities and base gas, located in 
Marshall County, West Virginia and Greene and Washington Counties, 
Pennsylvania. Specifically, Columbia proposes to abandon 57 injection/
withdrawal wells, 14 observation wells, the Majorsville Compressor 
Station, and all associated pipelines and aboveground appurtenances.

Background

    On June 30, 2026, the Commission issued a Notice of Scoping Period 
Requesting Comments on Environmental Issues for the Proposed 
Majorsville-Heard Storage Complex Abandonment Project (Notice of 
Scoping). The Notice of Scoping was sent to affected landowners; 
federal, state, and local government agencies; elected officials; 
environmental and public interest groups; Native American tribes; other 
interested parties; and local libraries and newspapers. The Commission 
received no comments in response to the Notice of Scoping.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202)502-6595 or <a href="/cdn-cgi/l/email-protection#c986999989afacbbaae7aea6bf"><span class="__cf_email__" data-cfemail="511e010111373423327f363e27">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the FERC 
website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select ``General 
Search'' from the eLibrary menu, enter the selected date range and 
``Docket Number'' excluding the last three digits (i.e., CP26-527), and 
follow the instructions. For assistance with access to eLibrary, the 
helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
<a href="/cdn-cgi/l/email-protection#0a4c4f584945646663646f597f7a7a65787e4a6c6f7869246d657c"><span class="__cf_email__" data-cfemail="f3b5b6a1b0bc9d9f9a9d96a08683839c8187b395968190dd949c85">[email&#160;protected]</span></a>. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

(Authority: 18 CFR 2.1)

    Dated: September 9, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-18772 Filed 9-11-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on September 14, 2026.