Erie Boulevard Hydropower, L.P.; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
August 7, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 151 (Friday, August 7, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 151 (Friday, August 7, 2026)]
[Notices]
[Pages 51169-51170]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-16170]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2538-102]


Erie Boulevard Hydropower, L.P.; Notice of Application Accepted 
for Filing, Soliciting Motions To Intervene and Protests, Ready for 
Environmental Analysis, and Soliciting Comments, Recommendations, 
Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: 2538-102.
    c. Date Filed: August 30, 2024.
    d. Applicant: Erie Boulevard Hydropower, L.P. (Erie).
    e. Name of Project: Beebee Island Hydroelectric Project (project).
    f. Location: On the Black River in Jefferson County, New York.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Steven P. Murphy, Director--U.S. 
Licensing, Brookfield Renewable, 33 West 1st Street South, Fulton, NY 
13069; telephone at (315) 598-6130; email at 
<a href="/cdn-cgi/l/email-protection#3c6f48594c5459521271494e4c54457c5e4e5353575a555950584e5952594b5d5e5059125f5351"><span class="__cf_email__" data-cfemail="93c0e7f6e3fbf6fdbddee6e1e3fbead3f1e1fcfcf8f5faf6fff7e1f6fdf6e4f2f1fff6bdf0fcfe">[email&#160;protected]</span></a>.
    i. FERC Contact: Nicholas Ettema, Project Coordinator, Great Lakes 
Branch, Division of Hydropower Licensing; telephone at (312) 596-4447; 
email at <a href="/cdn-cgi/l/email-protection#234d4a404b4c4f42500d465757464e4263454651400d444c55"><span class="__cf_email__" data-cfemail="84eaede7ecebe8e5f7aae1f0f0e1e9e5c4e2e1f6e7aae3ebf2">[email&#160;protected]</span></a>.
    j. Deadline for filing motions to intervene and protests, comments, 
recommendations, preliminary terms and conditions, and preliminary 
fishway prescriptions: October 5, 2026, by 5:00 p.m. Eastern Time. 
Deadline for filing reply comments: November 17, 2026, by 5:00 p.m. 
Eastern Time.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests, comments, recommendations, preliminary 
terms and conditions, and preliminary fishway prescriptions using the 
Commission's eFiling system at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a>. Commenters can submit brief comments up to 10,000 
characters, without prior registration, using the eComment system at 
<a href="https://ferconline.ferc.gov/QuickComment.aspx">https://ferconline.ferc.gov/QuickComment.aspx</a>. For assistance, please 
contact FERC Online Support at <a href="/cdn-cgi/l/email-protection#dc9a998e9f93b2b0b5b2b98fa9acacb3aea89cbab9aebff2bbb3aa"><span class="__cf_email__" data-cfemail="692f2c3b2a26070500070c3a1c1919061b1d290f0c1b0a470e061f">[email&#160;protected]</span></a>, (866) 208-
3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, you may submit a paper copy. Submissions sent via the U.S. 
Postal Service must be addressed to: Debbie-Anne A. Reese, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426. Submissions sent via any other carrier must be 
addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. The 
first page of any filing should include docket number P-2538-102.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    l. Project Description: The existing project includes: (1) a 92-
foot-long, 26.25-foot-high dam (South Channel dam) with a crest 
elevation of 443.62 feet North American Vertical Datum of 1988 (NAVD 
88); and (2) a 357.6-foot-long, 18-foot-high dam (Beebee Island dam) 
that includes: (a) an 81.5-foot-long powerhouse that is integral with 
the dam that includes: (i) a debris/ice chute with a 2.4-foot-long 
stoplog gate; (ii) an intake structure with a trashrack with 2-inch 
clear bar spacing, four sluice gates, and a skimmer; (iii) a 3.75-
megawatt (MW) vertical propeller turbine-generator and a 4-MW vertical 
Kaplan turbine-generator; (b) a 42-foot-long and 50.5-foot-long 
spillways with 3-foot-high inflatable rubber crest gates that have a 
crest elevation of 430.62 feet NAVD 88; (c) 97.4-foot-long and 61-foot-
long spillways with 3-foot-high wooden flashboards that have a crest 
elevation of 430.62 feet; and (d) a bulkhead section with a 3-foot-long 
sluice gate. Erie proposes to replace the wooden flashboards with 3-
foot-high inflatable rubber crest gates.
    The project's dams create a 20-acre impoundment at a water surface 
elevation of 430.62 NAVD 88. From the impoundment, water flows through 
the powerhouse to a 15-foot-long tailrace that discharges into the 
Black River. From the impoundment, water also flows through a 24-inch 
diameter pipe controlled by a valve in the South Channel dam to provide 
minimum flows to an approximately 1,000-foot-long bypassed reach. The 
generators are connected to the regional electric grid by an 
underground generator lead line. The current license requires a hand-
carry boat access site upstream of the dam and directional signage to 
downstream boat put-in locations.
    Erie proposes to: (1) continue operating the project in a run-of-
river mode and maintain water levels in the impoundment that are no 
lower than 0.5 foot below the crest of the dam or flashboards, if 
present; (2) continue to release a minimum flow of 1,000 cfs or inflow, 
whichever is less, downstream of the project; (3) continue to release a 
year-round minimum flow of 14 cfs from the project impoundment into the 
bypassed reach; (4) continue to implement a Streamflow and Headpond 
Monitoring Plan; (5) continue to implement a Minimum Flow and Fish 
Conveyance Plan, including a provision to release 37 cfs from the ice 
chute from April 1 through November 30; (6) continue to operate and 
maintain the hand-carry boat access site; (7) continue to provide one-
half inch veiling flows over the center section of Beebee Island dam 
from May 1 to October 31; (8) continue to maintain project facilities, 
including fencing and outbuildings, in a dark brown/green color; and 
(9) develop a historic properties management plan.
    m. A copy of the application can be viewed on the Commission's 
website at <a href="http://www.ferc.gov">http://www.ferc.gov</a> using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document (i.e., P-2538). For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the Roswell P. Flower Memorial Library, located at 229 
Washington Street Watertown, NY 13601.
    You may also register online at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a> to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Anyone may submit comments, a protest, or a motion to intervene 
in accordance with the requirements of Rules of Practice and Procedure, 
18 CFR 385.210, .211, and .214. In determining the appropriate action 
to take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the

[[Page 51170]]

proceeding. Any comments, protests, or motions to intervene must be 
received on or before the specified comment date for the particular 
application.
    All filings must (1) bear in all capital letters the title 
``PROTEST,'' ``MOTION TO INTERVENE,'' ``COMMENTS,'' ``REPLY COMMENTS,'' 
``RECOMMENDATIONS,'' ``PRELIMINARY TERMS AND CONDITIONS,'' or 
``PRELIMINARY FISHWAY PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name of the person 
protesting or intervening; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, 
recommendations, terms and conditions or prescriptions must set forth 
their evidentiary basis and otherwise comply with the requirements of 
18 CFR 4.34(b). Agencies may obtain copies of the application directly 
from the applicant. A copy of any protest or motion to intervene must 
be served upon each representative of the applicant specified in the 
particular application. A copy of all other filings in reference to 
this application must be accompanied by proof of service on all persons 
listed on the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#7b342b2b3b1d1e0918551c140d"><span class="__cf_email__" data-cfemail="0c435c5c4c6a697e6f226b637a">[email&#160;protected]</span></a>.
    o. The applicant must file on or before 5:00 p.m. Eastern Time on 
October 5, 2026: (1) a copy of the water quality certification; (2) a 
copy of the request for certification, including proof of the date on 
which the certifying agency received the request; or (3) evidence of 
waiver of water quality certification.
    p. Final amendments to the application must be filed with the 
Commission on or before 5:00 p.m. Eastern Time on September 3, 2026.

(Authority: 18 CFR 2.1.)

     Dated: August 4, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-16170 Filed 8-6-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>