Notice2026-16044

Duke Energy Carolinas, LLC; Belews Creek; Notice of Hearing

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
August 6, 2026

Issuing agencies

Nuclear Regulatory Commission

Abstract

The U.S. Nuclear Regulatory Commission (NRC) is providing public notice for an uncontested hearing on NRC staff's review of the early site permit (ESP) application, from Duke Energy Carolinas, LLC, (Duke Energy) for the Belews Creek Site located in Sauratown Township, Stokes County, and Belews Creek Township, Forsyth County, North Carolina.

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 150 (Thursday, August 6, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 150 (Thursday, August 6, 2026)]
[Notices]
[Pages 50896-50897]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-16044]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 52-055; NRC-2025-2161]


Duke Energy Carolinas, LLC; Belews Creek; Notice of Hearing

AGENCY: Nuclear Regulatory Commission.

ACTION: Early site permit application; notice of uncontested hearing.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is providing 
public notice for an uncontested hearing on NRC staff's review of the 
early site permit (ESP) application, from Duke Energy Carolinas, LLC, 
(Duke Energy) for the Belews Creek Site located in Sauratown Township, 
Stokes County, and Belews Creek Township, Forsyth County, North 
Carolina.

DATES: The hearing is scheduled for September 17, 2026, from 5 p.m. to 
9 p.m. eastern time (ET) at the Ronald W Reagan Building 
(Administration Building) 1014 Main Street, Hwy 89, Danbury, NC 27016.

ADDRESSES: Please refer to Docket ID NRC-2025-2161 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
    <bullet> Federal Rulemaking Website: Go to <a href="https://www.regulations.gov">https://www.regulations.gov</a> and search for Docket ID NRC-2025-2161. Address 
questions about Docket IDs in <a href="http://Regulations.gov">Regulations.gov</a>to Bridget Curran; 
telephone: 301-415-1003; email: <a href="/cdn-cgi/l/email-protection#efad9d868b888a9bc1ac9a9d9d8e81af819d8cc1888099"><span class="__cf_email__" data-cfemail="7b3909121f1c1e0f55380e09091a153b150918551c140d">[email&#160;protected]</span></a>. For technical 
questions, contact the individual(s) listed in the FOR FURTHER 
INFORMATION CONTACT section of this document.
    <bullet> NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at <a href="https://www.nrc.gov/reading-rm/adams.html">https://www.nrc.gov/reading-rm/adams.html</a>. To begin the search, select ``Begin ADAMS Public Search.'' 
For problems with ADAMS, please contact the NRC's Public Document Room 
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email 
to <a href="/cdn-cgi/l/email-protection#18485c4a364a7d6b776d6a7b7d58766a7b367f776e"><span class="__cf_email__" data-cfemail="2e7e6a7c007c4b5d415b5c4d4b6e405c4d00494158">[email&#160;protected]</span></a>. The Belews Creek ESP application is available 
in ADAMS under Package Accession No. ML25364A004. A copy of the 
application is also available for public inspection at <a href="https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with/applicant-projects/dukeenergy">https://www.nrc.gov/reactors/new-reactors/advanced/who-were-working-with/applicant-projects/dukeenergy</a>.
    <bullet> NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
<a href="/cdn-cgi/l/email-protection#025246502c5067716d77706167426c70612c656d74"><span class="__cf_email__" data-cfemail="603024324e3205130f15120305200e12034e070f16">[email&#160;protected]</span></a> or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. ET, Monday through Friday, except Federal holidays.

FOR FURTHER INFORMATION CONTACT: Emmanuel Sayoc, telephone: 301-415-
4084; email: <a href="/cdn-cgi/l/email-protection#46032b2b272833232a6815273f29250628342568212930"><span class="__cf_email__" data-cfemail="95d0f8f8f4fbe0f0f9bbc6f4ecfaf6d5fbe7f6bbf2fae3">[email&#160;protected]</span></a>; or Kodaran Anand, telephone: 301-
287-0767; email: <a href="/cdn-cgi/l/email-protection#1e55717a7f6c7f70305f707f707a5e706c7d30797168"><span class="__cf_email__" data-cfemail="773c1813160516195936191619133719051459101801">[email&#160;protected]</span></a>. Both are staff of Office of 
Advanced Reactors at the U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001.

SUPPLEMENTARY INFORMATION:

I. Discussion

    By letter dated December 30, 2025 (ADAMS Package Accession No. 
ML25364A004), Duke Energy submitted to the NRC, the ESP application, in 
accordance with the requirements contained in part 52 of title 10 of 
the Code of Federal Regulations (10 CFR), ``Licenses, Certifications, 
and Approvals for Nuclear Power Plants,'' Subpart A, ``Early Site 
Permits.'' Duke Energy is seeking this ESP to approve the Belews Creek 
site for the potential deployment of multiple advanced nuclear 
reactors. Because a specific reactor technology has not yet been 
selected, the ESP application uses the Plant Parameter Envelope (PPE) 
approach. The PPE approach combines information from reactor vendors 
whose technologies are under consideration to define a bounding 
surrogate facility. It identifies the maximum or minimum values for key 
plant parameters across the candidate technologies, and these bounding 
values are used as inputs to the analyses supporting the ESP 
application, which is currently under NRC review.
    Pursuant to Section 189a. of the Atomic Energy Act of 1954, as 
amended, and the Commission Policy Statement on Mandatory Hearings for 
Reactor Licensing (published in the Federal Register on June 8, 2026, 
at 91 FR 34661), notice is hereby given that the uncontested (i.e., 
mandatory) hearing will be held on September 17, 2026, starting at 5 
p.m. (ET) in the Ronald W Reagan Building (Administration Building) 
1014 Main Street, Hwy 89, Danbury, NC 27016. Members of the public are 
invited to attend this hearing. There will be an opportunity for 
members of the public to ask questions and provide feedback on the ESP 
application. This is not an opportunity to request a contested hearing, 
where petitioners can file intervention requests that contain the 
contentions they wish to litigate pursuant to 10 CFR 2.309. The 
opportunity to request a contested hearing and petition for leave to 
intervene was noticed on February 9, 2026 (91 FR 5787) and no 
intervention petitions were received.
    An open house will be held before the hearing begins, from 4:30 
p.m. to 5 p.m., to give the public an opportunity to speak with the NRC 
staff. The hearing will then convene at 5 p.m. and begin with a 
presentation by the NRC staff that will explain the review process and 
provide a brief overview of the application, followed by a comment 
period of up to 3 hours. During the comment period, the public will be 
provided an opportunity to speak on the

[[Page 50897]]

record. Each member of the public will be allowed to speak for no more 
than 5 minutes at a time to ensure that all stakeholders who wish to 
provide oral comments or ask questions will have the opportunity to do 
so.
    The hearing record for comments will remain open until October 1, 
2026. Written comments must be submitted via the following email 
address: <a href="/cdn-cgi/l/email-protection#e7a5828b829094a49582828ca2b4b7caaf8286958e8980a7899584c9808891"><span class="__cf_email__" data-cfemail="2d6f4841485a5e6e5f484846687e7d0065484c5f44434a6d435f4e034a425b">[email&#160;protected]</span></a>. In order to be included in the 
hearing record, written comments must be received by October 1, 2026. 
The NRC staff will not consider comments or questions received via 
other means or after the deadline of October 1, 2026. The NRC staff 
will treat any comments or questions received consistent with the 
Commission Policy Statement on Mandatory Hearings for Reactor 
Licensing.

(Authority: 42 U.S.C. 2011 et seq.)

    Dated: August 4, 2026.

    For the Nuclear Regulatory Commission.
Michelle Hayes,
Chief, Advanced Reactor Licensing Branch 2, Division of Advanced 
Reactor Licensing, Office of Advance Reactors.
[FR Doc. 2026-16044 Filed 8-5-26; 8:45 am]
BILLING CODE 7590-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on August 6, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.