Venice Gathering System, L.L.C.; Notice of Request for Extension of Time

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
May 26, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 100 (Tuesday, May 26, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 100 (Tuesday, May 26, 2026)]
[Notices]
[Pages 30625-30626]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-10397]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP24-93-001]


Venice Gathering System, L.L.C.; Notice of Request for Extension 
of Time

    Take notice that on March 12, 2026, Venice Gathering System, L.L.C. 
(Venice Gathering) requested that the Commission grant an extension of 
time, until April 17, 2027, to construct and place into service its 
Venice Gathering System Pipeline (Project) located near the town of 
Venice, in Plaquemines Parish, Louisiana as authorized in the Order 
Approving Abandonment

[[Page 30626]]

(Order).\1\ The Order required Venice Gathering to complete abandonment 
of the facilities within one year of the date of the Order, or by April 
17, 2026.
---------------------------------------------------------------------------

    \1\ Venice Gathering System, L.L.C., 191 FERC ] 61,055 (2025).
---------------------------------------------------------------------------

    Venice Gathering states that it is in the process of obtaining 
permits needed to start the abandonment activities, but due to 
unforeseen circumstances Venice Gathering requires additional time to 
obtain federal permits. Specifically, Venice Gathering has been 
actively engaged in seeking but has not yet received Regulations and 
Enforcement Authorizations from the Bureau of Ocean Energy Management.
    This notice establishes a 15-calendar day intervention and comment 
period deadline. Any person wishing to comment on Venice Gathering's 
request for an extension of time may do so. No reply comments or 
answers will be considered. If you wish to obtain legal status by 
becoming a party to the proceedings for this request, you should, on or 
before the comment date stated below, file a motion to intervene in 
accordance with the requirements of the Commission's Rules of Practice 
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
Natural Gas Act (NGA) (18 CFR 157.10).
    As a matter of practice, the Commission itself generally acts on 
requests for extensions of time to complete construction for NGA 
facilities when such requests are contested before order issuance. For 
those extension requests that are contested,\2\ the Commission will aim 
to issue an order acting on the request within 45 days.\3\ The 
Commission will address all arguments relating to whether the applicant 
has demonstrated there is good cause to grant the extension.\4\ The 
Commission will not consider arguments that re-litigate the issuance of 
the certificate order, including whether the Commission properly found 
the project to be in the public convenience and necessity and whether 
the Commission's environmental analysis for the certificate complied 
with the National Environmental Policy Act (NEPA).\5\ At the time a 
pipeline requests an extension of time, orders on certificates of 
public convenience and necessity are final and the Commission will not 
re-litigate their issuance.\6\ The Director of the Office of Energy 
Projects, or his or her designee, will act on all of those extension 
requests that are uncontested.
---------------------------------------------------------------------------

    \2\ Contested proceedings are those where an intervenor disputes 
any material issue of the filing. 18 CFR 385.2201(c)(1).
    \3\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
    \4\ Id. at P 40.
    \5\ Similarly, the Commission will not re-litigate the issuance 
of an NGA section 3 authorization, including whether a proposed 
project is not inconsistent with the public interest and whether the 
Commission's environmental analysis for the permit order complied 
with NEPA.
    \6\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
---------------------------------------------------------------------------

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (<a href="http://www.ferc.gov">http://www.ferc.gov</a>). From 
the Commission's Home Page on the internet, this information is 
available on eLibrary. The full text of this document is available on 
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or 
downloading. To access this document in eLibrary, type the docket 
number excluding the last three digits of this document in the docket 
number field.
    User assistance is available for eLibrary and the Commission's 
website during normal business hours from FERC Online Support at (202) 
502-6652 (toll free at 1-866-208-3676) or email at 
<a href="/cdn-cgi/l/email-protection#d6b0b3a4b5b9b8babfb8b3a5a3a6a6b9a4a296b0b3a4b5f8b1b9a0"><span class="__cf_email__" data-cfemail="22444750414d4c4e4b4c47515752524d505662444750410c454d54">[email&#160;protected]</span></a>, or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at 
<a href="/cdn-cgi/l/email-protection#176762757b7e74396572717265727974726578787a577172657439707861"><span class="__cf_email__" data-cfemail="69191c0b05000a471b0c0f0c1b0c070a0c1b060604290f0c1b0a470e061f">[email&#160;protected]</span></a>.
    The Commission strongly encourages electronic filings of comments 
in lieu of paper using the ``eFile'' link at <a href="http://www.ferc.gov">http://www.ferc.gov</a>. In 
lieu of electronic filing, you may submit a paper copy which must 
reference the Project docket number.
    To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
    To file via any other courier: Debbie-Anne A. Reese, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#a2edf2f2e2c4c7d0c18cc5cdd4"><span class="__cf_email__" data-cfemail="cb849b9b8badaeb9a8e5aca4bd">[email&#160;protected]</span></a>.
    Comment Date: 5:00 p.m. Eastern Time on June 4, 2026.

(Authority: 18 CFR 2.1.)

     Dated: May 20, 2026.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2026-10397 Filed 5-22-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on May 26, 2026.