Skip to main content
Notice2026-09880

In the Matter of Kairos Power LLC; Hermes Test Reactor; Extension of Latest Date for Completion of Construction

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
May 18, 2026

Issuing agencies

Nuclear Regulatory Commission

Abstract

The U.S. Nuclear Regulatory Commission (NRC) has approved the Kairos Power LLC (Kairos) request to amend Construction Permit No. CPTR-6 for the Hermes test reactor facility in Oak Ridge, Tennessee. The approved amendment extends the latest date for completion of the construction of the Hermes test reactor facility from December 31, 2026, to April 30, 2029.

Indexed from Federal Register on May 18, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.