In the Matter of Kairos Power LLC; Hermes Test Reactor; Extension of Latest Date for Completion of Construction
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
The U.S. Nuclear Regulatory Commission (NRC) has approved the Kairos Power LLC (Kairos) request to amend Construction Permit No. CPTR-6 for the Hermes test reactor facility in Oak Ridge, Tennessee. The approved amendment extends the latest date for completion of the construction of the Hermes test reactor facility from December 31, 2026, to April 30, 2029.