Notice of Issuance of the Department of the Army Program Comment for Army Warfighting Readiness and Associated Infrastructure

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
May 5, 2026
Effective
April 3, 2026

Issuing agencies

Advisory Council on Historic Preservation

Abstract

The Advisory Council on Historic Preservation has issued a program comment for the U.S. Department of the Army that sets forth how the Army may comply with Section 106 of the National Historic Preservation Act on Army installations for its warfighting readiness activities and associated infrastructure, including: training, testing, equipping, and industrial activities and management actions on associated infrastructure.

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 86 (Tuesday, May 5, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 86 (Tuesday, May 5, 2026)]
[Notices]
[Pages 24249-24259]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-08674]


=======================================================================
-----------------------------------------------------------------------

ADVISORY COUNCIL ON HISTORIC PRESERVATION


Notice of Issuance of the Department of the Army Program Comment 
for Army Warfighting Readiness and Associated Infrastructure

AGENCY: Advisory Council on Historic Preservation.

ACTION: Notice of issuance of the Department of the Army Program 
Comment for Army Warfighting Readiness and Associated Infrastructure.

-----------------------------------------------------------------------

SUMMARY: The Advisory Council on Historic Preservation has issued a 
program comment for the U.S. Department of the Army that sets forth how 
the Army may comply with Section 106 of the National Historic 
Preservation Act on Army installations for its warfighting readiness 
activities and associated infrastructure, including: training, testing, 
equipping, and industrial activities and management actions on 
associated infrastructure.

DATES: The Program Comment went into effect on April 3, 2026.

ADDRESSES: Address any questions concerning the Program Comment to 
Jaime Loichinger, Office of Federal Agency Programs, Advisory Council 
on Historic Preservation, 401 F Street NW, Suite 308, Washington, DC 
20001, <a href="/cdn-cgi/l/email-protection#68020407010b0001060f0d1a28090b0018460f071e"><span class="__cf_email__" data-cfemail="3b51575452585352555c5e497b5a58534b155c544d">[email&#160;protected]</span></a>.

FOR FURTHER INFORMATION CONTACT: Jaime Loichinger, (202) 517-0219, 
<a href="/cdn-cgi/l/email-protection#d8b2b4b7b1bbb0b1b6bfbdaa98b9bbb0a8f6bfb7ae"><span class="__cf_email__" data-cfemail="aec4c2c1c7cdc6c7c0c9cbdceecfcdc6de80c9c1d8">[email&#160;protected]</span></a>.

SUPPLEMENTARY INFORMATION: Section 106 of the National Historic 
Preservation Act, 54 U.S.C. 306108 (Section 106), requires federal 
agencies to consider the effects of projects they carry out, license, 
or assist (undertakings) on historic properties and to provide the 
Advisory Council on Historic Preservation (ACHP) a reasonable 
opportunity to comment with regard to such undertakings. The ACHP has 
issued the regulations that set forth the process through which federal 
agencies comply with these duties. Those regulations are codified at 36 
CFR part 800 (Section 106 regulations).
    Under Section 800.14(e) of those regulations, agencies can request 
the ACHP to provide a ``program comment'' on a particular category of 
undertakings in lieu of conducting individual reviews of each 
individual undertaking under such category, as set forth in 36 CFR 
800.4 through 800.7. An agency can meet its Section 106 
responsibilities with regard to considering the effects of those 
undertakings by taking into account an applicable program comment and 
following the steps set forth in that comment.
    The U.S. Department of the Army (Army) sought a program comment for 
its training, testing, equipping, and industrial activities as well as 
management actions related to its inventory of properties across 135 
Army installations. Actions covered by the program comment would 
include military maneuvers and exercises; military weapons and materiel 
testing on ranges and in facilities; research, development, testing, 
evaluation, manufacturing, storing, maintaining, shipping, and 
disposing of materiel; and maintenance, repair, rehabilitation, 
renovation, abatement of hazardous materials, mothballing, cessation of 
maintenance, demolition, new construction, lease, transfer, or 
conveyance as management actions. These actions present a potential for 
adverse effects to historic properties.
    The ACHP issued the Program Comment for Army Warfighting Readiness 
and Associated Infrastructure (Program Comment) on April 3, 2026. The 
Section 106 regulations require that the Program Comment be published 
in the Federal Register. This Federal Register notice fulfills the 
Army's notification requirement at 36 CFR 800.14(e)(5)(i).

I. Need for the Program Comment

    The Army's warfighting readiness mission is defined by 10 U.S.C. 
7062. This Program Comment supports the statutory military readiness 
mission. It accelerates and improves Section 106 compliance for Army 
warfighting readiness and associated infrastructure by using defined 
standards and procedures to ensure predictable outcomes. The Program 
Comment also enables Army-wide warfighting readiness while balancing 
Section 106 historic preservation requirements. It allows the Army to 
manage its portfolio of historic properties effectively while ensuring 
it can adapt its infrastructure to meet modern defense challenges and 
execute warfighting readiness activities at mission speed.

[[Page 24250]]

II. Overview

    The Army has 250 years of experience designing, building, 
operating, and maintaining military infrastructure. Since its origins 
as the Continental Army in 1775, the Army has designed and constructed 
a broad portfolio of real property assets. The Army has an 
infrastructure of 14 million acres and 135 installations with over 
390,000 buildings and structures exceeding one billion square feet, 
designed, built, and managed by the Army for warfighting readiness 
purposes. Since 1866, the Army's construction of buildings has relied 
on standardized Army-wide plans and designs, resulting in nearly 
identical historic building types and installation designs nationwide, 
which are often subject to recurring management actions. The Army 
currently manages over 200,000 properties (122,000 buildings and 
structures and 84,000 archaeological sites). With the Army's large and 
aging inventory of buildings and archaeological sites continually being 
discovered, the number of Army properties that may be subject to 
Section 106 review is projected to exceed 500,000 in the near future.
    The Program Comment utilizes the military landscape as the 
nationwide analytical framework for management of Army historic 
properties. The military landscape is composed of two primary 
components--built infrastructure and natural infrastructure--
collectively termed associated infrastructure. The military landscape 
framework supports consistent and context-sensitive decision making on 
all Army installations. The Program Comment implements this approach 
through a tiered system that aligns with the Army's historic property 
portfolio:
    <bullet> Tier 1--National Historic Landmarks (NHLs);
    <bullet> Tier 2--Properties of Traditional Religious and Cultural 
Importance (PTRCI);
    <bullet> Tier 3--Pre-1941 Built Infrastructure (Non-NHL)/
Archaeological Sites and Districts (Non-PTRCI); and
    <bullet> Tier 4--WWII and Cold War Era Built Infrastructure (1941-
1989) (Non-NHL).
    The Program Comment establishes management review procedures based 
on these tiered property types.

III. Consultation on the Program Comment

    The Army submitted its request for the Program Comment to the ACHP 
on December 18, 2025. The Army sought participation from the public, 
State Historic Preservation Officers (SHPOs), Indian Tribes, Native 
Hawaiian Organizations (NHOs), and other interested parties in the 
Program Comment's development prior to formally submitting its request 
for a Program Comment to the ACHP.
    Upon receipt of the Army's request and in accordance with 36 CFR 
800.14(e)(2),(3), and (4), the ACHP conducted consultation with SHPOs, 
Tribal Historic Preservation Officers (THPOs), Tribes, and NHOs and 
provided for public participation.
    During the ACHP's consultation in January 2026, outreach consisted 
of broadcast emails, social media posts, and a dedicated website for 
the Program Comment. The ACHP conducted two government-to-government 
consultations with Indian Tribes with a total of seven Tribal nations 
represented. Additionally, the ACHP conducted two (2) SHPO meetings 
with a total of 22 states represented in addition to the National 
Conference of State Historic Preservation Officers (NCSHPO). Thirty-
five written comments were received. During consultation, the ACHP 
received comments and questions regarding the Program Comment's scope 
and applicability, its effect on existing Section 106 agreements, and 
its processes for identifying historic properties, assessing effects to 
them, and resolving adverse effects.
    Regarding the Program Comment's scope and applicability, comments 
were received that the category of undertakings subject to the Program 
Comment's terms were overbroad and undefined. Comments also questioned 
the Program Comment's application on lands not managed by the Army. 
Commenters also requested that the provision terminating existing 
Section 106 Memoranda of Agreement (MOAs), Programmatic Agreements 
(PAs), and Army Alternate Procedures (AAPs) be removed, and noted that 
Section 106 agreements must be terminated in accordance with the 
relevant termination processes. Comments regarding identification, 
assessment and resolution efforts generally requested additional 
consultation with consulting parties and raised concerns with the use 
of standard mitigation processes for resolving adverse effects to 
historic properties.
    The Army's request for the Program Comment was considered by ACHP 
membership during the February 12, 2026, ACHP business meeting. Members 
voted in favor of requesting the Army consent to providing an 
additional 45 days for the ACHP to take action on its request. The Army 
provided the additional time, requiring ACHP member action by April 3, 
2026.
    ACHP staff worked with the Army to address the outstanding comments 
and concerns from the Members and ACHP staff. The Army added language 
limiting the Program Comment's application to Army installations, and 
further defined the category of undertakings subject to the Program 
Comment's terms. The Program Comment was revised to acknowledge that it 
is an optional compliance tool, and that existing Section 106 
agreements would have to be terminated in accordance with their own 
provisions. The Army also added detail regarding the processes it would 
follow to consult with Tribes and incorporate Indigenous Knowledge, and 
to notify SHPOs, Tribes, and the ACHP on post-review discoveries. 
Revisions were also made to identify the process by which the Program 
Comment could be amended and to include an expiration date of December 
31, 2055.

V. More Information

    For further information on the Program Comment and its appendices, 
see <a href="https://www.denix.osd.mil/army-pcwr/">https://www.denix.osd.mil/army-pcwr/</a>.

VI. Text of the Program Comment

    Due to their length, the appendices of the issued Program Comment 
are not reproduced here. A copy of the full Program Comment with its 
appendices, and related information, can be found at <a href="https://www.denix.osd.mil/army-pcwr/">https://www.denix.osd.mil/army-pcwr/</a>. The Program Comment for Army Warfighting 
Readiness and Associated Infrastructure with appendices is the document 
linked as ``Program Comment Army Readiness.''
    What follows is the text of the issued Program Comment, minus its 
appendices:

Program Comment for Department of the Army Warfighting Readiness and 
Associated Infrastructure

1.0. Introduction

1.1. Authority

    Section 106 of the National Historic Preservation Act, 54 U.S.C. 
306108 (Section 106 and NHPA), requires Federal agencies to consider 
the effects of their undertakings on historic properties, and afford 
the Advisory Council on Historic Preservation (ACHP) a reasonable 
opportunity to comment with regard to such undertakings. The ACHP 
has issued regulations that set forth the process through which 
Federal agencies comply with their statutory responsibilities. Those 
regulations are codified under 36 CFR part 800 (Section 106 
regulations).
    A Section 106 undertaking is defined in 36 CFR 800.16 as a 
project, activity, or program funded in whole or in part under the 
direct or indirect jurisdiction of a Federal agency,

[[Page 24251]]

including those carried out by or on behalf of a Federal agency; 
those carried out with Federal financial assistance; and those 
requiring a Federal permit, license or approval. Under 36 CFR 
800.14(e), Federal agencies can request the ACHP provide a ``program 
comment'' on a ``category of undertakings'' and, once provided, the 
agency operates under the program comment ``in lieu of'' conducting 
individual reviews of such undertakings under 36 CFR 800.3 to 800.7. 
The category of undertakings addressed under this program comment is 
Department of the Army (Army) warfighting readiness activities and 
management actions on associated infrastructure proposed to take 
place on Army installations across the country.
    A Federal agency can meet its Section 106 responsibilities by 
following the process set forth in an applicable program comment. 
The Army developed and requested the ACHP provide this Program 
Comment for Army Warfighting Readiness and Associated Infrastructure 
to better support Army warfighting readiness.

1.2. Rationale

    The Army's warfighting readiness mission is defined by 10 U.S.C. 
7062. This program comment directly supports the statutory military 
readiness mission. It accelerates and improves Section 106 
compliance for Army warfighting readiness and associated 
infrastructure by reducing bureaucracy, optimizing resources, and 
using defined standards and procedures to ensure predictable 
outcomes. It is an at scale solution that enables Army-wide 
warfighting readiness while balancing NHPA Section 106 historic 
preservation requirements.
    Program comments operate on two key principles: (1) they apply 
to a category of undertakings that in this case are warfighting 
readiness activities and management actions on associated 
infrastructure; and (2) they operate in lieu of 36 CFR 800.3-800.7, 
meaning program comment procedures replace the project-by-project 
review procedures in the regulation. A benefit of program comments 
is that they allow a federal agency to comply with Section 106 in a 
tailored, consistent way for an agency-wide category of undertakings 
rather than addressing each undertaking individually through 
project-by-project review. Program comments enable a federal 
agency's headquarters to establish a broader, more holistic agency-
wide approach to Section 106 compliance than is possible at the 
local level.\i\
    The Army has 250 years of experience designing, building, 
operating, and maintaining military infrastructure. Since its 
origins as the Continental Army in 1775, the Army has designed and 
constructed an enormous portfolio of real property assets. The Army 
has a sprawling infrastructure of 14 million acres and 135 
installations with over 390,000 buildings and structures exceeding 
one billion square feet, designed, built, and managed by the Army 
for warfighting readiness purposes. Since 1866, the Army's 
construction of buildings has relied on standardized Army-wide plans 
and designs, resulting in nearly identical historic building types 
and installation designs nationwide,\ii\ which are subject to many 
recurring management actions. Program comments are designed for 
federal agencies like the Army, that have repetitive management 
actions affecting a large inventory of similar types of historic 
properties and for agencies with programs that generate many similar 
undertakings.\iii\
    The Army currently manages over 200,000 properties subject to 
Section 106 review (122,000 buildings and structures and 84,000 
archaeological sites). With the Army's large and aging inventory of 
buildings and new archaeological sites continually being discovered, 
the number of Army properties subject to Section 106 review is 
projected to exceed 500,000 in the near future. This situation is 
compounded by a complex and inconsistent regulatory environment 
driven by 115 different Army installation-level Section 106 
compliance agreements with State Historic Preservation Offices 
(SHPOs), the ACHP, and others. Under these agreements, project-by-
project reviews occur for actions having no adverse effects, 
standardized Army-wide property types are treated inconsistently 
across states and installations, and military infrastructure is 
often required to meet highly restrictive, high-cost museum-level 
historic preservation standards that impact the economic viability 
of projects.\iv\ A recent ACHP Chairman's report titled ``Report and 
Recommendations on the Application of Federal Historic Preservation 
Standards'' documents the inconsistent application of overly 
restrictive historic preservation standards and similar economic 
impacts.\v\
    This program comment provides a strategic, at scale Army-wide 
solution to its Section 106 compliance challenge. It provides the 
Army with a standardized framework ensuring that appropriate 
preservation standards are applied consistently across all Army 
installations. This is a proven strategy for the Army's built 
infrastructure. The same approach has been successfully implemented 
under four other ACHP-approved program comments covering the Army's 
30,000 historic homes, providing a clear proof of concept for Army 
built infrastructure.\vi\ This program comment recognizes that 
historic Army housing and associated built infrastructure were 
planned and developed in a coordinated manner during the same time 
periods. Under this program comment, they are now treated in the 
same consistent manner for Section 106 compliance purposes.
    This program comment details the specific category of Army 
undertakings, specifies their likely effects on historic properties, 
and outlines the steps the Army takes to ensure those effects are 
considered. Critically, all substantive on-the-ground Army historic 
preservation activities continue under this program comment. The 
Army continues its historic preservation efforts including historic 
property inventory, evaluation, assessment, and treatment activities 
but through a standardized system that aligns with the nature of the 
Army's historic property portfolio and Army mission requirements. 
This program comment approach allows the Army to manage its vast 
portfolio of historic properties more effectively while ensuring it 
can adapt its infrastructure to meet modern defense challenges and 
execute warfighting readiness activities at mission speed.

1.3. Overview

    This program comment implements the military landscape as the 
nationwide analytical framework for management of Army historic 
properties. The military landscape is composed of two primary 
components--built infrastructure and natural infrastructure--
collectively termed associated infrastructure. The military 
landscape framework supports more consistent and context sensitive 
decision making on all Army installations. This program comment 
implements this approach through a tiered system that aligns with 
the Army's historic property portfolio:
    <bullet> Tier 1--National Historic Landmarks (NHLs): The Army's 
20 NHLs are subject to a higher standard of care if they are 
directly and adversely affected by an undertaking. For actions that 
may adversely affect NHLs, Army Secretariat-level project-by-project 
consultation with the ACHP and National Park Service (NPS) occurs to 
minimize harm and inform mitigation measures.
    <bullet> Tier 2--Properties of Traditional Religious and 
Cultural Importance (PTRCI): Tier 2 properties are subject to higher 
standard of care. Proactive and project-by-project consultations are 
conducted by installations with Federally recognized Tribes and 
Native Hawaiian Organizations (NHOs) for actions to identify, 
evaluate, and treat PTRCI.
    <bullet> Tier 3--Pre-1941 Built Infrastructure (Non-NHL)/
Archaeological Sites and Districts (Non-PTRCI): Program comment 
procedures and guidelines are implemented internally by 
installations in coordination with Army commands for actions 
affecting non-NHL pre-1941 built infrastructure and non-PTRCI 
archaeological sites and districts.
    <bullet> Tier 4--WWII and Cold War Era Built Infrastructure 
(1941-1989) (Non-NHL): Adverse effects from the covered undertakings 
to Tier 4 properties have been addressed by extensive mitigative 
documentation and by the physical preservation of period NHL 
properties.

2.0. Program Comment Goal, Category of Undertakings, and Effect

2.1. Goal

    The goal of this program comment is to obtain programmatic 
compliance with Section 106 for the Army's warfighting readiness 
activities and management actions on associated infrastructure on 
Army installations by means of this program alternative under 36 CFR 
800.14(e). This program comment establishes nationwide consistency 
and accelerates Section 106 compliance for Army warfighting 
readiness activities and associated infrastructure.

2.2. Category of Undertakings

    The category of undertakings addressed by this program comment 
is Army warfighting readiness activities and management actions on 
associated infrastructure on Army installations. The warfighting 
readiness

[[Page 24252]]

category of undertakings are detailed in Appendix A. Associated 
infrastructure is detailed in Appendix B, management actions that 
may affect associated infrastructure are also detailed in Appendix 
B.

2.3. Effect

    The category of undertakings addressed by this program comment 
may adversely affect historic properties through ground disturbing 
activities and by management actions occurring on associated 
infrastructure. Adverse effects will be avoided whenever possible, 
and where avoidance may not be possible, adverse effects will be 
resolved through minimization and mitigative measures in accordance 
with this program comment.

3.0 Program Comment Operating Principles

    This program comment applies a tiered historic property 
management system that tailors management to the nature of the 
Army's historic property portfolio.
    This program comment recognizes that Army installations in their 
entirety may be considered bounded, defined military landscapes. 
Military landscapes serve as the nationwide analytical framework for 
management of Army historic properties.
    This program comment recognizes that the Army's historical use 
of standardized construction plans has resulted in nearly identical 
historic building types and installation designs nationwide, which 
are subject to recurring management actions.
    This program comment recognizes the historical and developmental 
connection between Army housing and other built infrastructure on 
installations. ACHP approved program comment guidelines applicable 
to the Army's pre-1941 historic housing will be applied to the 
Army's pre- 1941 built infrastructure (see Appendices C and D) via 
the terms of this program comment.
    This program comment recognizes that Army installations, through 
consultation with Federally recognized Tribes and NHOs, will 
consider Indigenous Knowledge and the significance that Federally 
recognized Tribes and NHOs ascribe to PTRCI.
    This program comment does not affect or in any way alter the 
Army's responsibilities under applicable Treaties, the Native 
American Graves Protection and Repatriation Act, American Indian 
Religious Freedom Act, or Executive Order 13007 Indian Sacred Sites, 
or any requirements other than those of the NHPA.
    This program comment is supported by comprehensive documentation 
of World War II and Cold War era (1941-1989) historic properties 
prepared by the Army and Department of War.\vii\
    This program comment recognizes that the comprehensive 
documentation of World War II and the Cold War era historic 
properties and the physical preservation of Army World War II and 
the Cold War NHLs constitute mitigation addressing the adverse 
effects of warfighting readiness activities and management actions 
on non-NHL historic properties from the WWII and Cold War eras 
(1941-1989).
    The Army will apply the Secretary of the Interior's Standards 
for Rehabilitation to pre-1941 buildings through the procedures and 
guidelines of this program comment. The Army will utilize substitute 
building materials when historic building materials and in-kind 
building materials are not economically or technically feasible. The 
Army intends that most substitute building materials will be 
reversible and can be replaced with in-kind building materials at 
any time.
    As specified below, this program comment recognizes the inherent 
danger and unlikely prospect of identifying intact historic 
properties safely in areas on Army installations where there are 
human health and safety hazards including areas containing 
unexploded ordnance (UXO) such as impact areas and surface danger 
zones, and any contaminated land areas and contaminated properties.
    This program comment identifies National Mitigation Areas that 
preserve a broad range of historic property types and recognizes the 
Army's statement that National Mitigation Areas are an enduring 
compensatory mitigation for adverse effects to historic properties.

4.0 Implementation of the Program Comment

4.1. The Military Landscape

    This program comment implements the military landscape as the 
nationwide analytical framework for managing historic properties in 
the context of the Army's warfighting readiness activities. 
Installation military landscapes are a unique and dynamic nationwide 
asset; they are the only landscapes in the U.S. that have 
historically been and continue to be actively shaped by military 
warfighting readiness missions and activities.
    Unlike static historic military sites such as battlefields or 
military memorials, installation military landscapes are the living, 
evolving manifestation of the Army's past and present warfighting 
readiness activities. Each Army installation in its entirety is a 
military landscape characterized by the following defining features:
    <bullet> A landscape defined by restricted access, controlled 
entry/exit points, and defined borders.
    <bullet> Warfighting readiness activities are the fundamental 
factor influencing the landscape and associated infrastructure 
development.
    <bullet> The siting and layout of installations directly relates 
to the evolution of the military mission over time.
    <bullet> A high degree of similarity in basic military 
components, standardized building designs and overall layout within 
and between installations.
    <bullet> Pre-military historic properties embedded within the 
military landscape.
    The military landscape is composed of two primary components--
built infrastructure and natural infrastructure--collectively termed 
associated infrastructure. Built infrastructure includes the 
buildings and structures under Army Real Property Category Codes 1-
8. Natural infrastructure is under Army Real Property Category Code 
9 and incorporates all Army installation lands (see Appendices A and 
B).
    The military landscape analytical framework recognizes that each 
Army installation is a continuously evolving military landscape. 
Army military landscapes are defined by ongoing infrastructure 
change and modification in response to the changing demands of the 
Army's warfighting readiness mission. Changes in military doctrine, 
training methods, and weapons technology trigger a constant process 
of adaptation, including new construction, demolition, reuse, and 
the physical expansion and contraction of installations. The 
military landscape is a cohesive and dynamic setting, continually 
shaped and defined by the military readiness mission.
    Recognizing the dynamic nature of warfighting readiness 
activities and their role in creating and maintaining the 
installation military landscape is fundamental for historic property 
management in this setting. Installation military landscapes are 
created and maintained by the continuous execution of warfighting 
readiness activities. Warfighting readiness activity-related 
physical changes to the setting of historic properties and visual, 
atmospheric, and audible elements related to warfighting readiness 
activities are features of the military landscape that may 
contribute to the significance of historic properties within that 
setting.
    The installation military landscape is also where warfighting 
readiness activities and the management of pre-military historic 
properties intersect. Pre-military historic properties have their 
own intrinsic non-military significance. Some of those properties, 
such as archaeological sites and PTRCI, may have significance that 
predates military use and may continue to have significance 
independent of military use. The military landscape contextualizes 
management of such pre-military historic properties. Pre-military 
historic properties located within the military landscape setting 
require a dual management approach by installations that addresses 
both their intrinsic historic significance, and their place within 
the operational military landscape setting.

4.2. Historic Property Management Procedures

4.2.1. General

    For warfighting readiness activities and management actions on 
associated infrastructure on Army installations, the identification, 
evaluation, assessment of effect, monitoring, and mitigation of 
adverse effects to historic properties may occur under the 
procedures in this program comment in lieu of individual project-by-
project reviews under 36 CFR 800.3-800.7.
    The Army will define the area of potential effects of covered 
undertakings and will identify historic properties within the area 
of potential effects. The Army will evaluate identified properties 
for eligibility for inclusion in the National Register of Historic 
Places under the applicable National Register criteria. The Army 
will assess the effects of covered undertakings on historic 
properties and identify appropriate treatment measures where there 
are adverse effects. Due to the passage of time, changing 
perceptions of

[[Page 24253]]

significance, or incomplete prior evaluations, reevaluation may be 
needed for properties previously determined eligible or ineligible 
for inclusion in the National Register of Historic Places. For 
certain covered undertakings, the review process will occur 
internally within the Army and as described below, with identified 
exceptions where outside consultation will occur.

4.2.2. Professional Standards and Qualifications

    The Army will conduct all work on historic properties in 
accordance with the Secretary of the Interior's Standards and 
Guidelines for Archeology and Historic Preservation.\viii\ This work 
will be supervised by individuals meeting the applicable Secretary 
of the Interior's Professional Qualification Standards.\ix\ 
Installations satisfy the supervision requirement either by using 
their own qualified staff, or by securing support through a contract 
or other service agreement with a firm or organization having 
qualified personnel that supervise the work on historic properties.
    For all covered undertakings, any efforts pertaining to 
identification, evaluation and mitigation of PTRCI will be conducted 
in consultation with the appropriate Federally recognized Tribes or 
NHOs to ensure those efforts are informed by Indigenous Knowledge.

4.2.3. Management of Tier 1 Properties--Army NHLs

    NHLs are Tier 1 properties under this program comment. NHLs are 
designated by the Secretary of the Interior under the authority of 
the Historic Sites Act of 1935. The Army will treat NHLs with a 
higher standard of care that includes planning to minimize harm to 
NHLs when they may be adversely affected by a covered undertaking. 
The Army Federal Preservation Officer (FPO) will conduct project-by-
project consultation with the ACHP and NPS when NHLs may be directly 
and adversely affected by an undertaking.
    There are 20 designated NHLs located on Army installations, 
including both individual NHL properties and NHL districts. The 
Army's NHLs were constructed by the Army and continue to serve the 
Army's national defense mission.\x\

<bullet> Ladd Field NHL District, Fort Wainwright, AK
<bullet> Fort Huachuca NHL District, Fort Huachuca, AZ
<bullet> Pioneer Deep Space Station, Fort Irwin, CA \xi\
<bullet> National War College, Fort McNair, DC
<bullet> Yuchi Town Archaeological Site, Fort Benning, GA
<bullet> Palm Circle NHL District, Fort Shafter, HI
<bullet> Wheeler Field NHL District, Schofield Barracks, HI
<bullet> Fort Des Moines NHL District, Des Moines, IA (Army is only 
responsible for specific contributing buildings)
<bullet> Rock Island Arsenal NHL District, Rock Island Arsenal, IL
<bullet> Fort Leavenworth NHL District, Fort Leavenworth, KS
<bullet> Launch Complex 33, White Sands Missile Range, NM
<bullet> Trinity Site, White Sands Missile Range, NM
<bullet> Watervliet Arsenal NHL District, Watervliet Arsenal, NY
<bullet> West Point NHL District, US Military Academy, West Point, 
NY
<bullet> Fort Sill NHL District, Fort Sill, OK
<bullet> Carlisle Indian School NHL District, Carlisle Barracks, PA
<bullet> Fort Douglas NHL District, Salt Lake City, UT (transfer out 
of Army ownership is currently underway and once completed this will 
no longer be an Army NHL)
<bullet> Fort Myer NHL District, Fort Myer, VA
<bullet> Quarters 1, Fort Myer, VA
<bullet> Opana Radar Site, Kahuku Training Area, HI

    NHPA Section 306107 ``Planning and actions to minimize harm to 
National Historic Landmarks'' states that prior to the approval of 
any undertaking that may directly and adversely affect an NHL, 
federal agencies will to the maximum extent possible undertake 
planning and actions as may be necessary to minimize harm to the 
landmark. The Federal agency also affords the ACHP a reasonable 
opportunity to comment regarding the adverse effect undertaking. 
Further, 36 CFR 800.10 requires the agency to notify the Secretary 
of the Interior/NPS and invite them to participate in consultation 
where there may be an adverse effect.
    The Secretary of the Interior's Standards and Guidelines for 
Federal Agency Historic Preservation Programs (63 FR 20496, April 
24, 1998) provide agencies with implementing guidelines for NHPA 
Section 306107. Per the Secretary's Guideline at 4(k) pertaining to 
NHLs, when alternatives to avoid an adverse effect to NHLs appear to 
require undue cost or compromise the undertaking's goals and 
objectives, the agency will balance those goals and objectives with 
the intent of Section 306107 of the NHPA.
    Army installations seek to avoid adverse effects to NHLs to the 
maximum extent possible. Where adverse effects to NHLs are 
unavoidable, installations and commands prepare and submit a 
treatment plan for the adversely effected NHL through their chain of 
command to the Army FPO. The NHL treatment plan will indicate why 
the adverse effect is unavoidable and identify the appropriate 
mitigation measure identified in this program comment to minimize 
harm to the NHL.
    The Army FPO will notify and invite the ACHP and NPS to 
participate in a thirty (30) calendar day consultation to address 
adverse effects to NHLs. The Army FPO will consider written comments 
from the ACHP and NPS and may require installations and commands to 
revise NHL treatment plans in consideration of the views provided by 
the ACHP and NPS. Prior to taking any action that adversely affects 
an NHL, the command and installation will receive the FPO's written 
endorsement of the NHL treatment plan. The Army FPO will make the 
approved treatment plan available to the ACHP and NPS for 
informational purposes.

4.2.4. Management of Tier 2 Properties--Properties of Traditional 
Religious and Cultural Importance

    The relationship between the Army and Federally recognized 
Tribes is a government-to-government relationship founded on the 
principle of tribal sovereignty. This unique relationship between 
Federally recognized Tribes and the Army transcends the requirements 
of the NHPA. The Army also has respectful consultative relationships 
with NHOs. Through these relationships, the Army will address the 
significance that Tribes and NHOs attribute to PTRCI.
    Indigenous Knowledge is a unique and valuable form of expertise 
not held by the Army, ACHP, NPS, SHPOs, or anyone other than Indian 
Tribes and NHOs. Indigenous Knowledge is essential for the 
identification and management of PTRCI. The Army will seek and 
incorporate Indigenous Knowledge from Federally recognized Tribes 
and NHOs when identifying and considering the effects of its actions 
on PTRCI. Installations will assess how actions under this program 
comment may affect such properties, considering the cultural values 
and beliefs associated with those properties.
    PTRCI are Tier 2 properties subject to a higher standard of 
care. Prior to planning covered undertakings, installations will 
proactively consult with Federally recognized Tribes and NHOs to 
identify locations of PTRCI on Army installations for the purposes 
of avoiding adverse effects to such properties. Installations may, 
subject to the availability of funds, reimburse travel expenses for 
members of Federally recognized Tribes and NHOs when consulting and 
seeking such Indigenous Knowledge regarding PTRCI. Archaeological 
sites and other properties associated with Federally recognized 
Tribes or NHOs are presumptively treated as potential PTRCI, subject 
to further consultation with the respective Tribes or NHOs. The Army 
will avoid adverse effects to PTRCI to the maximum extent possible.
    If a proposed warfighting readiness activity may have an 
unavoidable adverse effect on a PTRCI, installations will engage in 
a sixty (60) day consultation period with the affected Federally 
recognized Tribes or NHOs to inform the development of a treatment 
plan with appropriate mitigation measures. The recommendations 
provided by the Federally recognized Tribes or NHOs will be a 
primary consideration in preparing the treatment plan. If the 
recommended mitigation is not technically or financially feasible, 
the installation will work with the affected Federally recognized 
Tribes or NHOs to develop a feasible or an alternative mitigation 
measure.
    Following the sixty-day consultation period, the Army may 
proceed with the undertaking in a manner that allows for the 
completion of the mitigation measures outlined in the approved 
treatment plan. Army installations may afford additional time for 
Federally recognized Tribes or NHOs to provide their views on the 
proposed mitigation if there are significant extenuating 
circumstances and there are no major impacts to the timing and cost 
of the undertaking.

[[Page 24254]]

    The confidentiality of any sensitive site information, 
Indigenous Knowledge, and other culturally sensitive information 
provided by Federally recognized Tribes and NHOs should be 
protected.
    Reports prepared for PTRCI will protect the confidentiality of 
sensitive information to the maximum extent possible under 
applicable authorities. Reports addressing the mitigation of PTRCI 
will be provided to the Federally recognized Tribes or NHOs that 
attach significance to those properties.

4.2.5. Management of Tier 3 Properties--Non-NHL Pre-1941 Built 
Infrastructure and Non-PTRCI Archaeological Sites and Archaeological 
Districts

    This program comment recognizes that the Army possesses the 
equivalent professional expertise and access to information as 
SHPOs, NPS, and ACHP regarding pre-1941 built infrastructure and 
non-PTRCI archaeological sites and districts. Covered undertakings 
on Tier 3 properties will be managed by installations in 
coordination with their command. Identification, evaluation, and 
mitigation of such historic properties will be conducted by 
installations in accordance with the Secretary of the Interior's 
Standards and Guidelines for Archeology and Historic Preservation. 
The Army will ensure these activities occur under the supervision of 
individuals that meet the Secretary of the Interior's Professional 
Qualification Standards. When such historic properties may be 
adversely affected, installations will implement the applicable 
standard mitigation measure set forth in this program comment. Such 
activities for Tier 3 properties are reported by installations in 
their annual report prepared in accordance with section 7.

4.2.6. Management of Tier 4 Properties--Built Infrastructure From WWII 
and Cold War Eras (1941-1989) (Properties Constructed in 1941 Through 
and Including 1989)

    Non-NHL built infrastructure from WWII and Cold War eras (1941-
1989) are Tier 4 properties. Adverse effects from the covered 
undertakings to Tier 4 properties have been mitigated by existing 
extensive mitigative documentation and by the physical preservation 
of period NHL properties. The Army's Section 106 compliance for 
representative historic properties constructed during WWII and the 
Cold War eras has been addressed under the following nationwide 
programmatic compliance actions: Programmatic Memorandum of 
Agreement (PMOA) for DOD World War II Temporary Buildings, Program 
Comment for WWII and Cold War Era Army Ammunition Production 
Facilities, Program Comment for Department of Defense WWII and Cold 
War Era Ammunition Storage Facilities, Program Comment for 
Department of Defense Cold War Era Unaccompanied Personnel Housing 
(UPH).\xii\ Documentation of these representative WWII and Cold War 
era properties exists in the extensive studies prepared for those 
Section 106 compliance agreements. Nearly 600 additional Army and 
DoD Cold War era studies are listed in the annotated bibliography at 
<a href="https://www.denix.osd.mil/army-pcwr/">https://www.denix.osd.mil/army-pcwr/</a>, representing comprehensive 
documentation of Cold War era military historic properties.
    In addition to this extensive documentation of WWII and Cold War 
era historic properties, the Army preserves and manages four NHLs 
from the WWII and Cold War eras. Those WWII and Cold War era NHLs 
are Ladd Field NHL District, Fort Wainwright, AK; Launch Complex 33, 
White Sands Missile Range, NM; The Trinity Site, White Sands Missile 
Range, NM; and the Opana Radar Site, Kahuku Training Area, HI:
    <bullet> Ladd Field NHL 1939-1947 period encompasses the 
establishment of Ladd Field as a critical base for Lend-Lease 
operations with the Soviet Union during World War II and its 
subsequent role in early Cold War era research and development, 
particularly related to Arctic military operations.
    <bullet> Launch Complex 33 NHL 1945 to 1957 reflects the site's 
use for the V-2 rocket program after World War II, which was crucial 
for developing Cold War era rocketry and missile technology in the 
United States. While its operational lifespan extended beyond 1957, 
the early years are considered the most significant.
    <bullet> Trinity Site NHL period of significance is centered 
around July 16, 1945. This is the date of the Trinity Test, the 
first detonation of a nuclear weapon. The Trinity test was conducted 
by the Army on White Sands Missile Range at 5:29 a.m., July 16, 
1945, as part of the Manhattan Project.
    <bullet> Opana Radar Site NHL period of significance is December 
7, 1941. This single date marks when the radar site detected the 
incoming Japanese air attack on Pearl Harbor. While the detection 
was not effectively communicated in time to prevent the attack, the 
site represents the earliest warning of the attack and its role in 
the events of that day.
    Associated built infrastructure constructed during the WWII and 
the Cold War eras (1941-1989) has been well documented, and the most 
significant representative properties in the Army inventory are 
preserved and managed as NHLs. Adverse effects of warfighting 
readiness activities and management actions on non-NHL Army WWII and 
Cold War era associated infrastructure are addressed by the existing 
comprehensive documentation and by the physical preservation of 
period NHL properties.

4.2.7. Effect Determinations

    The effects of warfighting readiness activities and management 
actions on associated infrastructure are assessed as follows.

Adverse Effect

    <bullet> Physical damage or destruction of all or part of a Tier 
1, Tier 2, or Tier 3 property.
    <bullet> Alteration of NHLs and pre-1941 non-NHL buildings that 
is not consistent with the Secretary of the Interior Standards for 
Rehabilitation (36 CFR 68.3(b)) as implemented by the guidelines and 
procedures in Appendices C and D.
    <bullet> Removal of a Tier 1, Tier 2, or Tier 3 property from 
its historic location.
    <bullet> Neglect of a Tier 1, Tier 2, or Tier 3 property that 
causes significant deterioration.
    <bullet> Transfer, sale or lease of Tier 1, Tier 2, or Tier 3 
property out of Federal ownership.
    <bullet> Introduction of visual, atmospheric or audible elements 
that diminish the integrity of significant historic features of 
PTRCI.
    <bullet> Change in the character of PTRIC use or physical 
features within their setting that contribute to their significance.
    Tier 4 Properties: Adverse effects to Tier 4 properties will be 
mitigated by the extensive existing documentation (see endnote 7) 
and physical preservation of the most significant NHL examples of 
those properties.
    Interiors of Pre-1941 Buildings: Interior alterations and 
reconfiguration of interior floorplans in pre-1941 built 
infrastructure do not require further review due to the extensive 
modification and modernization that has occurred.\xiii\ Where an 
existing interior floorplan does not accommodate current or changing 
military needs, technology requirements, quality of life 
considerations, force protection requirements, or health and safety 
considerations, floorplan alterations and reconfigurations will 
occur using substitute building materials or any modern industry 
standard building materials.
    Army installations will resolve adverse effects to Tier 1, 2, 
and 3 historic properties following the Mitigation Measures for 
Adversely Affected Historic Properties.

4.2.8. Mitigation Measures for Adversely Affected Historic Properties

    General: The Army will strive to avoid adverse effects to 
historic properties. Where adverse effects to Tier 1, 2, and 3 
historic properties cannot be avoided, a treatment plan will be 
developed by the installation in accordance with the Secretary of 
the Interior's Standards and Guidelines for Archeology and Historic 
Preservation (48 FR 44716, September 29, 1983) to mitigate the 
adverse effect. Treatment plans should be technically and 
financially feasible and focus on mitigation of the historic 
property adversely affected.
    Treatment plans for Tier 1 NHL properties will be developed in 
consultation with the ACHP and NPS. Treatment plans for Tier 2 PTRCI 
will be developed in consultation with Federally recognized Tribes 
and NHOs ascribing significance to the historic property. Treatment 
plans for Tier 3 properties will be developed by the installation in 
coordination with their command. The Army FPO will approve 
installation treatment plans for Tier 1 NHL properties. Commands 
will approve installation treatment plans for Tier 2 and Tier 3 
properties. No treatment plans will be required for Tier 4 
properties since potential adverse effects will be mitigated by the 
extensive existing documentation of representative property types 
and by physical preservation of period NHLs.
    Once completed, Army installations will make mitigation reports 
resulting from the treatment plan available via an installation 
public website or by other means to the ACHP, SHPOs, Tribes, and 
NHOs for informational purposes. Mitigation reports will be subject 
to Army operational security review and be retained by the 
installation in accordance with Army document management and 
retention requirements. Specific locational information for 
sensitive historic properties is protected from

[[Page 24255]]

disclosure to the maximum extent possible in accordance with Section 
304 of the NHPA.
    Standard mitigation measures for buildings, structures, 
districts, objects, and landscapes. Installations may address 
adverse effects to buildings, structures, districts, and landscapes 
associated with warfighting readiness activities that are 
significant under National Register criterion C through 
documentation prepared to the standards of the Historic American 
Building Survey (HABS), Historic American Engineering Record (HAER), 
Historic American Landscapes Survey (HALS) standards, or to 
equivalent State standards, as appropriate. Where such properties 
are significant under other National Register criteria, historical 
documentation appropriate to their significance or signage may be 
prepared.
    Standard mitigation measures for archaeological sites. To 
address adverse effects on archaeological sites and districts, 
installations may implement standard mitigation measures. These may 
include: (1) site avoidance; (2) site protection measures like 
capping or signage; (3) archaeological monitoring of ground-
disturbing activities; or (4) data recovery excavations. Data 
recovery excavations will be conducted in accordance with the 
Secretary of the Interior's Standards and Guidelines for Archeology 
and Historic Preservation. For archaeological sites that are PTRCI, 
Indigenous Knowledge-informed mitigation will occur in accordance 
with the following section regarding mitigation measures for PTRCI. 
If data recovery is pursued, an archaeological site mitigation 
report will be prepared.
    Mitigation measures for properties of traditional religious and 
cultural importance. The Army recognizes that standard mitigation 
measures may not be applicable to PTRCI to Federally recognized 
Tribes and NHOs. To ensure Indigenous Knowledge-informed treatment 
occurs, installations will inform treatment plans through 
government-to-government consultation with the Federally recognized 
Tribe(s) ascribing significance to the property. Installations in HI 
will inform treatment plans through consultation with the NHO(s) 
ascribing significance to the property. For defined landscape areas 
that are considered PTRCI the Army may, as a mitigation measure, 
prepare ethnographic studies in coordination with Federally 
recognized Tribes or NHOs.
    Alternative mitigation measures. The Army may implement 
alternative mitigation measures in lieu of the standard mitigation 
measures for any adversely affected historic property. Alternative 
mitigation involves mitigative measures applied to property types 
other than those directly affected by the undertaking, or another 
type of creative mitigation. The Army may implement alternative 
mitigation on Army installations, Army owned and leased property, 
federal lands withdrawn by Army for military purposes, state lands 
used for federal warfighting readiness activities of the Army 
National Guard, and on properties with conservation easements. 
Alternative mitigations will be included in treatment plans. 
Alternative mitigation measures do not occur when standard 
mitigation measures may be applicable.

4.2.9. Avoiding Duplication of Effort for Mitigation of Pre-1941 Built 
Infrastructure

    In constructing its extensive military infrastructure, the Army 
used standardized designs and plans for buildings, structures, 
districts, landscapes, and for entire installations.\xiv\ The result 
of Army standardization is that the same designs for buildings, 
structures, districts, landscapes, housing, and overall installation 
designs are repeated, one after the other, on Army installations. 
The Army's pre-1941 built infrastructure was constructed following 
Army standardized plans; therefore, Army installations avoid 
duplicating mitigation efforts for such built infrastructure. When 
developing a treatment plan for mitigation of adverse effects to 
pre-1941 built infrastructure, installations and commands may 
identify if similar built infrastructure has been previously 
documented or if known better-preserved examples exist on the 
installation or elsewhere. If prior documentation or better-
preserved examples sufficiently represent the adversely affected 
property, that information should be incorporated into the treatment 
plan to minimize redundant mitigation efforts.

4.2.10. National Mitigation Areas

    National Mitigation Areas are locations where the Army has made 
a commitment to long-term stewardship of significant historic 
properties beyond the requirements of the NHPA. These areas, which 
include two National Monuments designated under the authority of the 
Antiquities Act (54 U.S.C. 32030) and a Native Hawaiian PTRCI, 
contain a high concentration of historic buildings, archaeological 
sites, historic districts, PTRCI, sacred landscapes, and significant 
natural resources and geological features.
    The Army's NMAs are nationally significant heritage resources 
and represent an investment in historic preservation at a landscape 
scale. The Army's preservation of these areas can serve as 
compensatory mitigation for adverse effects to historic properties 
for areas with health and safety hazards as described below, and as 
an alternative mitigation option. The National Mitigation Areas are:
    Carlisle Federal Indian Boarding School National Monument, 
Carlisle Barracks, PA: The Carlisle Federal Indian Boarding School 
National Monument was established under the authority of the 
Antiquities Act at the Army's Carlisle Barracks in December 2024 (89 
FR 100289, December 12, 2024). The Army, recognizing the profound 
cultural significance of the Carlisle Indian Industrial School to 
Federally recognized Tribes, partnered with the Department of the 
Interior in this National Monument designation. The school's former 
campus is located within Carlisle Barracks, an Army installation 
with a history dating back to the Revolutionary War. The Barracks 
saw limited use by the Army following the Civil War. In 1879, 
Congress authorized the Secretary of War to transfer vacant military 
posts to the Secretary of the Interior for industrial training of 
Indian youth, including Carlisle Barracks, leading to the school's 
establishment in 1879. The Carlisle Indian School was the Nation's 
first off-reservation Federal Indian boarding school. From 1879 to 
1918, over 7,800 children from 140 Tribes attended the Carlisle 
School. After the Department of the Interior closed the Carlisle 
Indian School, Carlisle Barracks was transferred back to the Army. 
While under Army stewardship the former Carlisle Indian School 
campus was designated as an NHL district in 1961. The 24 NHL 
historic structures associated with the Carlisle Indian School 
include residential, vocational, and athletic buildings that evoke 
the Federal Indian boarding school era. The National Park Service 
now collaborates with the Army and others to share the story of the 
school (see <a href="https://www.nps.gov/cibs/index.htm">https://www.nps.gov/cibs/index.htm</a>).
    Castner Range National Monument, Fort Bliss, TX: Established on 
Fort Bliss in March 2023 (88 FR 17999, March 27, 2023) under the 
authority of the Antiquities Act, the Castner Range National 
Monument encompasses 6,672 acres. The Army ensures the protection of 
sacred sites, PTRCI, and natural ecosystems within the Castner Range 
National Monument (<a href="https://www.denix.osd.mil/crnm/">https://www.denix.osd.mil/crnm/</a>). Castner Range 
remains undeveloped with historic properties preserved due to its 
history of military use. Since the cessation of live-fire exercises 
over half a century ago, Castner Range, under Army stewardship, is 
maintained as a natural Chihuahuan Desert ecosystem. Vital springs 
like Indian Springs, Cottonwood Springs, Mundy Springs, and 
Whispering Springs provide water sources and rare desert habitat for 
plants and wildlife. There are 41 identified prehistoric 
archaeological sites on Castner Range containing ancient pit houses, 
roasting pits, ceramics, bedrock mortars, petroglyphs, and other 
archaeological features and artifacts. The Army has listed 
archaeological sites and districts on Castner Range in the National 
Register of Historic Places including the Fusselman Canyon Rock Art 
District, the Northgate Site, and the Castner Range Archaeological 
District.
    500 Acre Conservation Easement Protecting K[umacr]kaniloko, 
O[revaps]ahu, HI: K[umacr]kaniloko is one of the most sacred Native 
Hawaiian places and is found within the cultural landscape of the 
Wahiaw[amacr] Plateau on O[revaps]ahu. This area was the royal birth 
site for high-ranking chiefs, known as ali[revaps]i, and was 
utilized as a birth site well into the 17th century. 
K[umacr]kaniloko is believed to be the geographical and spiritual 
center of O[revaps]ahu and is also spiritually connected to other 
sacred sites in Hawai[revaps]i (see <a href="https://www.oha.org/wp-content/uploads/Attachment-6-OHA-Kukaniloko-Information-Sheet.pdf">https://www.oha.org/wp-content/uploads/Attachment-6-OHA-Kukaniloko-Information-Sheet.pdf</a>). In 2012 
the Hawai[revaps]i State Legislature authorized $13 million towards 
the purchase of a conservation easement on 500 acres of sacred 
landscape surrounding K[umacr]kaniloko for its protection. Army and 
its conservation partners including the Trust for Public Land and 
the Office of Hawaiian Affairs raised the additional $12 million 
required for purchase of the easement, which included over $4.5 
million from the Army. As a result, the Office of Hawaiian Affairs 
received the 500-acre in-perpetuity easement surrounding 
K[umacr]kaniloko for long-term conservation. The area is not open to 
the

[[Page 24256]]

public and visits are coordinated through the Hawaiian Civic Club of 
Wahiaw[amacr]. The Army provides resources for on-going land 
management and conservation activities on the 500-acre easement.

4.2.11. Limitation on Disclosure of Information

    Section 304 of the NHPA (54 U.S.C. 307103) authorizes Federal 
agencies to withhold from public disclosure information about the 
location, character, or ownership of a historic property if that 
disclosure may cause a significant invasion of privacy, risk harm to 
the historic property, or impede the use of a traditional religious 
site by practitioners. Army compliance with 54 U.S.C. 307103 is 
demonstrated by implementation of the following actions: Army 
installations will ensure that reports, documents, or other 
materials that address the location and character of sensitive 
historic properties (including archaeological sites and PTRCI) are 
prepared and disseminated in a manner that maintains the 
confidentiality of such information. The determination to withhold 
information regarding the location and character of PTRCI is made in 
consultation with the property's affiliated Federally recognized 
Tribes and NHOs and pursuant to the requirements of Section 304.

4.2.12. Health and Safety Hazards

    No further Section 106 review, including historic property 
identification, evaluation, assessment, monitoring, and mitigation 
activities will occur in known areas on Army installations where 
there are human health and safety hazards including areas containing 
unexploded ordnance (UXO) such as impact areas and surface danger 
zones, and contaminated land areas and contaminated properties. It 
is unlikely that historic properties would be identified in these 
areas. Any potential adverse effects that may occur to historic 
properties located in such areas are resolved by the preservation of 
historic properties within the National Mitigation Areas identified 
in this program comment.

4.2.13. Public Outreach, Access, and Comment

    Army installations may foster transparency and strengthen civil-
military relationships by providing public educational tours, 
cultural events, and partnerships with local schools and 
organizations. These programs, which often include museum exhibits 
and tours that highlight Army historic properties and preservation 
initiatives, provide the opportunity for the public to connect with 
heritage firsthand. Installation Public Affairs Offices may be 
contacted at any time for information pertaining to such 
installation public outreach events. For installations with PTRCI, 
access to those historic properties is provided to Tribes and NHOs 
for their cultural use. In addition, opportunities for the public to 
comment on installation activities will occur under installation 
actions to comply with comprehensive environmental review 
requirements. These actions will ensure that the public has a voice 
in decisions that may affect the environment and historic properties 
on installations.

5.0 Discovery of Historic Properties

    The discovery of a historic property during implementation of 
warfighting readiness activities will be addressed by the procedures 
in this section. If the discovery involves Native American or Native 
Hawaiian cultural items or human remains, the Native American Graves 
Protection and Repatriation Act (NAGPRA) and 43 CFR part 10 will be 
followed in lieu of this program comment.
    If an undertaking covered by this program comment has commenced 
and a discovery or unanticipated effects to a non-NAGPRA property 
occur, activities will cease in the immediate area of the discovery. 
The undertaking can continue in areas outside of the immediate 
protected area of the discovery. The installation will notify the 
ACHP, the relevant SHPO, and Federally recognized Tribes or NHOs of 
the discovery and proposed mitigation and will provide them with 
five (5) calendar days to comment.
    The Army will consider any timely comments in assessing the 
National Register of Historic Places eligibility of the property 
under applicable National Register criteria. If the installation 
determines that the property is not a historic property, the 
undertaking can proceed in the area of the discovery. If the 
discovered property is determined by the installation to be a 
historic property and avoidance of adverse effects is not possible, 
the installation and command will consider any timely comments from 
the ACHP and SHPO, Federally recognized Tribe or NHO and prepare and 
implement a technically and financially feasible mitigation measure 
to resolve the adverse effect. If the property is identified by a 
Federally recognized Tribe or NHO as a PTRCI, the views provided by 
the Federally recognized Tribe or NHO will be a primary 
consideration in finalizing the mitigation measure. The undertaking 
may continue in a manner allowing for implementation of the 
mitigation measure. The installation will coordinate the mitigation 
with the command, incorporate command recommendations, carry out the 
mitigation measure, prepare the mitigation report, and summarize the 
action in their annual report.
    If no responses are received within five calendar days of the 
notification, the installation will inform the ACHP, SHPO, Federally 
recognized tribe or NHO that it will implement the mitigation 
proposed by the installation, will make the mitigation report 
available to the ACHP, SHPO, Federally recognized Tribe or NHO, and 
will report the action in their annual report. The installation may 
afford additional time for Federally recognized Tribes or NHOs to 
provide their views if there are significant extenuating 
circumstances and no major impacts to the timing and cost of the 
undertaking.

6.0 Emergency Situations

    In the event that an installation proposes an essential and 
immediate response to a disaster or emergency declared by the 
President, a tribal government, or the Governor of a State or 
another immediate threat to life and property, the Army will 
implement 36 CFR 800.12(b)(2). The Army will notify the ACHP, the 
appropriate SHPO/Tribal Historic Preservation Officer and any Indian 
tribe or NHO that may attach religious and cultural significance to 
historic properties likely to be affected prior to the undertaking 
and afford them an opportunity to comment within seven (7) calendar 
days of notification. If the Army determines that circumstances do 
not permit seven days for comment, the Army will notify the ACHP, 
the SHPO/THPO, and Indian tribe or Native Hawaiian organization and 
invite any comments within the time available.
    This section applies only to undertakings that will be 
implemented within 30 days after the disaster or emergency has been 
formally declared by the appropriate authority. The Army may request 
an extension of the period of applicability from the ACHP prior to 
the expiration of the 30 days. In accordance with 36 CFR 800.12(d), 
immediate rescue and salvage operations conducted to preserve life 
or property are exempt from the provisions of Section 106 and 36 CFR 
part 800.

7.0 Annual Reporting and Annual Meeting

    On or before 1 February of each year, each installation with 
undertakings addressed under this program comment will prepare an 
Annual Installation Program Comment Report for the preceding fiscal 
year. The installation annual report will summarize individual 
undertakings implemented under the program comment and efforts to 
identify, evaluate, assess effects, and avoid or mitigate adverse 
effects to historic properties. The Annual Installation Program 
Comment Report will be published by the installation on a publicly 
accessible website, following applicable requirements for 
information dissemination. When published, the installation will 
inform relevant SHPOs, THPOs, Federally recognized Tribes, and NHOs 
that the annual installation report is available for their 
information. Annual reporting by installations will occur for the 
duration of this program comment.
    After 1 February of each year, the Army FPO will prepare an 
annual Army Program Comment Summary Report for previous fiscal year 
activities. The annual Army report will provide an executive summary 
of activities under the program comment, identifies successes, 
significant challenges, how challenges were addressed, and how they 
may be avoided in the future. The annual report will also include an 
assessment of the overall effectiveness of the program comment in 
meeting its intent. The Army FPO will submit the Program Comment 
Summary Report to the ACHP. Following report submission, the FPO 
will meet with the ACHP and others as appropriate to discuss 
implementation of the program comment. Such annual reporting and 
annual meetings will occur for the duration of the program comment 
and may take place in-person, by phone, videoconference, or any 
combination of such methods.

8.0 Applicability

    The Army implements warfighting readiness activities and 
management actions on associated infrastructure in accordance with 
the terms of this program comment. This program comment applies to 
all warfighting readiness activities and

[[Page 24257]]

management actions on associated infrastructure on installations of 
the Active Army, Army Reserves, and Army National Guard. This 
program comment applies to joint bases where the Army is the lead 
military service. This program comment will apply to all real 
property that is acquired by the Army and incorporated into to an 
existing Army installation.\xv\
    This program comment does not apply to any proposed undertakings 
that would take place off of, or affect historic properties located 
off of Army installations. This program comment does not apply to 
any proposed undertaking that may occur on or affect historic 
properties located on Tribal lands. This program comment does not 
apply to any proposed undertakings at Arlington National Cemetery. 
This program comment does not apply to Army-owned family housing or 
to privatized Army family housing. This program comment does not 
apply to Civil Works activities of the U.S. Army Corps of Engineers.

9.0 Duration

    This program comment is effective upon the date of its adoption 
by the ACHP and remains in effect through December 31, 2055, unless 
withdrawn earlier as provided herein.
    The specified duration of this program comment aligns with the 
expiration dates of three program comments concerning historic Army 
housing.\xvi\ No later than one year prior to the expiration of this 
program comment, the Army and the ACHP may identify a process for 
integration of this program comment and the program comments for 
historic Army housing. The intent is to further standardize Army 
Section 106 compliance procedures into a single comprehensive 
program alternative.

10.0 Amendment and Withdrawal

    Amendment. The terms of this program comment can only be changed 
following the amendment procedures of this program comment. All such 
proposed amendments are submitted by the ACHP to the Army FPO for a 
30-day review and consultation period. Amendments will consider and 
address the Army's comments. Amendments to this program comment are 
subject to a vote and adoption by the ACHP membership. The ACHP will 
publish notice in the Federal Register regarding adopted amendments.
    Withdrawal. If the ACHP membership determines that consideration 
of historic properties is not being carried out in a manner 
consistent with this program comment, the ACHP membership may 
propose withdrawal of the program comment only after consultation 
with the Army to resolve the inconsistency. The ACHP will publish a 
notice in the Federal Register of any vote to withdraw. If this 
program comment is so withdrawn, the Army complies with the 
requirements of 36 CFR 800.3--800.7, or an applicable program 
alternative, for undertakings subject to this program comment.

11.0 Definitions

    The following definitions apply for the purposes of 
implementation of this program comment:
    Abate or abatement means actions to eliminate, lessen, reduce, 
encapsulate, or remove hazardous or toxic materials, and unsafe 
conditions.
    Alternative mitigation means actions taken to offset the 
unavoidable adverse effects of an undertaking on a historic 
property. Alternative mitigation may occur when mitigation actions 
on an adversely affected historic property are not financially or 
technical feasible, where there are national security implications, 
or other extenuating circumstances. Alternative mitigation may occur 
through other mitigative activities involving other historic 
properties.
    Area of potential effects means the same as the term's 
definition at 36 CFR 800.16.
    Associated infrastructure means the totality of all built 
infrastructure and natural infrastructure associated with Army 
warfighting readiness activities.
    Built infrastructure means all buildings, structures, districts, 
objects, sites, and landscapes and landscape features. The built 
infrastructure includes the entire overall design and layout of Army 
installations including but not limited to cantonments, training 
areas, testing areas, ranges, maneuver areas, all buildings, 
structures, landscapes, landscape features, sites, districts, 
objects, facilities, research related properties, industrial and 
manufacturing areas and properties, warehouses, roadways and 
circulation patterns and systems, rail lines, bridges, dams, utility 
systems, mechanical systems, airfields, heliports, energy 
infrastructure, etc. Includes all man- made landscapes and landscape 
features. See Appendix B for additional detail on buildings and 
structures included in the built infrastructure.
    Economic or Financial feasibility means the Army's assessment of 
relevant factors to determine if an action, project, or product to 
address a historic property are financially viable and sustainable. 
It considers the costs of building materials, labor, mitigation, 
among other factors against the available funding and longer-term 
financial resources to ensure the action is realistic, achievable, 
and will effectively preserve or document the property's historical 
value.
    Health or safety hazards means land, buildings or structures 
that have any of the following conditions: violations of health and 
safety codes and standards; structurally unstable roofs or walls; 
non-functional or poorly functioning mechanical systems; rodent, 
insect, or mold infestations, lead based paint exposure risks; 
asbestos exposure risks; sites contaminated with hazardous 
substances, pollutants, contaminates, toxic chemicals and materials, 
or any other environmental hazards; damages due to fire, flooding, 
or natural disasters; and other conditions that present health 
hazards or make the land, buildings or structures unsafe.
    Historic building materials means building materials that were 
used in the initial construction of a building, and for designated 
NHLs it means all materials within the period of significance.
    Historic character means the same as the terms usage in the 
Secretary of the Interior's Standards for the Treatment of Historic 
Properties at 36 CFR part 68.
    Historic district or district means the same as the term's 
definition in 36 CFR 60.3(d). The terms historic district, 
archaeological district, and district are used interchangeably in 
this program comment.
    Historic property means the same as the term's definition in 36 
CFR 800.16.
    Imitative substitute building materials or substitute building 
materials means modern, industry standard, natural, composite, and 
synthetic materials that that simulate the appearance of historic 
materials. They are used as alternatives to historic building 
materials and in-kind building materials when those materials are 
not financially or technically feasible, or where other factors such 
as contamination require replacement of historic building materials. 
The terms imitative substitute building materials and substitute 
building materials are used interchangeably for the purposes of this 
program comment.
    In-kind building materials means new building materials that are 
identical to historic building materials in all possible respects, 
including their composition, design, color, texture, and other 
physical and visual properties.
    Industrial activity means all activities at all Army research 
laboratories, depots, arsenals, and ammunition plants involved in 
research, development, manufacturing, storing, maintaining, and 
disposal of Army weapons and material.
    Installation means an aggregation of contiguous or near 
contiguous, common military mission-supporting real property 
holdings under the jurisdiction, possession, or control of the 
Department of the Army or of a State, commonwealth, territory, or 
the District of Columbia, and at which any unit or activity of the 
Active Army, Army Reserve, or Army National Guard is assigned or 
trains. Includes joint bases where Army is the lead military 
service.
    Land means real estate that is fee-owned by the Federal 
Government and or under custody and accountability of the Army. 
Includes land acquired by purchase, condemnation, donation, 
transfer, permit, lease or other means. Includes reclaimed or 
accredited lands if title is vested in the Federal Government and 
such lands are under custody and accountability of the Army. The 
terms land and Army land are used interchangeably in this program 
comment.
    Landscape and landscape features includes all plantings and 
landscaping, gardens, parade grounds, open spaces, recreational 
landscape features (including but not limited to recreational and 
athletic fields, playgrounds, golf courses, tennis courts, etc.), 
fencing, parking areas, garages, signage, site furnishings, parade 
grounds, lighting, sidewalks and curbing, driveways, setbacks, 
cemeteries, objects, statuary, monuments, archaeological sites and 
districts, and all human influenced landscapes and landscape 
features. Includes all visual elements and viewsheds into historic 
properties and historic districts and out from any historic property 
or historic districts into other historic properties and districts, 
and all other landscape features.
    Lease, transfer, and conveyance means the execution of documents 
for real property

[[Page 24258]]

lease, sale, possession, management, operation, development, 
conveyance, or transfer of real property into or out of Army 
ownership, jurisdiction, or management. Includes execution of 
property transfers and conveyances of ground leases, easements, and 
property ownership. Includes Enhanced Use Leases (EUL) and all EUL 
associated development activities, public land withdrawals, and any 
other form of real property conveyance or transaction. In the event 
of a conflict or inconsistency between a lease, transfer, or 
conveyance document and this program comment with respect to the 
obligations pursuant to Section 106 of the NHPA, the terms of this 
program comment have primacy.
    Maintenance and repair means all activities required to maintain 
the exterior of buildings and structures, mechanical systems, and 
exterior building features, elements, and materials in an 
operational state, or to bring them back to operating condition by 
repair or replacement of obsolete, broken, damaged, or deteriorated 
mechanical systems, features, elements, and materials on exteriors.
    Management actions are actions taken with respect to warfighting 
readiness associated infrastructure (see Appendix B) as follows:
    <bullet> Associated Infrastructure: Management actions 
concerning associated infrastructure (built infrastructure and 
natural infrastructure) include real property transactions including 
leasing, acquisition, and disposal of any real property interests 
into or out of government ownership whether by purchase, lease, 
easement, transfer, sale, public land withdrawal, agricultural out 
leasing, or any other form of real property conveyance. Includes 
activities supporting establishment and use of Enhanced Use Leases 
on Army installations. Includes the transfer of national defense 
areas to the Army as new installations or for incorporation into 
existing installations.
    <bullet> Built Infrastructure: Management actions concerning 
built infrastructure include maintenance, repair, rehabilitation, 
renovation, additions, improvements, abatement and remediation of 
health and safety hazards (such as lead based paint, asbestos, among 
others), mothballing, cessation of maintenance, and demolition. 
Includes new construction including major and minor military 
construction and construction on installations by parties other than 
the Army under EULs or other authorities.
    <bullet> Natural Infrastructure: Management actions on Army land 
including all land management activities such as natural resources 
management, cultural resources management, integrated training area 
management, soil erosion control, and forestry operations. Includes 
natural resource extraction activities, such as mineral exploration, 
extraction, mining, mineral processing, timber harvesting and sales, 
and harvesting and/or collection of other resources. Includes the 
removal and/or detonation of unexploded ordnance (UXO) or discarded 
military munitions, includes the assessment, investigation, and/or 
implementation of removal or remedial actions to address releases of 
hazardous substances, pollutants, or contaminants.
    Military landscape is composed of two components--built 
infrastructure and natural infrastructure, collectively referred to 
in this program comment as associated infrastructure. The military 
landscape encompasses the entirety of each Army installation 
including the totality of the associated infrastructure. The 
military landscape is the nationwide analytical framework for 
Section 106 compliance for Army warfighting readiness activities and 
management actions on associated infrastructure. The terms military 
landscape and installation military landscape are used 
interchangeably in this program comment.
    Mitigation measure means an action that serves to resolve 
adverse effects on historic properties.
    Mothballing means an action to close and deactivate buildings 
and structures for an extended period, with the intent that the 
property would be brought back to an operational status at some 
future time.
    National Historic Landmark means historic properties formally 
designated as such by the Secretary of the Interior under the 
authority of the Historic Sites Act of 1935.
    Natural infrastructure is addressed under Army Real Property 
Category Code 9, and it incorporates all Army lands, ecosystems, 
landscapes and viewsheds, natural features, and all other natural 
resources. Natural infrastructure includes forests, wetlands, 
rivers, streams, lakes, riparian areas, deserts, grasslands, 
prairies, habitats, vegetation, soils, mineral resources, 
archaeological and geological sites and features.
    Rehabilitation means, in accordance with the Secretary's 
Standards for Rehabilitation at 36 CFR 68.3(b), the act or process 
of making possible an efficient compatible use for a property 
through repair, alterations and additions while preserving those 
portions or features that convey its historical, cultural or 
architectural values. Includes actions to improve energy efficiency, 
address obsolete, damaged, deteriorated, or defective interior and 
exterior building materials and elements, fencing, and all other 
changes to improve the quality of life, health, and safety of 
residents. Rehabilitation includes additions, exterior alterations, 
and adjacent or related construction allowed under the Secretary 
Standards for Rehabilitation (9) and (10).
    Technical feasibility means the Army's assessment of relevant 
factors to determine if an action, project, or product is suitable, 
practical, viable, and can be successfully implemented in 
consideration of warfighting readiness requirements.
    Testing or military testing means activities that evaluate 
weapons and materiel performance, safety, and reliability.
    To the maximum extent possible means implementation of actions 
to the extent capable of being carried out with reasonable effort 
considering economic and technical feasibility.
    Training or military training means activities that prepare 
units and Soldiers for combat operations.
    Tribal lands means the same as the term's definition at 36 CFR 
800.16.
    Viewshed includes all the area visible from a particular 
location, viewing point, or series of viewing points. It includes 
all visual elements and surrounding points that are in the line of 
sight from any location, viewing point, or series of viewing points 
and excludes all points and locations that are not visible and/or 
are obstructed by terrain, other natural features, human influenced 
features, man-made features, and points beyond the horizon. Includes 
all visual elements and viewsheds into historic properties and 
historic districts and out from any historic property or historic 
districts into other historic properties and districts, and all 
other landscape features. Viewsheds are addressed under this program 
comment as part of the military landscape and landscape features.
    Warfighting readiness activities means those military training, 
testing, equipping, and industrial activities specified in Appendix 
A, and management actions occurring on associated infrastructure as 
specified in Appendix B.

12.0 Appendices

    See all Appendices on the Army's website at <a href="https://www.denix.osd.mil/army-pcwr/">https://www.denix.osd.mil/army-pcwr/</a>.
    Appendix A--Warfighting Readiness Category of Undertakings
    Appendix B--Associated Infrastructure and Management Actions
    Appendix C--Design Guidelines for Pre-1941 Buildings, 
Structures, and Landscapes
    Appendix D--Building Materials Guidelines and Catalog for Pre-
1941 Buildings, Structures, And Landscapes
(END OF DOCUMENT)

(Authority: 36 CFR 800.14(e).)

    Dated: April 29, 2026.
Reid Nelson,
Executive Director.

End Notes

    \i\ ACHP Program Comment guidance--<a href="https://www.achp.gov/program_comment_questions_and_answers">https://www.achp.gov/program_comment_questions_and_answers</a>.
    \ii\ Context Study of the United States Army Quartermaster 
General Standardized Plans 1866-1942. US Army Corps of Engineers, 
Seattle District, 1997; A Study of United States Army Family Housing 
Standardized Plans, Volumes 1-5, Beth Grashof, Georgia Institute of 
Technology, 1986; National Historic Context for Department of 
Defense Installations, 1790-1940, Volumes 1-4. Referenced studies 
are at <a href="https://www.denix.osd.mil/army-pchh/">https://www.denix.osd.mil/army-pchh/</a>.
    \iii\ ACHP Program Comment guidance--<a href="https://www.achp.gov/program_comment_questions_and_answers">https://www.achp.gov/program_comment_questions_and_answers</a>.
    \iv\ For examples see Supplemental Information Briefing at 
<a href="https://www.denix.osd.mil/army-pcwr/">https://www.denix.osd.mil/army-pcwr/</a>.
    \v\ Report and Recommendations on the Application and 
Interpretation of Federal Historic Preservation Standards. Sara C. 
Bronin, Chairman ACHP, March 1, 2024. <a href="https://www.achp.gov/standardsreport">https://www.achp.gov/standardsreport</a>.
    \vi\ See the four program comments for historic Army housing at 
<a href="https://www.denix.osd.mil/army-cr/army-dod-">https://www.denix.osd.mil/army-cr/army-dod-</a> comments/. For 
additional details including annual reports for the program comments 
for Pre-1919 housing, Inter-War era housing (1919-1940) and Vietnam 
War Era housing (1963-1975) see: <a href="https://www.denix.osd.mil/army-pre1919-pchh/">https://www.denix.osd.mil/army-pre1919-pchh/</a>, https://

[[Page 24259]]

www.denix.osd.mil/army-pchhttps://www.denix.osd.mil/army-vwehh-pc/.
    \vii\ The Department of War Cold War Historic Properties 
Bibliography at <a href="https://www.denix.osd.mil/army-pcwr/">https://www.denix.osd.mil/army-pcwr/</a> is a 244-page 
annotated bibliography that contains 590 individual reports that 
document historic properties from the Cold War era for the Army and 
the Department of War. Also see: National Historic Context for 
Department of Defense Installations, 1790-1940, Volumes I-4. DoD 
Legacy Resource Management Program Project 92-0075 (1995); Military 
Training Lands Historic Context, USACERL, 2010; World War II 
Temporary Military Buildings, USACERL Technical Report CRC-93/
01,1993; World War II and the U.S. Army Mobilization Program: A 
History of 700 and 800 Series Cantonment Program, Legacy Resources 
Management Program, USACERL; Army Ammunition Production During the 
Cold War (1946-1989), US Army Environmental Command, 2009; Army 
Ammunition and Explosives Storage in the United States: 1775-1945, 
US Army Corps of Engineers, 2000; Unaccompanied Personnel Housing 
During the Cold War 1946-1989, US Army Environmental Center, 2003; 
Historic Context for DoD Facilities WWII permanent Construction, US 
Army Corps of Engineers, Baltimore District, 1997; Historic Context 
for DoD Facilities World War II Permanent Construction, US Army 
Corps of Engineers, Baltimore District, 1997; California Historic 
Military Buildings and Structures Inventory, US Army Corps of 
Engineers, Sacramento District, 2000; A Historic Context for the 
African American Military Experience, USACERL, 1998; Army historic 
contexts at <a href="https://aec.army.mil/Conservation/Cultural-Resource-Technical-Documents/">https://aec.army.mil/Conservation/Cultural-Resource-Technical-Documents/</a>.
    \viii\ Archeology and Historic Preservation; Secretary of the 
Interior's Standards and Guidelines. 48 FR 44716. Department of the 
Interior, National Park Service. September 29, 1983.
    \ix\ ibid.
    \x\ Army housing NHLs are addressed under the Army's program 
comments historic housing and are not subject to this program 
comment.
    \xi\ The Pioneer Deep Space Station, Fort Irwin, CA is managed 
by National Aeronautics and Space Administration under their NHPA 
Section 106 PA for that property and is not subject to this program 
comment.
    \xii\ Referenced nationwide NHPA compliance agreements are 
located at <a href="https://www.denix.osd.mil/army-cr/army-">https://www.denix.osd.mil/army-cr/army-</a> dod-comments. 
Also see references listed in footnote 7.
    \xiii\ The historic interior floorplans of pre-1941 built 
infrastructure have been modified and modernized by Army use over 
time; all current floorplans include rooms that were not features of 
the original design, new walls and partitions added that were not 
features of the original design, floors, walls, and ceilings cut 
through and modified to add plumbing, electrical service, and 
heating and ventilation ductwork, plaster walls replaced with 
drywall, paint and plaster removed to create a new appearance.
    \xiv\ Context Study of the United States Army Quartermaster 
General Standardized Plans 1866-1942. US Army Corps of Engineers, 
Seattle District, 1997. A Study of United States Army Family Housing 
Standardized Plans, Volumes 1-5, Beth Grashof, Georgia Institute of 
Technology, 1986. National Historic Context for Department of 
Defense Installations, 1790-1940, Volumes 1-4. Referenced studies 
are found at <a href="https://www.denix.osd.mil/army-pchh/">https://www.denix.osd.mil/army-pchh/</a>.
    \xv\ For real property acquired by the Army and incorporated 
into an existing Army installation, the Army will carry out historic 
property identification efforts when it does not have any existing 
inventory or knowledge base about the types of historic properties 
that may be present on such real property.
    \xvi\ Program Comment for the Preservation of Pre-1919 Historic 
Army Housing, Associated Buildings and Structures, and Landscape 
Features, 89 FR 50350; Program Comment for Army Inter-War Era 
Historic Housing, Assoicated Buildings and Structures, and Landscape 
Features (1919-1940), 85 FR 64491; and Program Comment for Army 
Vietnam War Era Historic Housing, Associated Buildings and 
Structures, and Lanscape Features (1963-1975), 88 FR 28573.
[FR Doc. 2026-08674 Filed 5-4-26; 8:45 am]
BILLING CODE 4310-10-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on May 5, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.