Notice2026-07126

California Department of Water Resources & Los Angeles Department of Water and Power; Notice of Revised Procedural Schedule for an Environmental Impact Statement for the Proposed Project Relicense

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
April 13, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 70 (Monday, April 13, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 70 (Monday, April 13, 2026)]
[Notices]
[Page 18847]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-07126]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2426-235]


California Department of Water Resources & Los Angeles Department 
of Water and Power; Notice of Revised Procedural Schedule for an 
Environmental Impact Statement for the Proposed Project Relicense

    On January 30, 2020, the California Department of Water Resources 
and the Los Angeles Department of Water and Power (co-licensees) filed 
an application for a new license to continue to operate and maintain 
the 1,350-megawatt South SWP Hydroelectric Project No. 2426 (South SWP 
Project). On April 30, 2025, Commission staff (staff) issued a notice 
of intent to prepare an environmental impact statement (EIS) to 
evaluate the effects of relicensing the South SWP Project. The notice 
included an anticipated schedule for issuing a Draft EIS in August 2025 
and the Final EIS by March 31, 2026.
    Staff are still evaluating the effects of relicensing the South SWP 
Project. In order for staff to fully consider all the information filed 
by the co-licensees, the procedural schedule for completing the Draft 
and Final EIS is being revised as follows. Further revisions to the 
schedule may be made as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Commission issues Draft EIS...............  August 7, 2026.
Comments on the Draft EIS due.............  September 21, 2026.
Commission issues Final EIS...............  March 31, 2027.
------------------------------------------------------------------------

    Questions regarding this notice may be directed to Quinn Emmering 
at (202) 502-6382 or <a href="/cdn-cgi/l/email-protection#f3a2869a9d9dddb69e9e96819a9d94b395968190dd949c85"><span class="__cf_email__" data-cfemail="712004181f1f5f341c1c1403181f1631171403125f161e07">[email&#160;protected]</span></a>.

(Authority: 18 CFR 2.1.)

     Dated: April 8, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-07126 Filed 4-10-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js" defer></script></body>
</html>
Indexed from Federal Register on April 13, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.