Notice2026-04874

Forza Pipeline, LLC, Bull Run Pipeline, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Forza Pipeline Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 12, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 48 (Thursday, March 12, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 48 (Thursday, March 12, 2026)]
[Notices]
[Page 12189]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-04874]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP26-34-000, CP26-35-000]


Forza Pipeline, LLC, Bull Run Pipeline, LLC; Notice of Schedule 
for the Preparation of an Environmental Assessment for the Forza 
Pipeline Project

    On December 3, 2025, Forza Pipeline LLC (Forza) and Bull Run 
Pipeline LLC (Bull Run) filed an application in Docket Nos. CP26-34-000 
and CP26-35-000 requesting a Certificate of Public Convenience and 
Necessity pursuant to Section 7(c) of the Natural Gas Act to construct 
and operate certain natural gas pipeline facilities. The proposed 
project is known as the Forza Pipeline Project (Project), and would 
entail Forza constructing and operating a new interstate natural gas 
pipeline (Line FZA-A) and certain other facilities located in New 
Mexico and Texas; as well as entering an agreement for Forza to lease 
750,000 dekatherms per day (Dth/d) of natural gas transportation from 
Bull Run.
    On December 16, 2025, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\ The EA will be 
issued for a 30-day comment period.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1771401929.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA August 28, 2026
90-day Federal Authorization Decision Deadline \2\ November 26, 2026
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    According to Forza, the Project would provide up to 750,000 Dth/d 
of firm interstate natural gas transportation service from the rapidly 
growing Delaware Basin production areas in southeastern New Mexico to 
multiple delivery points at or near the Waha Hub in Texas. Forza also 
requests authorization to enter into a lease agreement pursuant to 
which Forza would lease 750,000 Dth/d of natural gas transportation 
from Bull Run.
    The Forza Pipeline Project would consist of the following 
facilities:
    <bullet> installation of Line FZA-A, a new 35.9-mile-long, 36-inch-
diameter natural gas pipeline beginning in Lea County, New Mexico and 
terminating in Winkler County, Texas;
    <bullet> construction of a new meter station (the Desert Ram 
Junction) in Lea County, New Mexico, including the installation of a 
new riser;
    <bullet> installation of a new mainline valve along the proposed 
Line FZA-A pipeline in Loving County, Texas; and
    <bullet> installation of a new riser at the existing Wildcat 
Junction site in Winkler County, Texas.

Background

    On January 28, 2026, the Commission issued a Notice of Scoping 
Period Requesting Comments on Environmental Issues for the Proposed 
Forza Pipeline Project (Notice of Scoping). The Notice of Scoping was 
sent to affected landowners; federal, state, and local government 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; other interested parties; and local libraries 
and newspapers. In response to the Notice of Scoping as well as the 
FERC's Notice of Application for the Project, the Commission received 
comments from the U.S. Environmental Protection Agency (EPA), the Texas 
Commission on Environmental Quality (TCEQ), and one potentially 
affected landowner. The EPA stated that the EA should analyze air 
quality, water quality, and the potential for hazardous waste to be 
encountered or produced during construction. The TCEQ stated that the 
Project does not require a General Conformity determination and there 
would not be significant long-term environmental impact in terms of 
water quality and waste disposal activities. The primary issues raised 
by the landowner is the routing of the Project across the landowner's 
ranch. In addition, the commenter raises concerns about the need for 
the project, segmentation of the environmental review under the 
National Environmental Policy Act, cumulative impacts, effects to soil, 
water, and vegetation resources, effects to special status species, use 
of eminent domain, and the potential use of the right-of-way across the 
ranch by trespassers. All substantive environmental comments will be 
addressed in the EA.
    The U.S. Bureau of Land Management is a cooperating agency in the 
preparation of the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202)502-6595 or <a href="/cdn-cgi/l/email-protection#4c031c1c0c2a293e2f622b233a"><span class="__cf_email__" data-cfemail="014e515141676473622f666e77">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the FERC 
website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select ``General 
Search'' from the eLibrary menu, enter the selected date range and 
``Docket Number'' excluding the last three digits (i.e., CP26-34 and/or 
CP26-35), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at <a href="/cdn-cgi/l/email-protection#bef8fbecfdf1d0d2d7d0dbedcbceced1cccafed8dbccdd90d9d1c8"><span class="__cf_email__" data-cfemail="0b4d4e594844656762656e587e7b7b64797f4b6d6e7968256c647d">[email&#160;protected]</span></a>. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

(Authority: 18 CFR 2.1)

    Dated: March 9, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-04874 Filed 3-11-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on March 12, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.