Notice2026-04873

Egan Hub Storage, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Proposed Egan Cavern Expansion Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 12, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 48 (Thursday, March 12, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 48 (Thursday, March 12, 2026)]
[Notices]
[Pages 12184-12185]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-04873]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP26-45-000]


Egan Hub Storage, LLC; Notice of Schedule for the Preparation of 
an Environmental Assessment for the Proposed Egan Cavern Expansion 
Project

    On December 18, 2025, Egan Hub Storage, LLC filed an application in 
Docket No. CP26-45-000 requesting a Certificate of Public Convenience 
and Necessity pursuant to Section 7(c) of the Natural Gas Act to 
construct and operate certain natural gas facilities. The proposed 
project is known as the Egan Cavern Expansion Project (Project) and 
would expand operations at the existing Egan Hub natural gas storage 
facility in Acadia Parish, Louisiana through construction of two new 
salt dome storage caverns each with a working gas capacity of 8.0 
billion cubic feet (Bcf) and a base gas capacity of 4.3 Bcf.
    On January 7, 2026, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\ The EA will be 
issued for a 30-day comment period.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1772013003.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA May 22, 2026
90-day Federal Authorization Decision Deadline \2\ August 20, 2026
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Egan Hub proposes to expand operations at its existing natural gas 
storage facility in Acadia Parish, Louisiana. Specifically, at its 
existing facility, Egan Hub would construct and operate two new salt 
dome storage caverns each with a working gas capacity of 8.0 Bcf and a 
base gas capacity of 4.3 Bcf; a new leaching and dewatering facility; 
new on-site compression facilities; and one new freshwater supply well. 
A new 0.75-mile-long 18-inch-diameter freshwater pipeline would also be 
installed to connect the freshwater well to the leaching and dewatering 
facility; a 0.25-mile-long, 16-inch-diameter freshwater pipeline and a 
0.25-mile-long, 16-inch-diameter brine pipeline would be constructed to 
connect the new caverns to the new leaching and dewatering system; and 
two new 0.25-mile-long 16-inch-diameter gas pipelines would be 
constructed to tie-in the new caverns to the existing facility.
    The project also includes construction of a new saltwater disposal 
well at a separate site located 1.5 miles southwest of the Egan 
Facility which would be tied into an existing brine disposal pipeline 
via installation of 485 feet total of 16-, 12-, and 8-inch-diameter 
pipeline.

Background

    On January 22, 2026, the Commission issued a Notice of Scoping 
Period Requesting Comments on Environmental Issues for the Proposed 
Egan Cavern Expansion Project (Notice of Scoping). The Notice of 
Scoping was sent to affected landowners; federal, state, and local 
government agencies; elected officials; environmental and public 
interest groups; Native American tribes; other interested parties; and 
local libraries and newspapers. In response to the Notice of Scoping, 
the Commission received comments from the United States Environmental 
Protection Agency, the Alabama-Coushatta Tribe of Texas, and one 
landowner. The primary issues raised by the commenters are

[[Page 12185]]

project permitting, contents of the environmental document, and the 
lateral extent of the proposed caverns. All substantive comments will 
be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#2e617e7e6e484b5c4d00494158"><span class="__cf_email__" data-cfemail="67283737270102150449000811">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the FERC 
website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select ``General 
Search'' from the eLibrary menu, enter the selected date range and 
``Docket Number'' excluding the last three digits (i.e., CP26-45), and 
follow the instructions. For assistance with access to eLibrary, the 
helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
<a href="/cdn-cgi/l/email-protection#397f7c6b7a76575550575c6a4c4949564b4d795f5c4b5a175e564f"><span class="__cf_email__" data-cfemail="1e585b4c5d51707277707b4d6b6e6e716c6a5e787b6c7d30797168">[email&#160;protected]</span></a>. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

(Authority: 18 CFR 2.1)

    Dated: March 9, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-04873 Filed 3-11-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>