Notice2026-04872

Natural Gas Pipeline Company of America LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Texas-Arkansas Power Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 12, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 48 (Thursday, March 12, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 48 (Thursday, March 12, 2026)]
[Notices]
[Pages 12185-12186]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-04872]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP26-46-000]


Natural Gas Pipeline Company of America LLC; Notice of Schedule 
for the Preparation of an Environmental Assessment for the Texas-
Arkansas Power Project

    On December 18, 2025, Natural Gas Pipeline Company of America LLC 
(Natural) filed an application in Docket No. CP26-46-000 requesting a 
Certificate of Public Convenience and Necessity pursuant to Section 
7(c) and Authorization pursuant to Section 7(b) of the Natural Gas Act 
to construct, operate, and abandon certain natural gas facilities. The 
proposed project is known as the Texas-Arkansas Power Project 
(Project), and would support a precedent agreement with Arkansas 
Electric Cooperative Corporation (AECC) to transport up to 400,000 
dekatherms per day of existing unsubscribed capacity and additional 
capacity on Natural's Gulf Coast Mainline. The purpose of the Project 
is to supply AECC with this capacity to power new and existing natural 
gas fired electric generation plants in northern Texas and Arkansas.
    On January 7, 2026, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1771492431.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA September 4, 2026
90-day Federal Authorization Decision Deadline \2\ December 3, 2026
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Texas-Arkansas Power Project would consist of the following 
facilities, all at Natural's existing Compressor Station 308 in 
Randolph County, Arkansas:
    <bullet> abandon in place nine reciprocating compressor units, with 
a combined rating of 30,850-horsepower;
    <bullet> install two new 20,482-horsepower Solar Turbines Titan 130 
centrifugal units;
    <bullet> modify plant yard piping and auxiliary equipment, 
including new inlet filter separators, and gas cooling and other minor 
equipment; and
    <bullet> construct a new, permanent access road and driveway.

Background

    On February 3, the Commission issued a Notice of Scoping Period 
Requesting Comments on Environmental Issues for the Proposed Texas-
Arkansas Power Project Notice of Scoping). The Notice of Scoping was 
sent to affected landowners; federal, state, and local government 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; other interested parties; and local libraries 
and newspapers. In response to the Notice of Scoping, the Commission 
received comments from AECC, and the Quapaw Nation. No issues were 
raised as the AECC comments were in support of the project and the 
Quapaw Nation comments that the project is not likely to affect its 
properties of cultural or sacred significance. All substantive comments 
will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#410e111101272433226f262e37"><span class="__cf_email__" data-cfemail="09465959496f6c7b6a276e667f">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the FERC 
website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select ``General 
Search'' from the eLibrary menu, enter the selected date range and 
``Docket Number'' excluding the last three digits (i.e., CP26-46), and 
follow the instructions. For assistance with access to eLibrary, the 
helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
<a href="/cdn-cgi/l/email-protection#4d0b081f0e0223212423281e383d3d223f390d2b283f2e632a223b"><span class="__cf_email__" data-cfemail="dd9b988f9e92b3b1b4b3b88ea8adadb2afa99dbbb8afbef3bab2ab">[email&#160;protected]</span></a>. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

(Authority: 18 CFR 2.1)


[[Page 12186]]


    Dated: March 9, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-04872 Filed 3-11-26; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on March 12, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.