Notice2026-04638

Certification Notice-261; Notice of Filing of Self-Certification of Coal Capability Under the Powerplant and Industrial Fuel Use Act

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 10, 2026

Issuing agencies

Energy Department

Abstract

On May 11, 2021, Long Ridge Energy Generation LLC (Long Ridge), as owner and operator of a new baseload electric generating powerplant, submitted a coal capability self-certification to the Department of Energy (DOE). The Powerplant and Industrial Fuel Use Act of 1978 (FUA), as amended, and regulations thereunder require DOE to publish a notice of filing of self-certification in the Federal Register.

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 46 (Tuesday, March 10, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 46 (Tuesday, March 10, 2026)]
[Notices]
[Page 11538]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-04638]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY


Certification Notice--261; Notice of Filing of Self-Certification 
of Coal Capability Under the Powerplant and Industrial Fuel Use Act

AGENCY: Office of Electricity, Department of Energy.

ACTION: Notice of filing.

-----------------------------------------------------------------------

SUMMARY: On May 11, 2021, Long Ridge Energy Generation LLC (Long 
Ridge), as owner and operator of a new baseload electric generating 
powerplant, submitted a coal capability self-certification to the 
Department of Energy (DOE). The Powerplant and Industrial Fuel Use Act 
of 1978 (FUA), as amended, and regulations thereunder require DOE to 
publish a notice of filing of self-certification in the Federal 
Register.

ADDRESSES: Copies of coal capability self-certification filings are 
available for public inspection, upon request, by contacting the Office 
of Electricity by electronic mail to <a href="/cdn-cgi/l/email-protection#fdb891989e898f949e948984d3b8858d928f898ebd958cd3999298d39a928b"><span class="__cf_email__" data-cfemail="0e4b626b6d7a7c676d677a77204b767e617c7a7d4e667f206a616b20696178">[email&#160;protected]</span></a>.

FOR FURTHER INFORMATION CONTACT: Marina Fennel at (240) 702-6156, 
<a href="/cdn-cgi/l/email-protection#73361f161007011a101a070a5d360b031c010700331b025d171c165d141c05"><span class="__cf_email__" data-cfemail="5d1831383e292f343e3429247318252d322f292e1d352c73393238733a322b">[email&#160;protected]</span></a>.

SUPPLEMENTARY INFORMATION: On May 11, 2021, Long Ridge, as owner and 
operator of a new baseload electric generating powerplant, submitted a 
coal capability self-certification to the DOE pursuant to section 
201(d) of the Powerplant and Industrial Fuel Use Act of 1978 (FUA), as 
amended (42 U.S.C. 8311(d)), and DOE regulations in 10 CFR 501.61(a). 
The FUA and regulations thereunder require DOE to publish a notice of 
filing of self-certification in the Federal Register. See 42 U.S.C. 
8311(d)(1); 10 CFR 501.61(c). Section 201(a) of the FUA provides that 
``no new base load electric powerplant may be constructed or operated 
without the capability to use coal or another alternate fuel as a 
primary energy source.'' 42 U.S.C. 8311(a). Pursuant to section 201(d) 
of the FUA, in order to meet the requirement of coal capability, the 
owner or operator of such a facility proposing to use natural gas or 
petroleum as its primary energy source shall certify to the Secretary 
of Energy (Secretary) prior to construction, or prior to operation as a 
base load electric powerplant, that such powerplant has the capability 
to use coal or another alternate fuel. See 42 U.S.C. 8311(d)(1). Such 
certification establishes compliance with FUA section 201(a) as of the 
date it is filed with the Secretary. Id.; 10 CFR 501.61(b). The 
following owner of a proposed new baseload electric generating 
powerplant has filed a self-certification of coal-capability with DOE 
pursuant to FUA section 201(d) and in accordance with DOE regulations 
at 10 CFR 501.61:

Owner: Long Ridge Energy Generation LLC
Design Capacity: Approximately 485 megawatts
Fuel To Be Used: Natural gas
Plant Location: 43840 State Route 7, Hannibal, OH 43931
In-Service Date: Testing began May 2021

Signing Authority

    This document of the Department of Energy was signed on February 6, 
2026, by Catherine Jereza, Assistant Secretary, Office of Electricity, 
pursuant to delegated authority from the Secretary of Energy. That 
document with the original signature and date is maintained by DOE. For 
administrative purposes only, and in compliance with requirements of 
the Office of the Federal Register, the undersigned DOE Federal 
Register Liaison Officer has been authorized to sign and submit the 
document in electronic format for publication, as an official document 
of the Department of Energy. This administrative process in no way 
alters the legal effect of this document upon publication in the 
Federal Register.

    Signed in Washington, DC on March 6, 2026.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
[FR Doc. 2026-04638 Filed 3-9-26; 8:45 am]
BILLING CODE 6450-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on March 10, 2026.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.