Notice2026-03013

Brown Bear II Hydro, Inc.; Notice Granting Extension of Time

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
February 17, 2026

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 91 Issue 31 (Tuesday, February 17, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 31 (Tuesday, February 17, 2026)]
[Notices]
[Page 7282]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-03013]



[[Page 7282]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3428-205]


Brown Bear II Hydro, Inc.; Notice Granting Extension of Time

    On January 14, 2026, the Commission issued a notice that the 
Worumbo Hydroelectric Project No. 3428 (project) was ready for 
environmental analysis and solicited motions to intervene, protests, 
comments, recommendations, preliminary terms and conditions, and 
preliminary fishway prescriptions (REA notice). On January 27, 2026, 
Brown Bear II Hydro, Inc. (Brown Bear) filed a request to extend the 
deadlines established in the REA notice by 74 days. Brown Bear states 
that additional time is needed to complete its ongoing evaluation of 
fish passage alternatives at the project in consultation with the 
licensing stakeholders. In support of its request, Brown Bear included 
correspondence from the National Marine Fisheries Service (NMFS), the 
U.S. Fish and Wildlife Service (FWS), and the Maine Department of 
Marine Resources. NMFS and FWS also filed separate letters on January 
29, 2026, and February 3, 2026, respectively, in support of the request 
to extend the deadlines established in the REA notice.
    The information provided by Brown Bear and supported by 
stakeholders indicates that evaluation of the fish passage alternatives 
is nearly complete. Because the results of the evaluation could inform 
Brown Bear's and the stakeholders' responses to the REA notice, this 
notice extends the deadlines established in the January 14 REA notice 
by 74 days. Accordingly, the application will be processed according to 
the schedule below. Revisions to the schedule may be made, as 
appropriate.

------------------------------------------------------------------------
                  Milestone                             Due date
------------------------------------------------------------------------
Final amendments.............................  April 28, 2026.
Filing of motions to intervene, protests,      May 29, 2026.
 comments, recommendations, preliminary terms
 and conditions, and preliminary
 prescriptions.
Filing a copy of the water quality             May 29, 2026.
 certification; a copy of the request for
 certification, including proof of the date
 on which the certifying agency received the
 request; or evidence of a waiver of water
 quality certification.
Filing of reply comments.....................  July 13, 2026.
------------------------------------------------------------------------


(Authority: 18 CFR 2.1.)

     Dated: February 10, 2026.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2026-03013 Filed 2-13-26; 8:45 am]