Notice2026-00476
Argent LNG, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Planned Argent LNG Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
January 13, 2026
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 91 Issue 8 (Tuesday, January 13, 2026)</title>
</head>
<body><pre>
[Federal Register Volume 91, Number 8 (Tuesday, January 13, 2026)]
[Notices]
[Pages 1296-1298]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2026-00476]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF25-11-000]
Argent LNG, LLC; Notice of Scoping Period Requesting Comments on
Environmental Issues for the Planned Argent LNG Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document that will discuss
the environmental impacts of the Argent LNG Project involving
construction and operation of facilities by Argent LNG, LLC (Argent
LNG) in Lafourche Parish, Louisiana. The Commission will use this
environmental document in its decision-making process to determine
whether the project is in the public interest.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of an authorization. This gathering of public input is
referred to as ``scoping.'' The main goal of the scoping process is to
focus the analysis in the environmental document on the important
environmental issues. Additional information about the Commission's
NEPA process is described below in the NEPA Process and Environmental
Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on February 9, 2026. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all written comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on September 8, 2025, you will need to file
those comments in Docket No. PF25-11-000 to ensure they are considered.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
Landowner topics of interest are available for viewing on the FERC
website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or <a href="/cdn-cgi/l/email-protection#4c0a293e2f0322202522291f393c3c233e380c2a293e2f622b233a"><span class="__cf_email__" data-cfemail="e0a6859283af8e8c898e85b39590908f9294a086859283ce878f96">[email protected]</span></a>.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (PF25-
11-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, MD 20852.
Additionally, the Commission offers a free service called
eSubscription, which
[[Page 1297]]
makes it easy to stay informed of all issuances and submittals
regarding the dockets/projects to which you subscribe. These instant
email notifications are the fastest way to receive notification and
provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to FERC Online to register
for eSubscription.
For public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, contact the Office
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#98d7c8c8d8fefdeafbb6fff7ee"><span class="__cf_email__" data-cfemail="9cd3ccccdcfaf9eeffb2fbf3ea">[email protected]</span></a>.
Summary of the Planned Project
Argent LNG plans to site, construct and operate a liquefied natural
gas (LNG) production and export facility along the northwest shore of
the Port Fourchon Belle Pass Channel (Belle Pass Channel) in Lafourche
Parish, Louisiana. The Argent LNG Project would produce up to 25
million ton per annum of LNG for export to U.S. trading partners.
The Argent LNG Project would consist of the following facilities:
<bullet> pretreatment systems;
<bullet> natural gas liquefication units;
<bullet> two aboveground full-containment LNG storage tanks;
<bullet> a 350-megawatt natural gas-fired power generation
facility;
<bullet> marine facilities and two new marine berths capable of
accommodating LNG carriers of up to 260,000 cubic meters; and
<bullet> a total of 0.7 mile of new dual 16-inch-diameter natural
gas interconnect pipelines.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
<a href="http://www.ferc.gov">www.ferc.gov</a> using the link called ``eLibrary.'' For instructions on
connecting to eLibrary, refer to the last page of this notice. For
assistance, contact FERC at <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="0c4a495e4f4362606562695f797c7c637e784c6a697e6f226b637a">[email protected]</a> or call toll
free, (886) 208-3676 or TTY (202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
The new LNG export terminal would be constructed on approximately
269.9 acres within a larger 885.5-acre leased property. The project
also includes Marine Facilities that would impact a total of 147.1
acres (127.4 acres within the leased site and 19.7 acres within the
Belle Pass Channel), and a total of 0.7 mile of new dual 16-inch-
diameter natural gas interconnect pipelines that would tie into the
existing Kinetica interstate pipeline system located near the site.
Following construction, Argent LNG would maintain about 445 acres for
permanent operation of the project's facilities; the remaining acreage
would be restored.
NEPA Process and the Environmental Document
Any environmental document issued by Commission staff will discuss
impacts that could occur as a result of the construction and operation
of the planned project under the relevant general resource areas:
<bullet> geology and soils;
<bullet> water resources and wetlands;
<bullet> vegetation and wildlife;
<bullet> threatened and endangered species;
<bullet> cultural resources;
<bullet> socioeconomics;
<bullet> land use;
<bullet> air quality and noise; and
<bullet> reliability and safety.
Commission staff have already identified several issues that
deserve attention based on a preliminary review of the planned
facilities and the environmental information provided by Argent LNG.
This preliminary list of issues may change based on your comments and
our analysis:
<bullet> marine transportation;
<bullet> socioeconomic effects; and
<bullet> facility construction and effects on water resources,
wetlands, and marine species.
Commission staff will also evaluate reasonable alternatives to the
planned project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Although no formal application has been filed, Commission staff
have already initiated a NEPA review under the Commission's pre-filing
process. The purpose of the pre-filing process is to encourage early
involvement of interested stakeholders and to identify and resolve
issues before the Commission receives an application. As part of the
pre-filing review, Commission staff will contact federal and state
agencies to discuss their involvement in the scoping process and the
preparation of the environmental document.
If a formal application is filed, Commission staff will then
determine whether to prepare an Environmental Assessment (EA) or an
Environmental Impact Statement (EIS). The EA or the EIS will present
Commission staff's independent analysis of the environmental issues. If
Commission staff prepares an EA, a Notice of Schedule for the
Preparation of an Environmental Assessment will be issued. The EA may
be issued for an allotted public comment period. The Commission would
consider timely comments on the EA before making its determination on
the proposed project. If Commission staff prepares an EIS, a Notice of
Intent to Prepare an EIS/Notice of Schedule will be issued once an
application is filed, which will open an additional public comment
period. Staff will then prepare a draft EIS that will be issued for
public comment. Commission staff will consider all timely comments
received during the comment period on the draft EIS, and revise the
document, as necessary, before issuing a final EIS. Any EA or draft and
final EIS will be available in electronic format in the public record
through eLibrary \2\ and the Commission's natural gas environmental
documents web page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). If eSubscribed, you will receive
instant email notification when the environmental document is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues related to this project to formally cooperate in
the preparation of the environmental document.\3\ Agencies that would
like to request cooperating agency status should follow the
instructions for filing comments provided under the Public
Participation section of this notice.
---------------------------------------------------------------------------
\3\ Cooperating agency responsibilities are addressed in Section
107(a)(3) of NEPA (42 U.S. Code Sec. 4336(a)(3)).
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\
[[Page 1298]]
The environmental document for this project will document our findings
on the impacts on historic properties and summarize the status of
consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the planned project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to <a href="/cdn-cgi/l/email-protection#2b6c4a587b5944414e485f6a4f4f594e585868434a454c4e6b4d4e5948054c445d"><span class="__cf_email__" data-cfemail="6126001231130e0b040215200505130412122209000f060421070413024f060e17">[email protected]</span></a> stating your
request. You must include the docket number PF25-11-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments.
OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Becoming an Intervenor
Once Argent LNG files its application with the Commission, you may
want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Only intervenors have the right to seek
rehearing of the Commission's decision and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in the proceeding by filing a request to
intervene pursuant to Rule 214 of the Commission's Rules of Practice
and Procedures (18 CFR 385.214). Motions to intervene are more fully
described at <a href="https://www.ferc.gov/how-intervene">https://www.ferc.gov/how-intervene</a>. Please note that the
Commission will not accept requests for intervenor status at this time.
You must wait until the Commission receives a formal application for
the project, after which the Commission will issue a public notice that
establishes an intervention deadline.
Additional Information
Additional information about the project is available on the FERC
website (<a href="http://www.ferc.gov">www.ferc.gov</a>) using the eLibrary link. Click on the eLibrary
link, click on ``General Search'' and enter the docket number in the
``Docket Number'' field. Be sure you have selected an appropriate date
range. For assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#fabc9f8899b5949693949fa98f8a8a95888eba9c9f8899d49d958c"><span class="__cf_email__" data-cfemail="9cdaf9eeffd3f2f0f5f2f9cfe9ececf3eee8dcfaf9eeffb2fbf3ea">[email protected]</span></a> or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at <a href="https://www.ferc.gov/news-events/events">https://www.ferc.gov/news-events/events</a> along with
other related information.
Authority: 18 CFR 2.1.
Dated: January 8, 2026.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2026-00476 Filed 1-12-26; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on January 13, 2026.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.