Notice2025-23711
Columbia Gulf Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Pulaski Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
December 23, 2025
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 244 (Tuesday, December 23, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 244 (Tuesday, December 23, 2025)]
[Notices]
[Pages 60090-60093]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-23711]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP26-11-000]
Columbia Gulf Transmission, LLC; Notice of Scoping Period
Requesting Comments on Environmental Issues for the Proposed Pulaski
Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document that will discuss
the environmental impacts of the Pulaski Project involving construction
and operation of facilities
[[Page 60091]]
by Columbia Gulf Transmission, LLC (Columbia) in Lincoln County and
Pulaski County, Kentucky. The Commission will use this environmental
document in its decision-making process to determine whether the
project is in the public convenience and necessity.
On November 24, 2025, FERC staff issued a Notice of Scoping Period
Requesting Comments on Environmental Issues for the Pulaski Project and
Notice of Public Scoping Session. It was brought to FERC staff
attention that the notice may not have been mailed properly to the
environmental mailing list. This notice is being sent to an updated
environmental mailing list and extends the scoping period for the
project.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. This
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on January 20, 2025. Comments may be
submitted in written. Further details on how to submit comments are
provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on October 15, 2025, you will need to file
those comments in Docket No. CP26-11-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law. The Commission does
not subsequently grant, exercise, or oversee the exercise of that
eminent domain authority. The courts have exclusive authority to handle
eminent domain cases; the Commission has no jurisdiction over these
matters.
Columbia provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' which addresses typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the Natural Gas, Landowner Topics link.
Public Participation
Please carefully follow these instructions so that your comments
are properly recorded. The Commission encourages electronic filing of
comments and has staff available to assist you at (866) 208-3676 or
<a href="/cdn-cgi/l/email-protection#80c6e5f2e3cfeeece9eee5d3f5f0f0eff2f4c0e6e5f2e3aee7eff6"><span class="__cf_email__" data-cfemail="04426176674b6a686d6a61577174746b767044626176672a636b72">[email protected]</span></a>.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP26-
11-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, MD 20852.
It is important to note that the Commission provides equal
consideration to all comments received.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
For public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, contact the Office
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#cc839c9c8caaa9beafe2aba3ba"><span class="__cf_email__" data-cfemail="08475858486e6d7a6b266f677e">[email protected]</span></a>.
Summary of the Proposed Project
Columbia proposes to install and operate 41.3 miles of new 30-inch-
diameter greenfield natural gas pipeline from Lincoln County Kentucky
to the new South Somerset Delivery Meter Station located in Pulaski
County, Kentucky, with additional aboveground facilities. The Pulaski
Project would provide about 253 million standard cubic feet of natural
gas per day to the John S. Cooper Power Station in Pulaski County,
Kentucky. According to Columbia, its project would service its new and
existing generation resources.
[[Page 60092]]
The Pulaski Project would consist of the following facilities:
<bullet> 41.3 miles of new 30-inch-diameter greenfield natural gas
pipeline;
<bullet> a proposed tie-in to the Columbia Mainline in Lincoln
County, Kentucky, including a new launcher/receiver and bidirectional
pig \1\ trap;
---------------------------------------------------------------------------
\1\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
<bullet> a new meter and regulator station designated as the South
Somerset Delivery Meter Station in Pulaski County, Kentucky, including
a tie-in to East Kentucky Power Cooperative's (EKPC's) John S. Cooper
Power Station, a new launcher/receiver, and a bidirectional pig trap;
and
<bullet> four new mainline valves.
The general location of the project facilities is shown in appendix
1.
Land Requirements for Construction
Construction of the proposed facilities would disturb about 657.2
acres of land for the aboveground facilities and the pipeline.
Following construction, Columbia would maintain about 254.0 acres for
permanent operation of the project's facilities; the remaining acreage
would be restored and revert to former uses. About 27 percent of the
proposed pipeline route parallels existing EKPC and/or Kentucky
Utilities Company rights-of-way.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the construction and operation
of the proposed project under the relevant general resource areas:
<bullet> geology and soils;
<bullet> water resources and wetlands;
<bullet> vegetation and wildlife;
<bullet> threatened and endangered species;
<bullet> cultural resources;
<bullet> land use;
<bullet> socioeconomics;
<bullet> air quality and noise; and
<bullet> reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued, which will open up an
additional comment period. Staff will then prepare a draft EIS which
will be issued for public comment. Commission staff will consider all
timely comments received during the comment period on the draft EIS and
revise the document, as necessary, before issuing a final EIS. Any EA
or draft and final EIS will be available in electronic format in the
public record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). If eSubscribed, you
will receive instant email notification when the environmental document
is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ Cooperating agency responsibilities are addressed in Section
107(a)(3) of NEPA (42 U.S.C. 4336(a)(3)).
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to <a href="/cdn-cgi/l/email-protection#1354726043617c7976706752777761766060507b727d747653757661703d747c65"><span class="__cf_email__" data-cfemail="4106203211332e2b242235002525332432320229202f262401272433226f262e37">[email protected]</span></a> stating your
request. You must include the docket number CP26-11-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments.
OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the FERC
website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the eLibrary link. Click on the eLibrary
link, click on ``General Search'' and enter the docket number in the
``Docket Number'' field. Be sure you have selected an appropriate date
range. For assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#adebc8dfcee2c3c1c4c3c8fed8ddddc2dfd9edcbc8dfce83cac2db"><span class="__cf_email__" data-cfemail="3a7c5f485975545653545f694f4a4a55484e7a5c5f4859145d554c">[email protected]</span></a> or (866)
[[Page 60093]]
208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also
provides access to the texts of all formal documents issued by the
Commission, such as orders, notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at <a href="https://www.ferc.gov/news-events/events">https://www.ferc.gov/news-events/events</a> along with
other related information.
Authority: 18 CFR 2.1.
Dated: December 18, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-23711 Filed 12-22-25; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on December 23, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.