Notice2025-22551

Algonquin Gas Transmission, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Cape Cod Canal Pipeline Relocation Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
December 11, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 236 (Thursday, December 11, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 236 (Thursday, December 11, 2025)]
[Notices]
[Pages 57460-57461]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-22551]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP25-552-000]


Algonquin Gas Transmission, LLC; Notice of Schedule for the 
Preparation of an Environmental Assessment for the Cape Cod Canal 
Pipeline Relocation Project

    On September 29, 2025, Algonquin Gas Transmission, LLC (Algonquin) 
filed an application in Docket No. CP25-552 requesting a Certificate of 
Public Convenience and Necessity pursuant to Section 7(c) and 
Authorization pursuant to Section 7(b) of the Natural Gas Act to 
construct and operate, and to abandon certain natural gas pipeline 
facilities. The proposed project is known as the Cape Cod Canal 
Pipeline Relocation Project (Project). Algonquin would modify its 
existing interstate natural gas pipeline system facilities within the 
Town of Bourne, Barnstable County, Massachusetts, to accommodate the 
planned replacement of the Bourne Bridge and Sagamore Bridge by the 
Cape Cod Bridges Program while continuing to provide uninterrupted 
natural gas service to the National Grid distribution system on both 
sides of the Cape Cod Canal.\1\
---------------------------------------------------------------------------

    \1\ The U.S. Army Corps of Engineers owns and operates the 
Bourne and Sagamore Bridges and the Cape Cod Canal and is jointly 
implementing the Cape Cod Bridges Program with the Massachusetts 
Department of Transportation.
---------------------------------------------------------------------------

    On October 8, 2025, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\2\ The EA will be 
issued for a 30-day comment period.
---------------------------------------------------------------------------

    \2\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1763050824.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA--April 17, 2026
90-day Federal Authorization Decision Deadline \3\--July 16, 2026
---------------------------------------------------------------------------

    \3\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.
---------------------------------------------------------------------------

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Project would consist of the following facilities and 
activities:
    <bullet> installation of approximately 3.0 miles of 16-inch-
diameter and

[[Page 57461]]

approximately 2.2 miles of 18-inch-diameter pipeline to replace 
National Grid's existing pipelines currently attached to the existing 
Bourne and Sagamore Bridges;
    <bullet> relocation of approximately 0.4 mile of existing 8-inch-
diameter and 0.7 mile of 18-inch-diameter pipelines adjacent to the 
existing Sagamore and Bourne Bridges;
    <bullet> abandonment by removal or in place of approximately 3.0 
miles of existing 8-inch-diameter and 0.5 mile of 18-inch-diameter 
pipelines;
    <bullet> removal and relocation of two existing mainland meter and 
regulating (M&R) stations--Sagamore and Bourne--that are within the 
footprint of the Cape Cod Bridges Program workspace; and
    <bullet> installation of two new M&R stations--Pave Paws Road and 
Bourne Rotary.

Background

    On April 3, 2025, the Commission issued a Notice of Scoping Period 
Requesting Comments on Environmental Issues for the Planned Cape Cod 
Canal Bridge Relocation Project and Notice of Public Scoping Session 
(Notice of Scoping).\4\ The Notice of Scoping was issued during the 
pre-filing review of the Project in Docket No. PF25-4 and was sent to 
affected landowners; federal, state, and local government agencies; 
elected officials; environmental and public interest groups; Native 
American tribes; other interested parties; and local libraries and 
newspapers. In response to the Notice of Scoping, the Commission 
received comments from the Cape Cod Chamber of Commerce, the Cape & 
Islands Bridges Coalition, the Berkshire Environmental Action Team, one 
landowner, and 18 other individuals. The primary and relevant issues 
raised by the commenters were the purpose and need for the Project; 
effects to sensitive resources in the Project area (e.g., wetlands, 
sole source aquifers, and listed species); effects to local traffic and 
noise during construction; and effects to air quality during 
operations. All substantive comments will be addressed in the EA.
---------------------------------------------------------------------------

    \4\ During pre-filing, Algonquin changed the name of the FERC-
jurisdictional Project to avoid confusion with replacement of the 
Bourne and Sagamore Bridges planned by the Cape Cod Bridges Program.
---------------------------------------------------------------------------

    The U.S. Army Corps of Engineers, U.S. Environmental Protection 
Agency, and the Massachusetts Army National Guard are cooperating 
agencies in the preparation of the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    For public inquiries and assistance with making filings such as 
interventions, comments, or request for rehearing contact the Office of 
Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#67283737270102150449000811"><span class="__cf_email__" data-cfemail="b7f8e7e7f7d1d2c5d499d0d8c1">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the FERC 
website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select ``General 
Search'' from the eLibrary menu, enter the selected date range and 
``Docket Number'' excluding the last three digits (i.e., CP25-552), and 
follow the instructions. For assistance with access to eLibrary, the 
helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
<a href="/cdn-cgi/l/email-protection#0d4b485f4e4263616463685e787d7d627f794d6b687f6e236a627b"><span class="__cf_email__" data-cfemail="31777463727e5f5d585f54624441415e434571575443521f565e47">[email&#160;protected]</span></a>. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

(Authority: 18 CFR 2.1)

    Dated: December 8, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-22551 Filed 12-10-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on December 11, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.